Hampshire County Council

Executive Member - Environment

10 September 2001

Regeneration of Older Urban Areas Programme -
Emsworth Railway Station

Report of the County Planning Officer

Item 18

Contact: Simon Cramp, ext 6723

1. Summary

1.1 The following decision is sought:

2. Reason

2.1 To enable award of contract and completion of scheme.

3. Other Options Considered and Rejected

3.1 Reduction of quality of materials and reduction of scheme extent - rejected as they would not achieve programme objectives.

4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer consulted - Not Applicable.

5. Dispensation granted by the Standards Committee - Not Applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not Applicable.

Approved by: Date:

Councillor K B Estlin

7. Introduction

7.1 Funding for improvements at Emsworth Railway Station was set aside in the 1997-99 and 1999-2001 Regeneration of Older Urban Areas (ROUA) programmes. The County Council's investment of £85,000 has been matched by £50,000 from Railtrack and £5,000 from Havant Borough Council. A £20,000 contribution from the operator cannot be confirmed because the future of the franchise remains in doubt. Officers are working to secure this contribution for future improvements at the station.

7.2 The development of the scheme, as reported to Members previously, has been delayed by a number of factors, including:

8. Current Situation

8.1 A contract has been let for the repainting of the station buildings in a traditional colour, and this is due to commence in September. Tenders have been received for the main works to the frontage. However, the lowest tender of £147,850, plus 10% contingencies, is £30,650 in excess of the remaining budget of £132,000. The lowest tender is also more than 10% in excess of the pre-tender estimate of £124,750.

8.2 The reasons for these discrepancies are:

9. Conclusion

9.1 The ROUA programme maintains a contingency sum in order to provide some flexibility in responding to changing circumstances on individual projects. This facility is particularly important when the programme is working on complex projects where it is difficult to determine all the factors at the outset and the cost plan has been set before detailed proposals have been developed.

9.2 Approval is now sought for an increase in the budget for Emsworth Railway Station in the sum of £30,650, using the available contingency funding within the programme, and for the award of the contract to the lowest tenderer, Mackley Construction.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

6673/SC