Hampshire County Council

Executive Member - Environment

12 December 2001

Off site highway contribution - St George Barracks South, Gosport

Report of the County Surveyor

Item 10

Contact: Laura McCulloch, ext 6901

1. Summary

1.1 The following decisions are sought:

2. Reason

2.1 To secure an appropriate level of financial contribution towards transport improvements in the area.

3. Other Options Considered and Rejected - Not applicable.

4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer consulted - Not applicable.

5. Dispensation granted by the Standards Committee - Not applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.

Approved by: Date:

Councillor K B Estlin

7. Introduction

7.1 A planning application has been submitted by Fairview New Homes (Gosport) Limited to Gosport Borough Council for a mixed use development at St George Barracks South, Gosport. The site totals 3.5 hectares and is located immediately to the north-west of Gosport town centre and within 600 metres of the Gosport/Portsmouth passenger ferry terminal (see attached location plan).

7.2 The site is currently vacant and contains former barracks accommodation, a parade ground and other ancillary buildings. There are a number of buildings within the site, four of which are Grade II listed. The whole of the site falls within the St George Barracks South Conservation Area.

7.3 The application is for the development of the site for mixed use, comprising:

7.4 The County Council and the Borough Council support this form of development in this location and have resolved to grant approval, subject to the conclusion of appropriate legal Agreements.

7.5 The local Member, Councillor Geddes, raises no objection in principle to the proposals.

8. Transport Proposals

8.1 The approved development brief for this site identifies access being provided from the A32 Mumby Road, Clarence Road and Ordnance Road.

8.2 Gosport Borough Council's Cycling Strategy identifies Mumby Road as a cycle route that links to a cycle path which runs along the disused railway line from Spring Garden Lane.

8.3 The pedestrian routes will be to the east of the site, serving the town centre and the ferry. Also, with the completion of the Royal Clarence Yard development to the north of the site, a link across Mumby Road will be established. These links will be served by the combined cycle and pedestrian access points on to Mumby Road, Clarence Road and Ordnance Road, which are separate to the vehicular access points.

8.4 In accordance with current planning guidance the development framework seeks to minimise the overall requirement for car parking areas, provide covered cycle parking facilities and encourage access to the site by other transport modes.

8.5 The developer has agreed to make a financial contribution towards the improvement of cycleway and/or public transport along the A32 corridor, including the Light Rapid Transit (LRT) system or other transportation measures which may reasonably benefit the site.

9. Financial Implications

9.1 In the event of planning permission being implemented, the developer has agreed to make a financial contribution of £150,000 towards the improvement of cycleway and/or public transport along the A32 corridor, including the LRT system, or other transportation measures which may reasonably benefit the site.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

St George Barracks South, Gosport

File 6/3/11/27

County Surveyor's Department

Development Control

6766/LJM