Hampshire County Council
Asset Management Sub Committee
11 May 2000
Review of Financial and Related Systems - Update
Report of the County Treasurer
 
Contact: Jon Pittam, ext 7400
1.    Introduction
 
1.1   The Sub-Committee at its meeting on 4 November 1999 considered a report
      outlining the findings and recommendations of the PriceWaterhouseCoopers
      review of the County Council's financial and related systems.
 
1.2   Following the recommendations made by PriceWaterhouseCoopers the report
      sought approval to:
 
      *  Develop a strategic plan to replace the financial and related systems
         incrementally from April 2001 to March 2004 with an enterprise
         resource planning (ERP) system.
 
      *  Commence procurement procedures using the Central Government and
         Telecommunications Agency's (CCTA) G-Cat and S-Cat catalogues.
 
      *  Make the replacement of the payroll/human resources system a priority
         for implementation by April 2001.
 
      *  Develop an Invest to Save approach for consideration in the 2000/01
         budget strategy.
 
      *  Continue negotiations with neighbouring authorities on a possible
         consortium approach to procurement, implementation, training and
         support, and report further.
 
      *  Appoint consultants to assist with the procurement and implementation
         process.
 
1.3   This report sets out progress since November 1999.
 
2.    Project Structure and Management
 
2.1   A project management structure has been put in place and resources
      assigned to the project.  Currently the project is being resourced
      entirely by internal staff.  However, these project groups will be
      supplemented with external consultants once an implementation partner
      has been selected.  The resource implications are significant but at
      this stage of the project it is difficult to determine the precise
      resource requirements.  Once negotiations with shortlisted suppliers get
      underway it will be possible to refine the resource estimates and
      consider arrangements for how this will be managed.
 
3.    The Procurement Approach
 
3.1   The original approach outlined in the report to the Sub-Committee in
      November 1999 was to use G-Cat and S-Cat catalogues to procure the ERP
      software.  After further investigation and discussions with the
      Council's Head of Supplies and Procurement it was decided not to proceed
      with this option.  The G-Cat charge for providing procurement support
      would have been 7.5% of the total contract price yet would not have
      provided the significant benefits in terms of reduced timescales and
      administration that were originally anticipated.
 
3.2   A standard EU procurement process, using the negotiated route, was
      started in December.  A notice of requirements requesting expressions of
      interest was posted in the Official Journal of the European Community
      ((OJEC).
 
4.    Timetable
 
4.1   Due to the change in the procurement route the timetable has slipped
      slightly.  The aim remains for the replacement payroll system to be
      implemented and live by June 2001.  Indications from potential suppliers
      and implementation partners suggest this is still a realistic and
      achievable target.
 
4.2   The importance of replacing the payroll system by June 2001 has been
      emphasised by a recent problem in updating National Insurance bands for
      2000/01 within the existing system.  Though the problem was successfully
      resolved it did highlight how vulnerable the council is should a problem
      occur which cannot be solved in-house.  The MVS operating system in
      which the payroll runs is now so far behind current versions, and used
      by so few organisations, that knowledge and experience in the product is
      very scarce.  In addition, supplier support for the payroll application
      software is expected to be withdrawn soon, probably around the middle of
      next year.
 
5.    The Longlisting Process
 
5.1   Seventeen responses to the OJEC notice were received.  These were
      evaluated against pre-defined criteria.  Of the seventeen, eight
      successfully met the required criteria.
 
5.2   The longlisted suppliers all attended an individual briefing session
      that included a presentation outlining the council's approach to the
      process and the procurement timetable.  They were also issued with a
      document setting out the high level specification of requirements which
      they had to respond to by 25 February 2000.  Technical discussions have
      also been held with each of the software suppliers to ensure there were
      no problems with their solution fitting in with the County Council's
      corporate IT strategy.
 
5.3   As a direct result of the technical discussions one supplier
      partnership, JD Edwards, Rebus and Deloitte & Touche, pulled.  ITNET
      also decided to withdraw.
 
6.    The Shortlisting Process
 
6.1   Six responses to the specification of requirements were received.  The
      Project Team has evaluated the responses against the selection criteria.
      It is recommended that four implementation partners go through to the
      shortlist stage.  Of the four, three are proposing a solution using
      Oracle Financials software and one recommends the implementation of
      SAP's R/3 system.  The recommended shortlist is attached as an Appendix.
 
7.    The Consortium
 
7.1   Negotiations with neighbouring authorities regarding a possible joint
      project have continued.  Due to differences in timetables and priorities
      however it was not possible to reach agreement on a way forward early
      enough to allow the County Council to meet its key target date for
      replacing the payroll system.
 
8.    Next Steps
 
8.1   Now that the shortlist of suppliers has been agreed detailed
      negotiations and evaluation of the software products will begin.  This
      process is planned to take until mid May when suppliers will be asked
      for 'best and final' offers and a preferred supplier is chosen.
 
8.2   A report requesting approval to appoint the preferred supplier will be
      brought to the Asset Management Sub-Committee's July meeting.
 
8.3   Indicative budget figures provided by suppliers so far as in line with
      the figures included in the last report.  A number of financing options
      have also been put forward for consideration.  A lot of work needs to be
      done with the shortlisted suppliers to refine plans and requirements to
      allow suppliers to produce their final bids and for costs and benefits
      to be confirmed.
 
8.4   Further analysis will be done on the financing options between now and
      May, continuing with the strategy of Invest to Save outlined in the last
      report.  The business case for drawdown from the Invest to Save fund to
      finance the initial stages of the procurement will be included in the
      next report.
 
9.    Recommendations
 
That the switch to the EU procurement process using the negotiated route be
approved and continued.
 
That the Asset Management Sub-Committee at its July meeting receives a further
report on the results of the evaluation of shortlisted suppliers together with
a recommendation for preferred supplier for both software and implementation
support and a cost benefit analysis and proposed financing option for the
recommended solution.
 
 
 
                                                                      Appendix
 
 
                    Review of Financial and Related Systems
 
 
          Shortlisted Implementation Partners and Software Suppliers
 
 
Implementation Partner        Recommended Software Supplier
 
 
PriceWaterhouseCoopers        SAP R/3
 
KPMG                          Oracle Applications (including Financials)
 
Andersen                      Oracle Applications (including Financials)
 
Oracle                              Oracle Applications (including Financials)

Up: Top of this page       Home: Hantsweb Homepage