Hampshire Housing Supply Action Plan 2004

At the Strategic Planning Joint Advisory Panel meeting on 10 March 2004 the Hampshire authorities agreed to produce an action plan setting out the steps to be taken over the next year to raise housing supply and instil greater confidence in future forecasts of that supply. The Plan has been prepared by Hampshire County Council, Portsmouth City Council and Southampton City Council in conjunction with the Government Office and is split into two types of actions - outcomes and processes:

Success against the targets set out as outcome actions will be reported to the Strategic Authorities' Joint Advisory Panel (JAP) meeting in Spring 2005 and will, along with the conclusions arising from the Policy H4 Monitoring Paper 2005, help inform JAPs deliberations on whether a release of the reserve is required. In striving to meet the agreed targets Councils are not expected to compromise on their design standards. The Outcome Actions are weighted and, if the Hampshire authorities fall short on actions OA1 - OA10, this (in tandem with the conclusions of the Monitoring Paper) is likely to lead officers to recommend to Members that a release of reserve housing, on the basis of approved Supplementary Planning Guidance, would be necessary. If a release was not made under these circumstances, Members would be placing themselves in conflict with the Minister of State for Planning and Housing.

The Action Plan was approved by the Strategic Planning Authorities (Hampshire County Council, Portsmouth City Council and Southampton City Council) on 7 June 2004 and has been passed to the Minister for his consideration. Although the Plan has an end date of 31 March 2005 it is likely that it will need to be revised and rolled forward early next year in response to progress on outcomes and the results of the Policy H4 Monitoring Paper 2005.

Outcome Actions

Action

By

Date

Target

OA1

Increase county-wide supply of outline and full planning permissions

Local planning authorities

30 September 2004 (and updated for March 2005)

County-wide supply of outline and full planning permissions raised to 3.5 years (adjusted RPG requirement) as an interim step to achieving a 5 year supply by March 2006

OA2

Increase county-wide supply full planning permissions (including reserve matter approvals)

Local planning authorities

30 September 2004 (and updated for March 2005)

County-wide supply of full planning permissions raised to 2.5 years (adjusted RPG requirement) as an interim step to achieving a 3 year supply by March 2006

OA3

Ensure that district estimates of total supply April 2004 - March 2007 are not higher than the number of dwellings approved by LPA.

Strategic and local planning authorities

30 September 2004 (and updated for March 2005)

Estimated supply must equal or be less than number of dwellings approved (including those subject to Sect 106 agreements and Gov't referrals). At least two thirds of approved dwellings should be full details.

OA4

Keep to local plan/development document timetable. (see also OA15)

Local planning authorities/GOSE/PINS

For timetable see Appendix 1 & 2

No slippage in local plan/development document timetable

OA5

Resolution to grant outline consent for the whole of the allocated MDAs at West of Waterlooville and Andover subject to appropriate agreements, receipt of a favourable report from Local Plan Inquiry Inspector and in accordance with an agreed masterplan. Note: this action excludes the West of Waterlooville reserve allocation, which will be made in accordance Structure Plan policy.

Winchester City Council, Havant Borough Council and Test Valley Borough Council

31 December 2004

Action implemented.

OA6

Outline planning permission granted for the whole of the major development at North Basingstoke (Popley and Popley Fields) and Aldershot Sustainable Urban Extension

Basingstoke and Deane Borough Council and Rushmoor Borough Council

31 December 2004

Action implemented.

OA7

Resolution to grant outline consent for housing sites in the 2nd deposit local plan that have been supported by an Inquiry Inspector and are needed to meet housing supply requirements, subject to appropriate agreements. Note: this action excludes reserve allocations - their release will be made in accordance Structure Plan policy.

Local planning authorities

31 December 2004

Resolution made.

OA8

Notification to owners/ developers of sites affected by resolution in OA7.

Local planning authorities who have received Inspectors Report

Within 3 months of publication of Report

Notification sent to affected landowners and developers advising them of resolution and inviting planning applications that comply with policy in PPG3 on location, density, mix and provision of affordable housing.

OA9

Implement actions in district specific Action Plans already agreed or updated between districts and GOSE for 2004

Basingstoke, East Hampshire, Eastleigh, Hart and Winchester Councils and GOSE

31 December 2004

Actions implemented.

OA10

Improve performance on all major planning applications to meet ODPM PSA target

Local planning authorities

31 December 2004

(i) DC performance for most recent quarter meets target of 60% within 13 weeks or

(ii) DC performance meets district specific target set by ODPM. (iii) Where (i)and (ii) not yet met, performance for last 3 quarters shows improvement.

OA11

Preparation of, and consultation on, development briefs for sites allocated in 2nd deposit local plans where appropriate

Local planning authorities

Within 6 months of end of local plan inquiry

Development briefs prepared.

OA12

Work co-operatively with Government agencies such as the Highways Agency, English Nature and Environment Agency to overcome issues arising from consultations on planning applications. GOSE to provide assistance on resolving these issues where appropriate.

Referral of initial tranche of affected sites by local planning authorities explaining nature of issue to GOSE by end July 2004 for action

Ongoing

GOSE to report back on progress on individual sites by end September 2004

OA13

Work with Government departments, local authorities and agencies to release land allocated for housing in local plans.

Referral of initial tranche of affected sites by local planning authorities explaining issue to GOSE by end July 2004 for action. HCC/ other local authorities to expedite development on own land.

Ongoing

GOSE to report back on progress on individual sites by end September 2004

HCC to report on progress with sites in its ownership by end September 2004.

OA14

Encourage Housing Corporation and Regional Housing Board to maintain funding levels for RSLs. Housing Authorities to report on delays, difficulties and loss of affordable housing attributable to shortage of funding.

Referral of initial tranche of affected sites by local housing authorities explaining issue to GOSE by end July 2004 for action

Ongoing

GOSE to report back on progress on individual sites by end September 2004

OA15

Write to the Planning Inspectorate to expedite Local Plan Inquiries and the production of Inspector's reports

GOSE and Chair of HIPOG

May 2004

Letter sent to Planning Inspectorate

OA16

GOSE to take account of need for housing in application of the `Greenfield Directive' so that key housing sites required to meet Hampshire's housing needs are not unduly delayed.

GOSE

Ongoing

No applications called in on sites allocated in adopted and 2nd deposit local plans that are required to meet housing target, unless significant conflict with national or regional policy

OA17

Raise with the House Builders Federation the need for applicants to submit complete, good quality applications and explore potential for a protocol.

GOSE.

May 2004

House Builders Federation agree to advise its Members of the need to submit complete, good quality applications

OA18

JAP and GOSE to receive an update on progress towards all above outcomes at each JAP meeting

Strategic planning authorities

March 2005

Report submitted.

Process Actions

 

Action

By

Completion Date

PA1

Develop methodology to establish confidence levels for different sources of supply. Undertake limited consultation (district councils, HBF and CPRE) and approve prior to preparation of 2005 Monitoring Paper. Feed in conclusions of local plan inspectors as they are published.

Strategic planning authorities

August 2004

PA2

Analyse completions 2003 - 2004 against forecast. Input conclusions into 2005 forecast.

Strategic planning authorities

July 2004

PA3

Analyse housebuilders forecast of completions 2003 - 2004 against actual. Contact those housebuilders where completions are at variance with forecast to find out why. Input conclusions into HCC 2005 forecast.

Strategic planning authorities

June 2004

PA4

Approach HBF to request housebuilders to provide forecasts of future completions as an input into HCC 2005 forecast.

Strategic planning authorities

July 2004

PA5

Test urban capacity studies/ urban housing potential that Local Plan Inspectors have yet to report on for consistency with SEERA `Good Practice Guide'. If any found to be over optimistic, the adjustment applied to the supply from that particular district will be increased in the Policy H4 Monitoring Paper "adjusted supply" figures.

Strategic planning authorities

September 2004

PA6

Test the evidence that planning permissions for dwellings on urban capacity sites continue to be granted at, or above, the rates required in the Monitoring Paper - at district and county level

Strategic planning authorities

July - August 2004

PA7

Test the delivery rates that can be expected from very large sites (@ 500 dwellings+).

Strategic planning authorities

September 2004

PA8

Review and re-assess delivery rates of reserve sites if released in 2005 and 2006

Strategic planning authorities and local planning authorities

mid October 2004

PA9

Bring forward publication date of Policy H4 Monitoring Paper 2005 to 19 November 2004.

Include housing trajectories covering remaining plan period for each local planning authority

Strategic planning authorities and local planning authorities

19 November 2004

PA10

Undertake assessment as per Policy H4 SPG addendum to identify where release could be made if Policy H4 Monitoring Paper 2005 adjusted supply is below or within 5% of RPG requirement, or if there has been a significant failure to deliver key actions OA 1 to 10.

Strategic planning authorities

Publish Paper for consultation

17 December 2004 - 28 January 2005

Outcome to be reported to JAP at its Spring 2005 meeting.

PA11

Work together on implementing the Action Plan

Strategic planning authorities, GOSE and Local planning authorities

Regular meeting / exchange of information.

Reports to HIPOG and Development Plans/Development Control sub-groups as appropriate

Appendix 1 Local Plan Timetable

Authority

Public Inquiry start

Inspectors report

Draft Mods published

Adoption

Basingstoke and Deane

Oct 2004

Dec 2005

Feb 2006

July 2006

East Hants

April 2003

Jan 2005

June 2005

Feb 2006

Eastleigh

April 2004

Jan 2005

May 2005

Dec 2005

Fareham

See below

Gosport

Feb 2005

Dec 2005

March 2006

July 2006

Hart

See below

Havant

Held

April 2004

Aug 2004

Feb 2005

New Forest

Held

Oct 2004

Jan 2005

May 2005

Portsmouth

Held

Dec 03

June 04

Oct 04

Rushmoor

See below

Southampton

Held

Dec 04

March 05

Oct 05

Test Valley

Sept 2004

Nov 2005

Feb 2006

July 2006

Winchester

June 2004

Aug 2005

Nov 2005

May 2006

Appendix 2 Local Development Documents Timetable

Consultation on preferred options and proposals

Date for Submission to SoS

Consultation on submission document

Estimated date for adoption

Fareham

July 2005

Nov 2005

Dec 2005

Jan 2007

Hart

April 2005

July 2005

July 2005

Feb 2006

Rushmoor

Feb 2005

Oct 2005

Oct 2005

Feb 2007