Local Development Frameworks (LDFs) in Hampshire
District-by-District Timetable for Preparation of Documents (updated Jun. 08)
N.B. the dates below are indicative only - many Local Development Schemes (LDSs) are currently under review.
For further details, SPD timetables, or confirmation of dates please contact the relevant Council directly (contact details are given in the table below). For general enquiries please contact HCC's John Miles on 01962 846760, or john.miles@hants.gov.uk .
Council/Local Development Documents |
Issues and Options consultation |
Preferred Options consultation |
Submission to Secretary of State |
Public Examination |
Adoption |
Contact Details& Changes Anticipated |
BASINGSTOKE & DEANE BC | ||||||
Core Strategy |
March 08 |
Elizabeth Alexander liz.alexander@basingstoke.gov.uk Revised LDS not yet approved by GOSE. Dates are to be confirmed. | ||||
Site Allocations |
Nov - Dec 08 |
Feb - Mar 10 |
Nov 2010 |
May - July 11 |
Mar 2012 | |
Development Management |
June - July 08 |
Feb - Mar 09 |
Nov 2009 |
April 2010 |
Dec 2010 | |
EAST HAMPSHIRE DC | ||||||
Core Strategy |
Feb- May 2008 |
Jun 2008 |
Apr 2009 |
Feb 2010 |
Sept 2010 |
Alistair Speirs alistair.speirs@easthants.gov.uk Revised LDS not yet approved by GOSE. Dates are to be confirmed |
Development Allocations |
Sept 2008 |
July 2009 |
Oct 2010 |
July 2011 |
Jan 2012 | |
EASTLEIGH BC | ||||||
South Hampshire Strategic Employment Zone Action Area Plan |
May 2007 |
Nov 2008 |
June 2009 |
Jan 2010 |
Jun 2010 |
Julia Norman Revised LDS not yet approved by GOSE. Dates are to be confirmed. |
Core Strategy |
Oct 2008 |
June 2009 |
Jan 2010 |
Jul 2010 |
Feb 2011 | |
Town Centre Action Area Plan (AAP) |
May 2007 |
Late 2008 |
Jun 2009 |
Jan 2010 |
Jul 2010 | |
Policies & Designations |
Sept 2009 |
Feb 2010 |
Sept 2010 |
Mar 2011 |
Nov 2011 | |
Site Allocations |
Sept 2009 |
Feb 2010 |
Sept 2010 |
Mar 2011 |
Nov 2011 | |
Strategic Development Area Area Action Plan |
?Mar 2010 |
?Sept 2010 |
?Mar 2011 |
?Sept 2011 |
?May 2012 |
Programme to be agreed with Winchester CC |
FAREHAM BC | ||||||
Core Strategy |
Jan - Mar 07 |
July-Aug 08 |
Jan 2009 |
Aug 2009 |
Feb-Mar 2010 |
Linda Jewell GOSE approved 30.03.07 |
Site Allocations |
Jan - Mar 07 |
Jul - Aug 08 |
Apr 2010 |
Nov 2010 |
May-June 2011 | |
Town Centre Area Action Plan |
Jan - Mar 07 |
Jul - Aug 08 |
May 2010 |
Dec 2010 |
Jun-July 2011 | |
Development Control Policies |
Nov 08 - Aug 09 |
Jan - Feb 2010 |
Jan 2011 |
August 2011 |
Feb - Mar 2012 | |
GOSPORT BC | ||||||
Core Strategy |
Dec 06 - Feb 07 |
Late 08 |
June 2008 |
Dec 08-Jan 09 |
Sep 2009 |
Chris Payne Revised LDS approved by GOSE. Dates are to be confirmed. |
Site Allocations & Distribution |
May - June 08 |
Jan - Feb 09 |
Aug 09 |
Apr-May 2010 |
Dec 2010 | |
Development Control DPD |
Nov-Dec 09 |
Jul-Aug 2010 |
Jan 2011 |
Jul-Aug 2011 |
Mar 2012 |
|
HART DC | ||||||
Core Strategy |
Jan - Jun 06 |
Aug - Sept 06 |
Feb 2009 |
Jul-Aug 2008 |
Mar 2009 |
Revised LDS not yet approved by GOSE. Dates in need of amendment. |
Development Control Policies |
Jan - Jun 06 |
May - Jul 08 |
Apr 2009 |
Dec 09 - Jan 10 |
Jul 2010 | |
Site Specific Allocations |
Apr-May 08 |
Nov-Dec 08 |
Jun-Jul 09 |
Feb-Mar 10 |
Sep 2010 | |
HAVANT BC | ||||||
Core Strategy |
Mar09 - May09 |
Mar09 - May09 |
Jul/Aug 09 |
Nov/Dec 09 |
June 2010 |
Ray Bryant |
Development Allocations |
Mar 08 |
Jul-Sep 2008 |
Oct 2009 |
August 2010 |
November 2010 | |
NEW FOREST DC | ||||||
Core Strategy |
Nov 06 - Jan 07 |
Nov-Dec 07 |
Late 2008 |
Nov 2008 |
May 2009 |
Graham Ashworth Timetable reflects LDS brought into effect beginning of May 2007 Dates for DPDs to be revised |
Sites and Designations DPD |
Jan - Feb 2008 |
Sept - Oct 08 |
May 2009 |
Nov 2009 |
June 2010 | |
Development Control Policies DPD |
Jan - Feb 2008 |
Sept - Oct 2008 |
May 2009 |
Nov 2009 |
June 2010 | |
Totton Town Centre DPD |
Sept - Oct 2008 |
Feb - Mar 2009 |
Sept 2009 |
March 2010 |
Oct 2010 | |
NEW FOREST NATIONAL PARK AUTHORITY | ||||||
Core Strategy |
Nov 06 - Jan 07 |
John Clements john.clements@newforestnpa.gov.uk LDS brought into effect 23 Feb 07. Core Strategy no longer joint with New Forest DC. LDS to be revised. | ||||
Sites and Designations DPD |
Sept - Oct 08 |
May 2009 |
Nov 2009 |
June 2010 | ||
Development Control Policies DPD |
Sep - Oct 2007 |
May - Jun 2008 |
May 2009 |
Nov 2009 |
June 2010 | |
PORTSMOUTH CC | ||||||
Core Strategy |
Oct - Nov 07 |
Aug- Sep 08 |
Mar - Apr 09 |
Sept 2009 |
April 2010 |
Vicky Piper vicky.piper@portsmouthcc.gov.uk Gemma Jephcott (until Sept 07) gemma.jephcott@portsmouthcc.gov.uk Revised LDS approved by GOSE.2.08.07 *Revised dates for Somerstown AAP not yet agreed with GOSE |
Site Allocations |
Mar -Apr 09 |
Feb - Mar 2010 |
Sept - Oct 2010 |
March 2011 |
November 2011 | |
Somerstown AAP* |
Nov - Dec 05 |
Aug - Sept 08 |
Oct - Nov 08 |
May 2009 |
Dec 2009 | |
The Hard AAP |
Oct - Nov 08 |
Sept - Oct 09 |
Aug - Sept 2010 |
Feb 2011 |
Sept 2011 | |
Port Solent AAP |
Oct - Nov 08 |
Sept - Oct 09 |
Aug - Sept 2010 |
Feb 2011 |
Sept 2011 | |
Southsea Town Centre AAP |
Aug - Sept 05 |
Feb - Mar 06 |
Sept - Oct 06 |
March 2007 |
Sept 2007 | |
RUSHMOOR BC | ||||||
Core Strategy |
Sept 2008 |
April 2009* |
Sept 2009 |
April 2010 |
Sept 2010 |
Tim Richings Revised dates to be confirmed * Pre-submission consultation |
Farnborough airport area action plan |
Sept 2008 |
Sept 2009 |
January 2011 |
Sept 2011 |
February 2012 | |
SOUTHAMPTON CC | ||||||
Core Strategy |
May - July 06 |
Oct-Dec 06 |
Late 2008 |
Nov 2008 |
July 2009 |
Helen Pearce |
City Centre AAP |
Apr - May 07 |
Sep 08 -Jan 09 |
Jan 2010 |
May 2010 |
Jan 2011 | |
Development Control Policies |
Oct 2008 |
May 2010 |
Sept 2010 |
May 2011 | ||
Allocations |
Nov - Dec 07 |
Mar 2010 |
Jul 2010 |
Sept 2010 | ||
Proposals Map |
Ongoing - |
change with |
adoption of |
DPDs |
||
Affordable Housing |
Deleted - |
now in core |
strategy |
|||
TEST VALLEY BC | ||||||
Core Strategy |
Feb-Mar 08 |
Late 2008 |
Apr 2009 |
Dec 09 |
Steve Lees | |
Andover AAP |
Dec 2010 |
July 2011 |
July 2011 |
Oct 2012 | ||
Southern Test Valley AAP |
March 2010 |
Nov 2010 |
Nov 2010 |
Aug 2012 | ||
Settlement Boundaries AAP |
Jan 2010 |
July 2010 |
Nov 2011 | |||
WINCHESTER CITY COUNCIL | ||||||
Core Strategy |
Jan-Feb 08 |
Jun-Aug 2008 |
Sept 2008 |
Apr-May 2009 |
Dec 2009 |
Steve Opacic |
Development Provision & Allocations |
Feb - Mar 2009 |
Feb - Mar 2010 |
Jul 2010 |
Jan - Feb 10 |
Sep 2011 | |
HAMPSHIRE COUNTY COUNCIL | ||||||
Core Strategy |
Sep - Nov 05 |
May - Jun 06 |
May 2006 |
Jan - Feb 07 |
July 2007 |
Adrian Flavell * Indicative - subject to confirmation. |
Hampshire Minerals Plan |
Late 06-Early 07 |
Oct-Dec 07 |
Oct 2008 |
July -Aug 09 |
Dec 2009 | |
Hampshire Waste Management Plan |
Aug 06-Jun 07 |
Jun - Aug 08* |
Dec 2008 |
June - Aug 09 |
Mar 2010 | |