The traffic management is necessary to safely reduce the number of lanes on the motorway from four to three. This ensures the safety of passing motorway users and construction staff working on the embankments, particularly around the area of a new underpass which will be delivered by the scheme. The lane reduction and 50mph speed limit on this section of the M27 will be in place for approximately 12 months whilst the project is underway.
Improvements are being made to the M27 Junction 10 to support the development of Welborne Garden Village, a new community of up to 6000 homes just outside Fareham in Hampshire and to provide easier access to the M27.
Hampshire County Council is delivering the scheme, working closely with National Highways. The scheme is being funded by Buckland Group, the developer of Welborne Garden Village and by Homes England.
Road users are advised that lane reductions and closures can be subject to changes at short notice.
Lane closure dates:
M27 eastbound and westbound overnight: Lanes 1, 2 and 3 closures will take place as required (Lane 4 will remain open for traffic):
• Monday 17 to Thursday 20 March between 9pm and 6am
• Monday 24 to Wednesday 26 March between 9pm and 6am
Additional closures between 9pm and 6am:
• Sunday 30 March – westbound lane 4 closure for drainage surveys
• Monday 31 March – eastbound lane closures 1,2 and 3 for barrier installation
• Tuesday 1 April – westbound lane closures 1, 2 and 3 for barrier installation
• Monday 7 April to Wednesday 9 April - westbound lane closures 1 and 2 for the delivery of large metal construction materials
Full overnight closure dates:
Eastbound
M27 eastbound full overnight closure between junctions 9 and 11 (between Whiteley and Fareham) will take place:
• Sunday 30 March between 9pm and 6am (Monday 31 March) for one night
• Thursday 3 April between 9pm and 6am (Friday 4 April) for one night as a contingency if needed
The works will enable the closure of lane 1 between the junctions, along with the installation of a 50-mph speed restriction, and safety cameras.
A signed diversion will direct road users between junctions 9 and 11 via the A27.
When the junction 10 eastbound entry slip road is closed, a signed diversion will direct road users between junctions 10 and 11 via the A27.
Westbound
M27 westbound full overnight closure between junctions 11 and 9 (between Fareham and Whiteley) will take place:
• Monday 31 March between 9pm and 6am (Tuesday 1 April) for one night.
• Friday 4 April between 9pm and 6am (Saturday 5 April) for one night as a contingency if needed.
The works will enable the closure of lane 1 between the junctions, along with the installation of a 50-mph speed restriction, and safety cameras.
A signed diversion will direct road users between junctions 11 and 9 via the A27.
For more information about the diversion routes for the overnight closures visit: https://one.network/
General updates will be available on the scheme webpages: https://www.hants.gov.uk/transport/transportschemes/m27junction10
Travel alert: M27 Junction 10 Improvement Scheme – planned overnight lane reduction and full closures in March and April
As part of the ongoing M27 Junction 10 improvement works to support the Welborne Garden Village development near Fareham, some full and partial overnight lane closures on the M27 are required in March and April. Some of these closures will be limited to between Junctions 9 and 10, while others will extend between Junctions 9 and 11
read ( words)