Eclipse Busway - Completion of Phase I

The Eclipse Busway is being extended 1km south to Rowner Road, Gosport.

Last update: June 2020

Latest update

Hampshire County Council have appointed Dyer and Butler and the start of works was postponed due to the impact of COVID-19 and is now planned to commence on 15 June 2020 for an estimated duration of 18 months.

Advance works will take place over the coming weeks in preparation for the start of the works. These works will be carried out by Dyer and Butler to establish site offices and access at Gosport Leisure Centre. This work will create temporary fencing, parking, offices and associated welfare facilities, which will be removed upon completion of the scheme when the field will be re-instated. There should be no disruption on the local road network from these works.

Dyer and Butler will be maintaining social distancing and following national guidelines with all work carried out in line with the Construction Leadership Council’s Site Operation Procedures, which is based on Public Health England guidance.

Advanced Works

An Advanced Works Package and Drainage Maintenance works (south of Rowner Road) has now been completed in preparation for the Main Works Contract. This included removal of the old rail track, vegetation clearance, Statutory Undertaker apparatus diversion and installation of ducting, and maintenance to the existing drainage run.

 The approved technical plan for the revised Rowner Road junction can be viewed here.

A further £1.4m of additional funding from the Department for Transport's Transforming Cities Fund, has been successfully secured to meet the additional cost of constructing the alternative southern junction. Approval to progress this revised scheme was given at the Executive Member for Environment and Transport Decision Day on 23rd April 2019.

Scheme overview

Hampshire County Council successfully bid for funding from the National Productivity Investment Fund (NPIF) to complete the outstanding section of the Eclipse Busway in Summer 2017 and a further £1.4m of additional funding for the alternative southern junction that retains Rowner Road bridge, was secured in partnership with Portsmouth City Council from the Department for Transport's Transforming Cities Fund in March 2019.  Approval to progress this revised scheme was given at the Executive Member for Environment and Transport Decision Day on 23rd April 2019.

The Eclipse Busway provides a priority public transport route connecting Fareham in the north to Gosport in the south. The existing route, completed in 2012, is largely off-road with a dedicated section following the line of a former railway. The proposed 1km southern extension will follow the disused railway corridor between Tichborne Way / Hutfield Link and Rowner Road in Gosport and forms one component of a wider package of measures for Improving Access to Fareham and Gosport. The existing route is judged a great success and proposals have long existed to extend the route so that it benefits a wider catchment area.

The scheme objectives are:

  • To reduce journey time delay and peak hour congestion on and off the Gosport peninsula.
  • To remove the transport barriers to growth and encourage investment and regeneration on the peninsula.
  • To improve connectivity and provide additional network resilience across the peninsula.

Once complete, the Eclipse service operator First Hampshire and Dorset will invest in a fleet of seventeen new high specification, low-emission buses and introduce a new Eclipse Extra service to the nearby Daedalus Enterprise Zone. The renewal of the bus fleet will also reduce emissions to help address known air quality issues in the Fareham Air Quality Management Area (AQMAs).

Planning permission was granted in April 2019 to amend the southern section of the approved scheme to provide a new junction arrangement at Rowner Road. This enhanced scheme includes a new ramp to connect the busway to Rowner Road. This change will allow Rowner Road bridge to be retained along with the existing shared-use route for pedestrians and cyclists under Rowner Road. 

Drainage Maintenance works (south of Rowner Road) has now been completed in preparation for the Main Works Contract. This also included the removal of the old rail track, vegetation clearance, Statutory Undertaker apparatus diversion and installation of ducting, and maintenance to the existing drainage run.

 The approved technical plan for the revised Rowner Road junction can be viewed here. 

Exhibition plans update

Due to current guidance regarding COVID-19 and social distancing it is no longer possible to hold a public exhibition to coincide with the start of works. An overview of the scheme and plans setting out the works can be accessed here.

A public event was held on Tuesday 2nd July at Bridgemary School, the event gave an opportunity to view the details of the design and discuss the enhanced scheme with members of the project team.

Please view the exhibition plans.

Eclipse Busway route map

Eclipses Service routes and maps

Contact us
Address
Economy, Transport and Environment Department
Hampshire County Council
The Castle

Winchester
SO23 8UD