TEMPORARY ROAD CLOSURE – PEACH HILL LANE, WINCHESTER

The following road will be temporarily closed at some point during the next 6 months with works expected to start on the 5th January 2026.

Start

Monday

5

January

2026

End

Sunday

5

July

2026

Highways – Temporary Road Closure from Hampshire County Council in Winchester area

NOTICE IS HEREBY GIVEN that Hampshire County Council has made an order under S.14 of the Road Traffic Regulation Act 1984, to allow works to be carried out on or near the road. 

ROAD TO BE CLOSED: that part of Peach Hill Lane between its junction with Hacks Lane and its junction with Crawley Road

ALTERNATIVE ROUTE: Peach Hill Lane, Stockbridge Road, Crawley Road, Peach Hill Lane  

DURATION OF ORDER: from 5th January 2026 for a period of 6 months or until completion of the works whichever is sooner.  (Notwithstanding, it is expected that the closure will be required for no longer than 2 days, working between the hours of 09:00-16:00)

The road closure has been granted by Hampshire County Council to facilitate works for Artemis to carry out repair works. If there are any queries or enquires regarding this Order, please contact: [email protected]

Artemis will provide reasonable facilities to allow access to adjacent premises and provide notice to those directly affected while the work is being carried out. 

A copy of this notice can be viewed: www.hants.gov.uk/publicnotices. 

PATRICK BLOGG Director of Universal Services, The Castle, Winchester, SO23 8UD
 