APPENDIX 2
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
|
|
|
|
|
|
|
Andover Strategy Area (ATS) |
|
|
|
|
1 |
Weyhill Road/Salisbury Road |
660 |
Feb 01 |
Nov 01 |
First stage includes Toucan crossing part of Safer Routes to School. |
2/3 |
Cycles and Pedestrians |
50 |
n/a |
started |
Contribution to Weyhill-Portway and cycle facilities at Andover Station. |
4 |
Safer Routes to School |
50 |
n/a |
Nov 01 |
£40,000 for Toucan (see above). £10,000 for Tollgate Road - Test Valley Borough Council developing. |
5 |
Weyhill to Portway Cycles |
60 |
Jan 02 |
Mar 02 |
Test Valley Borough Council progressing scheme. |
X1 |
King Arthur's Way |
80 |
tbc |
tbc |
Street lighting scheme added to programme October 2001. |
|
|
|
|
|
|
|
Basingstoke Strategy (BEST) |
|
|
|
|
6 to 17 |
Proposed amended programme (see elsewhere in report) |
|
|
|
(Total SCA kept within programme limits.) |
|
|
|
|
|
|
|
Central Hampshire (CHARTS) |
|
|
|
|
|
|
|
|
|
|
18/23 |
A325 Corridor Bordon/Whitehill |
190 |
n/a |
- |
Contribution to increased costs on extended Whitehill scheme for 2000/01. |
19/24/ X2 |
Petersfield/B2070 |
420 (+365) |
- |
- |
Continuing improvements programme in Petersfield. Most schemes deferred to 2002/03, including B2070 (to follow Tesco opening effects' assessment). High Street element of Country Towns scheme (added Oct 2001) may start early 2002. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
20 |
Hockley/Wickham Corridor |
20 |
- |
02/03 |
Schemes being developed. |
21 |
Sustainable Access to Area of Outstanding Natural Beauty |
25 |
- |
02/03 |
Schemes being developed. |
22 |
Alton Town Centre |
50 |
- |
02/03 |
Strategy being developed. |
25 |
Village Initiatives |
40 |
- |
02/03 |
Consultants working on schemes for West Meon and Hambledon. |
26 |
CHARTS ITS |
20 |
- |
Oct 01 |
Scheme being developed. |
27 |
Modal Integration |
60 |
Jul 01 |
early 02 |
Initial work on cycling facilities at Petersfield Station. |
28 |
Winchester to Eastleigh cycles |
50 |
n/a |
Jan 02 |
Contribution to Otterbourne scheme. |
29 |
Four Marks-Holybourne (Alton Cycles) |
120 |
Dec 01 |
Feb 02 |
Schemes being developed. |
30 |
TAPESTRY |
70 |
Jan 02 |
Feb 02 |
Re-assigned to Air Quality. |
31 |
CHARTS Safer Routes to School |
50 |
- |
Started |
Schemes identified in Purbrook Heath, Denmead, Colden Common and West Meon. |
|
|
|
|
|
|
|
Coastal Towns (CTTS) |
|
|
|
|
32/33 CTTS1 |
Avenue Road/Southampton Road Pedestrian Facilities |
115 (inc mtce) |
- |
early 02 |
CTTS/Safer Routes to School scheme. |
32/33 CTTS2 |
Lymington Quay |
50 |
- |
Oct 01 |
Contribution to New Forest District Council project - completed. |
32/33 CTTS3 |
New Milton Town Centre |
160 (+70 c/f) |
- |
02/03 |
Deferred for scheme development and local consultation (includes Station Road pedestrian project). |
32/33 CTTS4 |
Milford-on-Sea |
15 |
- |
Tbc |
New Forest District Council progressing. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
|
North East Hampshire Strategy (NEHTS) |
|
|
|
|
c/f |
A30 Blackwater - Kings Parade |
250 |
Jul 00 |
Jan 02 |
See Agenda item 18. |
c/f |
Farnborough Gate Cycles |
160 |
- |
- |
Staged approach, to be part funded from NEHTS cycles. |
c/f |
Ively Road |
125 |
- |
- |
Completed September 2001. |
34 |
Route 1 Corridor |
495 |
Oct 01 |
Jan 02 |
Scheme starting (including 02/03 allocation). |
35 |
Aldershot West - Town Centre |
65 |
Nov 01 |
Jan 02 |
Toucan crossing and cycle route 2001/02. |
36 |
Summit Avenue |
75 |
- |
- |
Contribution from NEHTS cycles to completed developer scheme. |
37 |
Aldershot Town Centre |
50 |
- |
02/03 |
Schemes to be developed. |
38 |
North Camp |
50 |
Jan 02 |
Mar 02 |
01/02 funding for Lynchford Road crossing. |
39 |
Elvetham Road, Fleet |
125 |
Jul 01 |
Feb 02 |
Awaiting completion of advanced lighting contract. |
40 |
Yateley (Eversley-Blackwater) |
100 |
- |
02/03 |
Consultants (W S Atkins) developing schemes. |
41 |
Decriminalised Parking |
200 |
- |
02/03 |
Schemes being prepared. |
42 |
NEHTS ITS |
80 |
- |
02/03 |
Schemes to be developed. |
43 |
Modal Integration |
70 |
Jan 02 |
Mar 02 |
Facilities at rail stations. |
44 |
NEHTS Cycles and Pedestrians |
150 |
- |
- |
Programme prepared. 01/02 contributions to scheme at Summit Avenue and cycle parking. |
45 |
Minley Cycle Route |
125 |
Spring 02 |
02/03 |
Design under way. |
46 |
NEHTS Health and Environment |
50 |
Jan 02 |
Feb 02 |
Schemes to be developed. |
47 |
NEHTS Safer Routes to School |
155 |
Nov 01 |
01/02 |
Schemes in Rushmoor and Hart. |
48 |
NEHTS Minor Works |
75 |
- |
- |
Reassigned to other schemes. Delete. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
|
NEW FOREST STRATEGY (NFTS) |
|
|
|
|
c/f |
Brockenhurst Village |
100 |
Dec 01 |
Feb 02 |
Reduced scheme being introduced. |
49 |
High Street, Fordingbridge |
80 |
- |
02/03 |
Scheme being developed. |
50 |
Lyndhurst Village Cycles |
50 |
- |
02/03 |
Scheme being developed. |
51 |
School and College Travel |
50 |
Dec 01 |
Jan 02 |
Northfields Road, Ringwood and possibly linked to Sway. |
52 |
B3055 Sway Footways |
10 |
- |
Spring 02 |
Schemes being developed. |
c/f |
Bickerley Road Footway |
50 |
Dec 01 |
Apr 02 |
Compulsory purchase completed. |
|
|
|
|
|
|
|
Southampton Area Strategy (SATS) |
|
|
|
|
53 |
Romsey Movement and Access |
690 |
Mar 02 |
May 02 |
Scheme being developed. |
54 |
Eastleigh Central Area |
225 |
- |
- |
01/02 contribution to Eastleigh Bus Station. |
55 |
Eastleigh Bus Quality Partnership |
100 |
Dec 01 |
Jan 02 |
Roadside facilities. |
56 |
Hythe Ferry Pier and Interchange |
400 |
- |
02/03 |
Scheme being developed. |
57 |
Totton and Waterside Cycles |
200 |
Summer 01 |
01/02 |
Works with maintenance scheme under way. |
58 |
Test Valley Cycle Network |
200 |
- |
02/03 |
Schemes being developed. |
59 |
Romsey Safer Routes to School |
200 |
- |
02/03 |
Schemes being developed. |
60 |
Eastleigh Safer Routes to School |
250 |
Dec 01 |
Jan 02 |
Schemes at Crestwood, Merdon, Hamble and Wyvern. |
61 |
Knightwood Cycle Schemes |
640 |
- |
02/03 |
Staged schemes being developed. |
62 |
Templars Way, Chandlers Ford |
200 |
- |
02/03 |
Schemes being developed. |
63 |
North Baddesley Traffic Calming |
80 |
- |
01/02 |
Completed. |
64 |
Portsmouth Road/Hamble Lane Junction |
70 |
- |
02/03 |
Held pending consultation on peninsula study. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
65 |
Water Lane, Totton |
300 |
Jun 02 |
Aug 02 |
Design progressing with ITS involvement. |
66 |
Doncaster Drove Cycles |
75 |
Dec 01 |
Feb 02 |
|
67 |
Eastleigh Cycle Network |
200 |
- |
02/03 |
Schemes being developed. |
68 |
Chestnut Avenue Cycles |
242 |
- |
02/03 |
Scheme being developed. |
|
|
|
|
|
|
|
SOUTH EAST HAMPSHIRE (SEHTS) |
|
|
|
|
69 |
SHRT A3 Corridor Bus Priority |
3,300 |
Jan 02 |
Mar 02 |
First stage to start early 2002. |
70 |
Fareham-Gosport Peninsula |
200 |
Dec 01 |
Apr 02 |
Fareham Bus Station, Gosport Bus Station, Stops and Ferry. |
71/X3 |
A27 Corridor Cycles |
510 |
Jan 02 |
Mar 02 |
Combined projects near to Cams School. |
72 |
Fareham Rail Station |
200 |
Jan 02 |
Mar 02 |
Reduced scheme to be implemented. £150,000 of SCA funding to be reallocated. |
73 |
Fareham Urban Centre |
150 |
Jan 02 |
Mar 02 |
Shopmobility, contribution to Kiln Lane and signing scheme. |
74 |
Gosport Bus Station |
30 |
Dec 01 |
Jan 02 |
CCTV cameras. |
75 |
Gosport Urban Centre |
125 |
Dec 01 |
Jan 02 |
7 schemes: Whitworth Road-Spring Garden Lane - lighting South Street-The Crescent - lighting Leesland - cycle track Lee-on-the-Solent - CCTV Contribution to Shopmobility scheme Stokes Bay - refuge Howe Road - footpath (from minor works)
|
76 |
Havant Urban Centre |
50 |
Sep 01 |
Jan 02 |
Hayling Billy cycle crossing and Crookhorn Lane cycle track (includes £25,000 from minor works). |
77 |
Waterlooville Urban Centre |
25 |
- |
02/03 |
Contribution to regeneration scheme. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
78 |
Leigh Park-Portsmouth Bus Corridor |
100 (+ 55 c/f) |
Apr 01 |
May 01 |
Under way. |
79 |
Lee-on-the-Solent the Browndown Cycle Route |
150 |
Nov 01 |
Mar 02 |
Gosport Borough Council developing scheme. Additional funding required (£60,000). |
80 |
SEHTS Minor Improvements |
75 |
- |
02/03 |
£25,000 to Castle Street regeneration. £25,000 to Howe Road (Gosport Urban Centre). £25,000 to Crookhorn Lane (Havant Urban Centre). |
81 |
SEHTS Safer Routes to School |
130 |
VAR |
01/02 |
8 proposals being progressed. (See this appendix.) Extra £20,000 funding - reported to SEHTS Panel on 19 July 2001. |
82 |
Outlands Lane, Curdridge |
25 |
early 02 |
02/03 |
Traffic order advertised. Objections to be considered. |
83 |
Whiteley/Segensworth Signs |
190 |
Feb 01 |
Jun 01 |
Substantially completed. |
84 |
Yew Tree Drive, Whiteley |
250 |
- |
02/03 |
Traffic management scheme starting 02/03. |
85 |
A3051 Burridge/Curbridge |
50 |
Jul 01 |
Nov 01 |
Fareham Borough Council implementing.. |
86 |
Hill Coppice, Whiteley |
200 |
- |
03/04 |
Scheme being developed - coordinated with M27 junction 9 filter lane scheme. |
87 |
Whiteley-Park Gate Cycles |
150 |
Jun 02 |
02/03 |
Schemes being developed in three phases. |
88 |
Fareham Western Wards Western Distributor, Schoner Way-Dibles Road |
400 |
Jun 01 |
Oct 01 |
Scheme under way. Consultation on linking scheme to existing road network to be reported to December meeting. |
89 |
Warsash Road/Locks Road |
140 |
- |
- |
Completed August 01. |
CP Ref. |
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
|
Western Hampshire (WHTS) |
|
|
|
|
90 |
Safer Routes to School |
40 (inc c/f) |
delegated |
Aug 01 |
Completed. |
91 |
Schemes to be identified |
50 |
- |
- |
To be considered at Panel meeting - November 01. |
|
|
|
|
|
|
|
Winchester (WMAP) |
|
|
|
|
c/f |
Bar End Park and Ride |
2,800 |
Jun 01 |
Apr 02 |
Delayed by legal challenge. |
92 |
Chesil Street Traffic Management |
75 |
Mar 02 |
Sep 02 |
Defer to 02/03. Scheme being developed. |
93 |
Romsey Road Traffic Management |
50 |
Jun 02 |
Jul 03 |
Defer to 03/04. |
94/95 |
Stockbridge Road |
150 |
Feb 02 |
Mar 02 |
Starting 01/02. |
96 |
Car Park Improvements |
50 |
Jan 02 |
Feb 02 |
Winchester progressing. |
97 |
Station Interchange |
100 |
May 02 |
Aug 02 |
Scheme at consultation. Extra funding needed 02/03. |
98 |
WMAP ITS |
50 |
tbc |
01/02 |
Scheme being developed. |
99/101 |
WMAP Cycle Schemes and Pedestrians |
130 |
tbc |
01/02 |
Garnier Road and Great Minster Street 01/02. |
100 |
Badger Farm Cycle Crossing |
100 |
Mar 02 |
Summer 02 |
Being developed, start 02/03. |
102 |
Air Quality Monitoring |
20 |
Feb 02 |
Mar 02 |
Scheme being developed with Winchester City Council. |
103 |
WMAP Safer Routes to School |
50 |
Nov 01 |
Jan 02 |
4 schemes being developed. |
|
to be added |
|
|
|
|
Other Integrated Transport
Special Projects |
|
Starts Value - £000 |
Project Appraisal |
Start Date |
Comment |
Otterbourne Traffic Calming |
|
575 |
Nov 2001 |
Jan 2002 |
Increased allocation Oct 2001 |
Dorchester Arms Junction Improvement |
|
315 |
Nov 2001 |
|
Proposed brought forward from 2002/03 |
|
|
|
|
|
|
Other Integrated Transport |
|
|
|
|
|
Central Intelligent Transport Systems |
|
275 & 100 carry forward |
Dec 2001 |
Dec 2001 |
Establishing links of CCTV and Urban Traffic Control Systems to County Council control centre |
Passenger Transport Information 2000 |
|
125 |
Dec 2001 |
Dec 2001 |
County Council contribution to national traveline information system |
Parish Partnership Schemes |
|
140 |
n/a |
n/a |
Continuing programme - 24 new schemes funded for 2001/02 making a total of 71 |
Community Safety Initiative |
|
60 |
n/a |
n/a |
Continuing programme |
|
|
|
|
|
|
Pedestrian Crossings |
|
|
|
|
|
1. Milford-on-Sea |
Pelican |
25 |
Apr 2001 |
Jul 2001 |
Completed |
2. Havant Road, Hayling Island |
Pelican |
30 |
Jan 2002 |
Feb 2002 |
Design - ITS/W S Atkins |
3. Titchfield Road, Stubbington |
Pelican |
35 |
Jan 2002 |
Feb 2002 |
Design - ITS/W S Atkins |
4. Griffin Way South, Hook |
Pelican |
35 |
Nov 2001 |
Feb 2002 |
Design - Engineering Consultancy |
Pedestrian Crossings |
|
Starts Value - £000 |
Project Appraisal |
Start Date |
Comment |
5. A323 Wellington Avenue, Aldershot |
Pelican |
33 |
Jan 2002 |
Feb 2002 |
ITS + Rushmoor Borough Council |
6. A337 Christchurch Road, Old Milton |
Toucan |
35 |
Feb 2002 |
Mar 2002 |
ITS + New Forest District Council |
|
|
|
|
|
|
7. C430 Ashley Road, New Milton |
Pelican |
30 |
Dec 2001 |
Jan 2002 |
ITS + New Forest District Council |
8. A30 Hook |
Conversion of Zebra to Pelican |
30 |
Nov 2001 |
Feb 2002 |
Engineering Consultancy |
|
|
|
|
|
|
Community Transport |
|
250 |
Jan 2002 |
Jan 2002 |
Community Transport Development Plan will identify baseline levels of provision in liaison with district councils, voluntary sector and health |
Minor Schemes |
|
280 |
n/a |
n/a |
Reduced from £400,000, transfer to Historic Buildings Grant |
Transport Monitoring Equipment |
|
200 |
Jan 2002 |
Feb 2002 |
Added to programme Oct 2001 |
APPENDIX 3
Scheme |
01/02 Starts Value £000 |
Project Appraisal |
Start |
Comments |
Casualty Reduction Programme - Proposed Revised Programme |
|
|
|
|
Low cost accident remedial programme |
910 |
n/a |
Apr 01 |
60 schemes implemented to date |
|
|
|
|
|
Larger Single Site Schemes |
|
|
|
|
M27 Junction 7, Hedge End |
55 |
Jul 01 |
Sep 01 |
Scheme completed Oct 01 |
Lower Farnham Road, Aldershot |
150 |
Jan 02 |
Mar 02 |
Rushmoor Borough Council progressing scheme |
B3055/B3058 Bashley Cross Roads |
240 |
Jan 02 |
Mar 02 |
Replaces B2177/B3354 Fishers Pond which is to be deferred to 02/03 |
B3006 Selborne Road (secret warning sign) |
23 |
Jul 01 |
Feb 02 |
ITS progressing scheme |
|
|
|
|
|
Enforcement Technology |
80 |
n/a |
Apr 01 |
Programme developed with Police |
|
|
|
|
|
Refurbish/Betterment Programme |
120 |
n/a |
Apr 01 |
W S Atkins progressing schemes |
|
|
|
|
|
Route Strategies |
|
|
|
|
A339 Basingstoke to Lasham |
22 |
Jul 01 |
Oct 01 |
Scheme completed Nov 01 |