Archived decisions

      HAMPSHIRE COUNTY COUNCIL

    BUILDING DESIGN PROJECT APPRAISAL

      EXECUTIVE MEMBER - EDUCATION

      23 NOVEMBER 2001

    PROJECT:

    HALTERWORTH PRIMARY SCHOOL, ROMSEY

    EXTENSION TO PROVIDE TWO CLASSOOMS, IT SUITE & SPECIAL NEEDS ROOM AND REMOVAL OF TEMPORARY CLASSROOM

    COMMENCEMENT DATE:

    JANUARY 2002

    COMPLETION DATE:

    JULY 2002

    PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

    2001/ 02

      RECOMMENDATION:

      That the building design project appraisal for the Halterworth Primary School scheme be approved.

      1. FINANCE

    Capital Expenditure

    Current Estimate

    (at Nov '00 prices)

    £'000

    Capital Programme

    (at Nov '00 prices)

    £'000

    Buildings

    351

    68

    Fees

    45

    11

    Land to be purchased

    _

    _

    TOTAL

    * 396

    79

      * The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.

      Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total

    Cost

    £'000

    1. From Committee's own Resources:

    a) Capital Programme 01/02 **

    68

    11

    79

    b) School - Devolved Capital (Total devolved capital from 2000/01 to 2003/04 - see below)

    67

    0

    67

    2. From Other Resources:

    a) Policy and Resources Committee's 2001/02 AMP Condition funding

    216

    34

    250

    TOTAL

    351

    45

    396

** To be reimbursed from anticipated NDS Modernisation funding. Subject to the approval of the Education Committee's Capital Programme report elsewhere on the agenda. £

Anticipated Devolved Capital allocations 2000/01 15,000

              2001/02 12,000

              2002/03 15,000

              2003/04 25,000

TOTAL 67,000

Landlord Funded Work connected with this Scheme

A contribution of £216,000, excluding fees, has been made from the Policy & Resources Committee's 2001/02 AMP Condition funding towards this scheme.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Net Cost = £ 1,109 per m2

Revenue Implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    Nil

    Nil

    -

    31

    31

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

(a) Energy Costs

        The existing school comprises some 1,630 m2 of accommodation and the annual fuel cost is approximately £5,300.

        Upon completion of this project and following the removal of the double temporary building, it is anticipated that the annual increase in fuel cost for the school will be in the order of £350.

(b) Maintenance Costs

      The detailed design and choice of materials will minimise future maintenance liability.

      2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

          The double temporary classroom unit on this site, which provides 60 places, has deteriorated to such an extent that an elevation failed during the October 2000 storm due to decay ( a window blew into one of the classrooms). This has resulted in one side of the unit being boarded up to give stability.

          The capacity of the school, including the places provided by the temporary unit is 420, with 417 pupils on roll. Forecast numbers show this number remaining stable requiring the replacement of the unit.

      3. DETAILS OF SITE

          LOCATION

          Halterworth Primary School is located at Halterworth Lane, Romsey

          ADJOINING LAND AND BUILDINGS

          The site is bordered by residential accommodation to the north and west with the A3090 and the town of Romsey beyond. To the south is further housing with fields and farm accommodation beyond. To the east is open fields with the A27 and the village of North Baddesley beyond to the south-east.

          AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

          The total site area is 7.00 acres (2.83 hectares). The DfES guideline for a school of this size is 4.50 acres (1.82 hectares).

          PLANNING POSITION

          Planning permission for these proposals has been granted.

          SUITABILITY FOR PROJECT

          The Headteacher, Governors and staff have been consulted throughout the feasibility and design stages of this scheme and the proposals have been agreed.

          The project will enable the replacement of a double temporary classroom with two general teaching classrooms. The development will also encompass an IT and a Special Needs Room along with additional circulation areas and a secure landscaped courtyard, all of which will improve the teaching environment for pupils.

          RESULTS OF TRIAL BORE HOLES

          A site investigation has revealed the ground condition to be topsoil overlying a sandy gravel substrata.

          The recommended foundations for this project are pad and strip foundations founded approximately 1000mm below existing ground level.

          ACCESS

          The main vehicular Access point to the school site is to the north-west of the site, from Halterworth Lane, which runs the length of the western boundary of the site. The main pedestrian access point is located further north along Halterworth Lane.

          It is proposed that a contractors compound be established to the east of the school playground on an area of the school playing field. It will be necessary for the contractor to use part of the school playground to access the compound and appropriate security arrangements made for this. The contractor will need to share the only vehicular entrance to the site with other school traffic and site restrictions will be enforced on the time and place of deliveries.

          COMMENTS ON SITE LAYOUT

          The school site is rectangular in shape with the vehicular entrance and car parking areas to the north-west. The school has two playground areas in the north-west corner of the site and directly south of the school buildings. The playing field extends from the school to the east and a double temporary classroom, which will be removed upon completion of these works, is positioned to the south-east corner of the school adjacent to the playground.

          The new accommodation will be constructed to the south-east corner of the school and will extend the existing building line towards the playing field. The layout of the new accommodation will form a secure courtyard area which will be landscaped.

          MAINS SERVICES POSITION

          Existing mains services are considered to be of a sufficient capacity to be extended as required to serve the proposed new accommodation.

          MAINTENANCE IMPLICATIONS

          The site will continue to be maintained in accordance with current County Council standards.

          LANDSCAPE PROPOSALS

          Paving will be provided to the perimeter and entrance / exit points of the new accommodation and the position of the new extension will create an enclosed courtyard area to the east of the main school building.

          The courtyard will have a tarmac covering and benching, line marking, a sand pit area along with planting of trees and shrubs will be provided in this area which is intended to be used by pupils in the reception class.

          The area currently occupied by the double temporary classroom will be reinstated following removal from site.

      4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION

          TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

          It is proposed to construct a single storey extension to the south-eastern corner of the existing school to provide replacement permanent accommodation and additional specialist facilities. The extension will provide the following accommodation:

          - two classrooms, with store and wet area

          - IT Suite, with stores

          - special needs room

          - corridor with cloak areas

          The shape of the extension will provide a courtyard area enclosed on three sides by buildings. The northern elevation will have a wall and planting to provide an enclosed secure play area for reception aged pupils.

          PLACES PROVIDED

          60 replacement places will be provided.

          PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

          The original school was constructed during 1971, with later additions of classrooms and music / drama facilities in the 1980's and 1990's. The original school is of a SCOLA design with later extensions in a traditional brick design and all of the buildings are all considered to be in a good condition.

          TEMPORARY BUILDINGS

          There is currently one double temporary classroom located to the south east of the school buildings. The unit is considered to be in a poor condition and will be removed from site and the area reinstated upon completion of the new accommodation.

          SITUATION ON SITE AND ENVIRONMENTAL IMPACT

          Any visual impact on site will be minimal as the extension is to the rear of the site behind existing buildings.

          The site will benefit from the removal of a temporary classroom and the provision of a secure courtyard for reception aged pupils. No trees will be removed from site as part of these proposals and additional shrubs and planting will be included.

          TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

          The new accommodation has been designed to reflect the varying styles of architecture which exist on this site. The Special Needs Room has been designed to match the adjoining music / drama room and will be of a brick and render construction with a high performance felt roof covering and aluminium framed windows.

          The two classrooms and IT suite have been designed to match the recent two classroom extension to the north and will be constructed from fair faced brick panels with aluminium doors and windows with a high performance felt roof covering.

      FACILITIES FOR THE DISABLED

          The proposed new accommodation will have level access throughout and will be constructed at the same level as the existing building which will eliminate the need for internal ramps. There is sufficient toilet provision, including an accessible WC, within the existing building and therefore no further toilets have been included in this design.

          HEATING AND VENTILATION SYSTEMS

          A new domestic size gas fired boiler serving a low pressure hot water system feeding radiators to the classrooms and under floor heating to the IT suite will be included in the proposed new accommodation.

          The IT Suite will have extraction ventilation, elsewhere the ventilation will mainly be by natural means via opening windows.

          ENERGY EFFICIENCY OF BUILDING

          The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

          ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

          These proposals have been agreed by the Headteacher and Governors of the school as being the most appropriate form of development to provide permanent replacement general teaching classrooms along with specialist teaching areas and will enable the removal of temporary buildings from site.

          CAR PARKING

          There will be no change to the existing car parking arrangements on this site.

          CONSULTATIONS

          The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, County Planning Officer, Test Valley Borough Council, County Surveyors, Estates Practice.

      5. THE BUILDING DEVELOPMENT

          These proposals realise permanent replacement accommodation and a dedicated external landscaped courtyard. The additional classroom and circulation space will better meet the operational requirements of the school.

      6. BUILDING MANAGEMENT

          CLEANING

          Existing arrangements will apply.

          CATERING

          Existing arrangements will apply.

      7. FURNITURE AND EQUIPMENT

          From the block vote in the Education Committee's Capital Programme.

      8. STAFFING

          No change.

      9. FEES

          Architectural Services - Alexander Design

          Quantity Surveying - Selway Joyce Partnership

          Electrical and Mechanical Engineering - Giffords

          Structural Engineering - Giffords

      EME1101c