Archived decisions

      HAMPSHIRE COUNTY COUNCIL

    BUILDING DESIGN PROJECT APPRAISAL

      EXECUTIVE MEMBER - POLICY & RESOURCES

      12 DECEMBER 2001

    PROJECT:

    THE ROMSEY SCHOOL

    EXTENSION TO PROVIDE THREE CLASSROOMS AND SPECIALIST RESOURCED PROVISION

    COMMENCEMENT DATE:

    MARCH 2002

    COMPLETION DATE:

    AUGUST 2002

    PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

    2001/ 02

      RECOMMENDATION:

      That the building design project appraisal for The Romsey School scheme be approved.

      1. FINANCE

    Capital Expenditure

    Current Estimate

    (at Nov '00 prices)

    £'000

    Capital Programme

    (at Nov '00 prices)

    £'000

    Buildings

    507

    507

    Fees

    81

    81

    Land to be purchased

    _

    _

    TOTAL

    588

    588

      Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total

    Cost

    £'000

    1. From Committee's own Resources:

    a) Capital Programme 2001/02

    293

    47

    340

    b) DfEE funding for Aspergers Unit

    214

    34

    248

    TOTAL

    507

    81

    588

                  £

Anticipated Devolved Capital allocations

              2001/02 27,000

              2002/03 36,000

              2003/04 72,000

TOTAL 135,000

NB: The school will not be making a contribution from their devolved capital allocations towards the proposals outlined in this design project appraisal.Landlord Funded Work connected with this Scheme

There is no Landlord funded work associated with these proposals.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Gross Cost = £1,136 per m2

      - Net Cost = £ 974 per m2

Revenue Implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    Nil

    9

    9

    46

    55

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

(a) Energy Costs

        The existing school comprises some 8,800 m2 of accommodation and the annual fuel cost is approximately £33,000.

        Upon completion of this project it is anticipated that the annual increase in fuel cost for the school will be in the order of £1,580

(b) Maintenance Costs

      The detailed design and choice of materials will minimise future maintenance liability.

      2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

          Two separate Basic Need bids were made in September 1999 and September 2000 to extend this school by a total of 57 places. At the same time (September 2000) a bid was also submitted to seek funding to provide a resourced provision for pupils with Autistic Spectrum Disorders.

          The main bid will take the school capacity to 1,104 places with a projected demand of 1,110 places by 2004/05 academic year.

      3. DETAILS OF SITE

          LOCATION

          The Romsey School is located at Greatbridge Road, Romsey

          ADJOINING LAND AND BUILDINGS

          The site is bounded to the west by open fields and farm accommodation with the River Test beyond. Residential accommodation boarders the site to all other sides with open fields and the A3057 Road to the north and the town of Romsey lying to the east and south.

          AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

          The total site area is 16.60 acres (6.75 hectares). The DfES guideline for a school of this size is 18.78 acres (7.60 hectares).

          PLANNING POSITION

          A detailed formal Planning Application was submitted to the County Planning Officer during October 2001.

          SUITABILITY FOR PROJECT

          The proposals outlined in this design project appraisal have been developed in consultation with the Headteacher and Governors of the school. Upon completion of the project the school will be enlarged to accommodate 1,104 pupils.

          The creation of the specialist unit will provide specialist accommodation for up to 12 pupils.

          RESULTS OF TRIAL BORE HOLES

          A site investigation was undertaken during April 2001 and revealed the ground conditions to be made ground overlying brown, slightly clayey fine to course flint gravel overlying grey flint gravel to a depth of 1.30m.

          Conventional strip foundations and a ground bearing slab would be suitable for the proposed structure.

          ACCESS

          The main vehicular and pedestrian access point to the school site is from Greatbridge Road in the north-east corner of the site and these arrangements will remain unchanged both during and upon completion of these proposals.

          It will be necessary to create a separate temporary entrance point to the site for use by the contractor for the duration of the contract. This will be formed from an existing entrance from Hollman Drive in the far south-west of the site. A secure temporary access road will lead north to the contractors compound which will be located to the east of the All Weather Pitch and adjacent to the proposed location of the new building.

          COMMENTS ON SITE LAYOUT

          The school buildings are located to the north of the site with the vehicular entrance to the north-east corner and car parking facilities to the north. Tennis courts / playcourt are located between existing school buildings and also to the south-west of the school buildings adjacent to the school playing field which extends to the south.

          The proposed new accommodation will be constructed to the south of the existing buildings on an area of the school playing field to the east of the All Weather Pitch. The accommodation will link to the main teaching block via a bridge walkway which will provide direct access to the general teaching classrooms on the first floor of the new accommodation.

          MAINS SERVICES POSITION

          Due to the increased load associated with the proposed extension a new electrical supply and transformer will be provided as part of this project. All other existing mains services are considered to be of a sufficient capacity to be extended as required to serve the proposed new accommodation.

          MAINTENANCE IMPLICATIONS

          The site will continue to be maintained in accordance with current County Council standards.

            LANDSCAPE PROPOSALS

          Perimeter paving will be provided to the new building along with paths linking the new and existing accommodation and the All Weather Pitch. Areas of low level planting will also be provided around the new building

      4. THE PROPOSEDBUILDING/RATIONALISATION/CONVERSION

          TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

          It is proposed to construct a two storey extension to the southern elevation of the existing school building.

          The ground floor accommodation will provide:

          - Specialist Unit - with kitchenette and store

          - SEN classroom

          - office

          - group room

          - shower

          - two WC's

          - boiler room

          - entrance - with lockers

          - stairs to first floor accommodation

          The first floor accommodation will provide:

          - three general teaching classrooms

          - corridor - with lockers

          - stairs to ground floor accommodation

          PLACES PROVIDED

          An additional 57 places will be provided along with 12 new places in the Specialist Unit.

          PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

          The original school was constructed during 1958 and many additions in accommodation have been added in the years since, the latest being a new library and IT block which was completed during 1997.

          The existing buildings on site are considered to be in a good condition for their age and type.

          TEMPORARY BUILDINGS

          There are no temporary buildings on this school site and none will be required either during or upon completion of the proposed scheme.

          SITUATION ON SITE AND ENVIRONMENTAL IMPACT

          The proposed location of the new accommodation has been carefully chosen to maximise the available space on this site and complement the location of existing buildings, which will minimise the movement of pupils around the site.

          No trees will be removed from site as part of these proposals.

          TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

          The proposed new accommodation will be of a traditional masonry load bearing construction, with a standing seam aluminium mono-pitched roof and powder coated aluminium frame windows.

          FACILITIES FOR THE DISABLED

          The proposed new accommodation will have level access throughout the ground floor accommodation and level access to the first floor classrooms will be possible via the link walkway from the main building.

          The school already has suitable accessible toilet provision within the existing buildings and therefore no further accessible toilets are included within the new building.

          HEATING AND VENTILATION SYSTEMS

          A boiler room will be located on the ground floor of the new extension and a new gas boiler will be installed to serve a low pressure hot water system feeding radiators.

          ENERGY EFFICIENCY OF BUILDING

          The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

          ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

          These proposals have been agreed by the Headteacher and Governors of the school as being the most appropriate form of development to provide the additional basic need places required for September 2002.

          The proposals will realise the aim of the County Council to provide resourced provision at two secondary schools in Hampshire.

          CAR PARKING

          No additional car parking spaces will be provided as part of these proposals as existing parking arrangements are sufficient to meet the school's requirements.

          CONSULTATIONS

          The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, County Planning Officer, Test Valley Borough Council, County Surveyor, Estates Practice.

      5. THE BUILDING DEVELOPMENT

          Upon completion of these proposals the school will have the desired amount of accommodation to meet the Basic Need requirement as well as dedicated specialist teaching accommodation.

      6. BUILDING MANAGEMENT

          CLEANING

          Existing arrangements will apply.

          CATERING

          Existing arrangements will apply.

      7. FURNITURE AND EQUIPMENT

          From the block vote in the Education Committee's Capital Programme.

      8. STAFFING

          No effect.

      9. FEES

          Architectural Services } Property, Business and

                  Regulatory Services Quantity Surveying - John Watson & Carter

          Electrical and Mechanical Engineering } Property, Business and

          Structural Engineering } Regulatory Services

          EMP&R1201g