Archived decisions

Hampshire County Council

Executive Member - Environment

15 January 2002

Project Appraisal - Installation of New Traffic
Monitoring Equipment throughout Hampshire

Report of the County Surveyor

Item 19

Contact: Jon Foley, ext 7559

1. Summary

1.1 The following decision is sought:

      That the Project Appraisal for the installation of new traffic monitoring equipment throughout Hampshire be approved.

2. Reason

2.1 To enable a more comprehensive permanent monitoring regime to be put in place for the county, and so improve future monitoring required for the Local Transport Plan. The use of remote monitoring units will greatly reduce time required in retrieving this information.

3. Other Options Considered and Rejected

3.1 No other suitable alternative.

4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer Consulted - Not applicable.

5. Dispensation granted by the Standards Committee - Not applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.

Approved by: Date:

Councillor K B Estlin

HAMPSHIRE COUNTY COUNCIL

EXECUTIVE MEMBER - ENVIRONMENT

ROADS

PROJECT APPRAISAL

_____________________________________________

15 JANUARY 2002

_____________________________________________

____________________________________________________________________

PROJECT:

INSTALLATION OF PERMANENT TRAFFIC COUNT EQUIPMENT THROUGHOUT HAMPSHIRE

____________________________________________________________________

COMMENCEMENT DATE:

FEBRUARY 2002

COMPLETION DATE:

MARCH 2002

PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME: 2001/02

____________________________________________________________________

____________________________________________________________________

____________________________________________________________________

1.

FINANCE (Client Department, Director of Property, Business and Regulatory Services [Estates Practice] and County Treasurer)

____________________________________________________________________

Current

Capital

Estimate

Programme

(at 2001

(at 2001

prices)

prices)

Capital Expenditure

£'000

£'000

Equipment

200

200

200

200

Less developers/

other contributions

200

200

Financial provision for total scheme

Total Cost

1.

From Committees own resources

(a) Capital programme (as above)

200

(b) Other

200

2.

From other resources

(a)

(b)

(c)

TOTAL

200

Value of land for this project in HCC ownership £

Variations from capital programme

Revenue implications

£'000

% variation

to Committee's

budget

Net current expenditure

10

0.023

Capital charges

32

0.053

TOTAL net expenditure

42

0.076

____________________________________________________________________

____________________________________________________________________

2.

STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

(Client Department)

____________________________________________________________________

Investment in new traffic monitoring equipment will allow more comprehensive permanent monitoring regimes to be put in place for the Area Transport Strategies, and so improve future monitoring required for the Local Transport Plan (LTP). The incorporation of remote monitoring units into new and existing sites will greatly reduce time required in retrieving the information, which in future can be carried out by telephone and avoid travelling to the sites. This will enable the more effective and efficient use of existing staff time.

____________________________________________________________________

3.

ROAD IMPROVEMENT PROPOSAL (Client Department)

____________________________________________________________________

National/County network and policies

The Government requires the County Council to produce an Annual Progress Report on its LTP. The information collected from the monitoring sites is key to understanding traffic trends.

Details of scheme and design standards

In summary the project requires the supply and installation of permanent traffic monitoring equipment at approximately 110 sites throughout Hampshire. This includes upgrading the equipment at approximately 70 existing locations with the remainder being new sites.

All installations are to make use of telemetry technology to enable the remote collection of data from a base in Winchester. This will also require the supply and installation of GSM telemetry computer software for the collection and storage of data.

Environmental impact

None.

Land requirements

Not applicable.

Statutory procedures

None.

Public consultation

Not applicable.

Facilities for the disabled

Not applicable.

Maintenance implications

There will be no change in the revenue budget required as a result of this investment. While there will be a revenue implication associated with implementation of additional sites (estimated to be an additional £10,000 per annum), the savings associated with converting the existing sites to remote collection will balance this expenditure. Additionally, the project will enable the more efficient use of staff time currently employed in the manual collection of data. Finally, any remedial works will be funded from within the existing revenue budget.

Local Member's View

Not appropriate for this county-wide project.

Crime and Disorder Act 1998

No areas of concern have been identified.

Sustainability

Not applicable.

____________________________________________________________________

4.

ROAD IMPROVEMENT - ALTERNATIVES CONSIDERED

(Client Department)

____________________________________________________________________

Not applicable.

____________________________________________________________________

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

6885/JF