BEST VALUE REVIEW OF HAMPSHIRE TRANSPORT MANAGEMENT - IMPROVEMENT PLAN Appendix 1
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resource/costs to complete |
Performance indicators |
Progress to date |
RG to spend more time in workshops |
EFQM Review |
Improve communications |
RG |
June 2001 (continuous) |
NIL |
RG to visit workshops at least every two months |
Commenced |
Involve staff in process improvements |
EFQM Review |
Increase staff commitment to changes |
BF/TB/RG |
June 2001 (continuous) |
NIL |
E.g., staff to agree new pay documentation |
Commenced |
Challenge legal constraints on market opportunities |
EFQM Review |
Expand legal market |
RG |
April 2002 |
NIL |
Changes in legislation will make it easier to trade with external organisations |
Included in Business Plan |
Additional telephone facilities |
EFQM Review |
Improve office efficiency |
BF |
April 2002 |
NIL |
More telephones |
Awaiting clarification from IT Services |
Database showing skills of personnel |
EFQM Review |
IiP, maximise potential use of staff, staff development |
BF/TB |
December 2001 |
NIL |
Part of IiP evidence |
Completed |
Greater formality in training programmes |
EFQM Review |
IiP, improve management, recording and evaluation of training |
RG/BF/TB/ JM |
November 2001 (continuous) |
NIL |
Appointed current member of staff as Training Officer to provide focus and coordination |
Commenced |
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resources/costs to complete |
Performance indicators |
Progress to date |
Recruitment becoming more difficult |
EFQM Review |
Retain full staffing compliment |
TB/RG |
June 2001 (continuous) |
NIL |
Staff turnover still low, two new staff recently appointed, improved pay and conditions implemented September 2001 |
Commenced |
Workshop environment |
EFQM Review |
Improve staff working conditions |
TB/RG |
June 2001 (continuous) |
Unknown |
£50k included in Business Plan for workshop/ fuel facilities improvements |
Commenced |
Uniforms and badges |
EFQM Review |
Improve customer perception - `professional outfit' |
TB |
April 2003 |
NIL |
HTM badges now on overalls |
Commenced but staff still prefer older style, dark blue overalls, without name badges |
Succession plan for BF |
EFQM Review |
BF retires April 2003 |
RG/NJ |
April 2002 |
Unknown |
Succession plan |
Included in Business Plan |
Communicate and record policy developments |
EFQM Review |
Improve staff knowledge and understanding of changes |
RG/BF/TB |
June 2001 (continuous) |
NIL |
Staff morale |
Commenced |
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resource/cost to complete |
Performance indicators |
Progress to date |
Check that internal communication has been understood |
EFQM Review |
Improve communications |
RG/BF/TB |
June 2001 (continuous) |
NIL |
Improved communications |
Commenced |
Funding of Courier service |
EFQM Review / Challenge |
HTM will not be able to fund deficit after April 2002 |
AJS/RG/RM/ CT |
April 2002 |
NIL |
Corporate funding of service |
Discussions underway between PB&R and CT |
IT |
EFQM Review / Challenge |
Improve IT facilities and systems, connect workshops and improve hardware reliability |
BF/TB/IT Services |
Investigate SAP Fleet Management module and manufacturers' technical data on-line by April 2003 |
Unknown |
IT 2000 rolled out November 2001. Ford technical data now on-line |
Commenced |
Review of current procedure notes |
EFQM Review |
Ensure procedures are fully documented |
BF/TB |
April 2002 |
NIL |
Revised procedure notes |
Completed |
Improve understanding of RCS through discussion |
EFQM Review |
Improve working relationship with RCS |
RG/BF/TB |
December 2001 |
NIL |
Agreed processes with RCS |
Joint workshop July 2001, agreed procedures implemented |
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resource/cost to complete |
Performance indicators |
Progress to date |
Improve management and admin of pool and spot-hire vehicles |
EFQM Review |
Improve service to customers |
BF/RG |
September 2001 (continuous) |
NIL |
Reduced customer complaints |
Improved handover and monitoring procedures with County Surveyor's reception staff |
Develop more non-financial `performance indicators' |
EFQM Review |
Improve service to customers |
BF/TB/RG |
April 2002 (continuous) |
NIL |
Record of customer complaint/compliments. Bottom line |
Included in Business Plan |
Start office team meetings |
EFQM Review |
Improved communications and staff awareness |
BF/TB/RG |
June 2001 (continuous) |
NIL |
Regular staff meetings |
Commenced |
Involve workshop staff in more decisions affecting them |
EFQM Review |
Improved communications and staff awareness |
TB/BF/RG |
June 2001 (continuous) |
NIL |
Regular staff meetings |
Commenced |
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resource/cost to complete |
Performance indicators |
Progress to date |
Highways Fleet |
Challenge |
Turnover and profitability |
RG/TB/BF |
April 2002 |
NIL |
Turnover and bottom line |
Negotiations underway with RCS and Balfour Fleet Services over Strategic Alliance |
New markets |
Challenge |
Turnover and profitability |
BF/TB/RG |
June 2001 (continuous) |
NIL |
Turnover, bottom line and customer profile |
Continued expansion of fleet in Education sector through competitive rates, high quality service and reputation |
Courier Service performance |
Challenge |
Service delivery |
BF/RG/JF |
June 2001 (continuous) |
NIL |
Customer satisfaction monitored through feedback and annual survey |
Continuous process of identifying additional tasks and/or routes |
Improvement |
Reference |
Reason |
Responsible Officer |
Target date for completion |
Resource/cost to complete |
Performance indicator |
Progress to date |
Upgrade of fuel facilities and systems |
Challenge |
Improved customer service and provide better management information for HTM and customers |
BF/RG |
Complete by April 2002 |
Costs included in Business Plan to be met from surpluses |
Updated facilities and management information |
Bar End, Hook, Micheldever, Totton and Petersfield completed. Bishops Waltham to finish |
Alternative fuels |
Challenge |
Increase the usage of alternative fuels - LPG & Electric |
BF/RG/TB |
December 2002 (continuous) |
Unknown as dependent on volumes |
Number of vehicles using alternative fuels. Evaluation of LPG and electric vehicles - overall costs, performance, reliability |
2 LPG/petrol and 1 electric vehicle in fleet. Install LPG facility in Winchester Depot once development issues have been resolved |
Courtesy vehicles |
Challenge |
Improve service to customers, reduce disruption to services of vehicles off the road |
BF/TB |
June 2001 (continuous) |
Costs met from HTM trading account |
2001/2002 - 30 vehicles (at least 1 minibus, 1 tail-lift and 1 car at each workshop) |
Number of courtesy vehicles has been increasing for last two years |