Archived decisions
Hampshire County Council South West Hampshire Transportation Panel 7 March 2002 Hedge End Transport Strategy Report of the County Surveyor |
Item 6 |
Contact: Helen Ackerman, ext 5077
1. Background
1.1 In August 2000 WSP Consultants was appointed by the County Council to carry out a study into the transport needs for the Hedge End Area. The study reviewed existing transport arrangements in the area and proposed improvements in Hedge End, Botley and West End which reflected the aspirations of the local community, businesses and the County Council's Transport Policies. The final report was submitted to the County Council in March 2001.
1.2 A meeting in July 2001 with Members of the County Council, Eastleigh Borough Council and Hedge End, West End and Botley (HEWEB) Local Area Committee approved a preferred list of projects from the WSP report. This list was recommended for approval by the former Southampton Area Transport Strategy Panel in November 2001.
2. Financial Details
2.1 The Hedge End Transport Strategy (HETS) is funded from various developer contributions (Section 278 Agreements) where monies have not been allocated to a specific project, but have an area qualification, for example the Hedge End area. This funding has been allocated to projects identified within this study and other projects that Eastleigh Borough Council has been developing, such as West End to Swaythling Cycles. There is currently £900,000 available for schemes recommended at the joint Members' meeting and in this report.
3. W S Atkins Review
3.1 In October 2001 as part of the Partnering Agreement with Hampshire County Council, W S Atkins (WSA) was commissioned to review the reports prepared by WSP, and others on some of the specific schemes by Eastleigh Borough Council and the County Council. The list of reports is provided in the attached appendix. WSA was required to assess each of the preferred schemes, and determine the nature and content of the likely works with a view to providing more detailed initial estimates.
4. Hedge End, West End and Botley/Hampshire County Council Member Forum
4.1 Following WSA's assessment, and the meeting of the Members on 13 February 2002, the following schemes are proposed.
4.2 In order to progress schemes with a shorter lead-in time, a list of projects that could be implemented within the next six to nine months has been prepared. These schemes were assessed using the following criteria:
(i) little or no survey work required;
(ii) little or no consultation required;
(iii) no Traffic Regulation Orders required;
(iv) little or no further feasibility work required;
(v) no significant utility works required;
(vi) no land acquisition required; and
(vii) no significant utility diversions.
4.3 The projects identified using these criteria are:
Project Name |
Brief Description |
Estimated Cost |
Missing links to Wildern School |
Extend existing footways to provide continuous pedestrian facilities to the school. |
£7,100 |
Tollbar/Charles Watts Way |
Apply coloured surfacing to pedestrian crossing and alter markings on approach from M27. |
£3,600 |
Charles Watts Way |
Make improvements to signing and quality of route over footbridge. |
£11,600 |
Chalk Hill/ West End Road |
Realign junction. |
£29,800 |
St Johns Road |
£35,600 | |
Estimated Costs |
£87,700 |
These projects are recommended for approval and to be taken forward for immediate implementation, taking advantage of the County Council's Term Maintenance Contract where possible.
4.4 The preferred list of schemes, excluding those above, has also been assessed to identify where it is appropriate to group like or dependent schemes together. Packaging schemes is likely to generate some cost savings in preparation, design and supervision fees. The recommendations have been made with the following criteria in mind:
(i) related projects, ie dependent on another scheme;
(ii) schemes contributing to a common policy; and
(iii) schemes in close proximity to others.
Packaging of schemes does not indicate a higher priority in terms of construction or need.
4.5 The following tables identify the recommended 'Packages':
Package 1 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improvement to cycle and pedestrian facilities. |
B1 |
St Johns/Lower Northam Road Junction Improvements |
£10,800 |
|
B18 |
Upper and Lower Northam Road |
£182,100 |
||
B21 |
Grange Road/Lower Northam Road |
£7,600 |
||
Total |
£200,500 |
£2,800 | ||
Net |
£197,700 |
It is proposed that this package be taken to its preliminary design stage.
Package 2 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Traffic calming and safety improvements to pedestrian and other facilities. |
B11 |
Hedge End Railway Station Junction |
£incl below |
|
B12 |
Maunsell Way |
£332,700 |
||
Total |
£332,700 |
£nil | ||
Net |
£332,700 |
It is proposed that this package is taken to preliminary design stage.
Package 3 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improvements to encourage modal shift to bus/cycle train. |
D3 |
Botley Railway Station pedestrian crossing facilities |
£55,300 |
|
D5 |
Waiting facility improvements |
£24,200 |
||
Total |
£79,500 |
£1,600 | ||
Net |
£77,900 |
This package is seen to have a low priority at this stage. No further work is to be done on this package at this time.
Package 4 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improvements to reduce vehicle speeds and improve pedestrian safety. |
B17 |
Turnpike Way new pedestrian crossing |
£30,000 |
|
B13 |
Turnpike Way traffic calming |
£222,900 |
||
Total |
£252,900 |
£3,900 | ||
Net |
£249,000 |
It is proposed that this package is taken to preliminary design stage.
Package 5 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improve pedestrian safety and bus egress from service area. |
B14 |
Tollbar Way Formal Crossing |
£76,000 |
|
E11 |
Tollbar Way service access |
£82,700 |
||
Total |
£158,000 |
£5,500 | ||
Net |
£153,200 |
The Tollbar Way formal crossing is to be put on hold by the County Council as this is the subject of a Section 278 Agreement which may fund this work. Tollbar Way service access was deleted from the list of schemes by Members.
Package 6 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improve pedestrian safety. |
C4 |
Chapel Road pedestrian crossing |
£25,400 |
|
C6 |
High Street improvement to pedestrian facilities |
£47,600 |
||
C11 |
Botley Road improvement to pedestrian/cycle facilities. |
£15,300 |
||
Total |
£88,300 |
£2,300 | ||
Net |
£86,000 |
The High Street Improvement is to be assessed under the County Council's crossings criteria. The Chapel Road scheme is to be the subject of a feasibility study.
Package 7 |
ID |
Scheme Title |
Individual Cost Ests |
Package Reductions |
Improve network operation. |
B15 |
Chalcroft Industrial Park signing survey and review |
£2,400 |
|
E12 |
Investigations into Charles Watts Way slip road to Retail Park |
£17,800 |
||
Total |
£20,200 |
£nil | ||
Net |
£20,200 |
This package is to be reviewed with the Police to determine if it is required.
Estimated total cost of Packaged Schemes to be undertaken now is £865,400.
4.6 Of the preferred schemes, the following do not lend themselves to being undertaken quickly, or packaged:
A1 |
Cycleway to Itchen Valley Country Park The Members decided that only a short link between Oakvale and the County Park on Allington Lane needed to be done. This work has been estimated at £50,000 by Eastleigh Borough. |
||
B6 |
Hedge End Railway Station |
£91,200 | |
C3 |
Moorgreen Road |
£162,300 | |
C7 |
West End Road/Church Hill Junction improvement |
£174,800 | |
D6 |
Cycle Parking in Botley Village Centre |
£11,400 | |
These schemes should be developed to feasibility design stage. |
|||
B8 |
Freegrounds School |
£15,700 | |
B9 |
Kings Copse School |
£15,700 | |
These are School Travel Plan related schemes and should await the outcome of these plans. |
|||
C9 |
Chalk Hill Traffic Management |
£145,000 | |
This scheme should await implementation of C7 above to determine its need. |
|||
The Botley to Hedge End cycle route along the A334 Broad Oak should be progressed as a part of the major maintenance project. This work is estimated to cost £200,000 from the HETS package. |
|||
The estimated total cost to be undertaken now is |
£689,700 | ||
5. The Way Forward
5.1 It is proposed that the projects identified for delivery within the next six to nine months will be progressed by WSA, and procured through the County Council's Term Maintenance Contract where possible.
5.2 The remaining funding will be allocated to those schemes recommended for feasibility or preliminary design as detailed in paragraphs 4.5 and 4.6. Each of these will be progressed by WSA for implementation in late 2002 and early 2003, depending on the level of consultation and any issues arising throughout the design stage.
5.3 One of the main aims for this study was to provide a basis for future negotiations with developers in the area. The County Council will continue to seek contributions towards the HETS, or particular schemes identified in this report, from developers as their proposals come forward.
Recommendation
That it be a RECOMMENDATION to the Executive Member for Environment that the packaging of schemes and the way forward in this report be approved.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
Hedge End Transport Strategy Feasibility Review |
County Surveyor's Department |
7000/HA
APPENDIX
List of Reports included in WSA Review | ||
Author |
Title |
Date |
Eastleigh Borough Council |
Chalk Hill West End Traffic Study |
February 2000 |
Maunsell Way, Hedge End Traffic Study |
June 2001 | |
Turnpike Way, Hedge End Traffic Study |
November 2001 | |
WSP Consultants |
Hedge End Transport Study (Final Report) |
February 2001 |
Hedge End Transport Study (Executive Summary) |
February 2001 | |
Traffic Survey Technical Data |
March 2001 | |
Consultation Technical Data |
March 2001 | |
Forecasting Technical Data |
February 2001 | |
Hampshire County Council |
Hedge End and Botley Railway Stations (comments on WSP report) |
May 2001 |