Archived decisions

Hampshire County Council

Executive Member, Policy & Resources Item 4

11 April 2002

Alton Day Services - Relocation to New Building (Design Project Appraisal)

Report by the Director of Property, Business and Regulatory Services

Contact: Andrew Smith Ext: 7826

1. Summary

1.1 The following decisions are sought:

That approval be given to the attached design project appraisal for the provision of a new Social Services Day Service in Alton.

2. Reason(s)

2.1 To enable the provision of a new Day Service building in Alton to replace the existing building which has become functionally obsolete and which will shortly require major maintenance expenditure.

3. Other options considered and rejected

3.1 Not applicable

4. Conflicts of interest declared by the decision-maker or a member for
officer consulted


4.1 Not applicable

5. Dispensation granted by the Standards Committee

5.1 Not applicable


6. Reason(s) for the matter being deal with if urgent

6.1 Not applicable

Approved by: ..................................... Date of decision: ...................

Councillor T K Thornber

EMP&R0402h