Intelligent Transport Systems Programme - Basingstoke
Extend the Basingstoke town centre car park monitoring and information system to include the new Festival Place car park, with additional signs at:
· Alencon Link approach to Victory roundabout
· Churchill Way approach to Victory roundabout;
· Timberlake Road approach to Victory roundabout;
· Churchill Way approach to Eastrop roundabout;
· Timberlake Road adjacent to the access to the Festival Place south ramp
Extend the present CCTV coverage to include:
· M3 junction 5 (subject to HA funding);
· Blackdam roundabout (subject to HA funding);
· A33/A339 Reading Road roundabout;
· A33 Reading Road/Popley Way.
Install a bus departure information system for the Basingstoke bus station funded from the Festival Place redevelopment, and install real time passenger information at a number of bus stops in association with the Route 1 Quality Bus Partnership.
In terms of traffic signals and pedestrian crossings, the following are planned;
· Two toucan crossings, one on Harrow Way near the Golden Lion roundabout, and one on Hatch Warren Lane;
· Puffin crossing in Brighton Way;
· A33/A339 Reading Road roundabout (note CCTV above provided as part of this scheme) - now more likely to be 2003/04;
· A33 Reading Road/Popley Way (note CCTV above provided as part of this scheme) - now more likely to be 2003/04.
· There is a pedestrian stage planned for the traffic signals at Essex Road/Worting Road, but this is planned for 2003/04.