Archived decisions

    Appendix 2

      Report to PRC January 2003

      Ofsted Action Plan Monitoring Report

    Felicity Roe

    Head of Planning and Communications

    Colour key

    Blue - action completed

    Green - action progressing well.

    Amber - action started, but progressing slower than anticipated.

    Red - action not yet started

    Purple - action deleted on EDMT decision, because of duplication or changing circumstances and needs.

    Progress on activities outlined in Ofsted Action Plan

    The LEA strategy for school improvement

Recommendation 1a. In order to improve the strategy for school improvement:

in the planned revision of the Education Development Plan, relate priorities and activities more precisely to the audit of needs.

    Actions

Responsibility: Andrew Seber and Felicity Roe

Start date

End date

1)

Blue

2) Prepare EDP2 taking full account of the audit of needs

a. Rigorous audit of needs using analysis of all available data combined with professional judgements.

Audit undertaken and met with DfES and Ofsted approval.

May 2001

July 2001

b.

Blue

c. Derive main priorities from the audit of need.

All main priorities clearly rooted in the audit of need

July 2001

Sept 2001

d.

Blue

e. Consult all partners on EDP and invite proposals for a third local priority.

Partners consulted in line with EDP statutory guidance. Third local priority set.

Sept 2001

Nov 2001

f.

Blue

g. Revise audit of needs with 2001 data.

This was done in December 2001.

Nov 2001

Dec 2001

h.

Blue

i. Revise EDP in light of consultation and any new indications from the 2001 data

Consultation responses were positive. New data confirmed the approach proposed.

Nov 2001

Jan 2002

3)

Blue

4) Establish annual data interrogation cycle to inform decisions on future EDP activities and to contribute to the annual evaluation of the EDP

a. Establish clear processes and responsibilities for data analysis and interpretation as an EDP monitoring activity.

These have been established and shared with all officers involved.

Oct 2001

Jan 2002

b.

Blue

c. Establish clear reporting arrangements for audit information affecting the EDP.

These are established. 2002 Key Stage results and other information due in January/February, will feed into the first EDP monitoring report to members. The first full evaluation of the EDP will take place summer/autumn 2003, after its first year of operation. This evaluation will also consider the audit base being used, and will trigger changes as necessary.

Oct 2001

Jan 2002

    Blue

    Blue

    Blue

    Monitoring and evaluation

· Ensure all relevant officers have offered professional interpretations of audit data. Checklist developed and responses received.

· Feedback from consultation with partners in the autumn term 2001.

· Scrutiny by elected members in Dec 2001. Scrutiny by DfES by 31 March 2002.

    Green

    Blue

    Blue

    Success criteria

· Schools in Hampshire show continued improvement as a result of the targeted support of the LEA.

2002 KS2 results show some `stalling'. Issues being addressed through EDP 2002 -2007 and literacy and numeracy programmes.

· Feedback from consultation positive, with support from schools and partners for the priorities in the plan.

Feedback was very positive.

· EDP2 accepted by DfES

Approved by DfES March 2002. Awarded a JRS 3 by Ofsted. Steps taken to improve the document, taking Ofsted comments on board.

    The LEA strategy for school improvement

Recommendation 1b. In order to improve the strategy for school improvement:

further raise members' capacity to identify the extent to which the EDP is providing value for money, by sharpening the performance indicators used to evaluate the effectiveness of EDP activities.

    Actions

Responsibility: Andrew Seber and Felicity Roe

Start date

End date

1) Give careful consideration to performance indicators during the drafting of EDP2

a.

Blue

b. Aim to use outcome measures wherever possible.

With a few unavoidable exceptions all the main success criteria in EDP2 are based on outcome measures

July 2001

Sept 2001

c.

Blue

d. Highlight for members measures of key importance for each EDP priority.

Blue

Members of Education PRC received a briefing on the key performance indicators for each priority. They will receive the first report on these as part of the annual review of EDP2.

Oct 2001

Jan 2001

e. Invite partners to comment on the robustness and value of the performance indicators during consultation.

    The document presented to partners for consultation did not contain this level of detail. The performance indicators chosen are all based on pupil outcomes and published data and were approved by Education PRC and County Council as suitable indicators to enable them to monitor progress.

Sept 2001

Nov 2001

f.

Blue

g. Build the regular monitoring and evaluation of the EDP performance indicators by Members into the EDP monitoring arrangements.

    Annual reports are scheduled on the full `basket' of EDP2 indicators. Many of these indicators are reported to PRC as part of separate reports in the course of the year.

Nov 2001

Dec 2001

2)

Green

3) Offer training for Members

a. Run a training session for Members when the EDP2 performance indicators are finalised.

    Decision made to run training linked to the first presentation of indicators in 2003.

Revised target date

May/June 2003

    Monitoring and evaluation

· Blue

· Scrutiny of EDP2 performance measures by Education Management Team.

First 6-monthly monitoring report taken to EDMT in November 2002.

    Blue

    Green

    Blue

    Blue

    Blue

    Green

Reporting of draft EDP2 to Members of Education Policy Review Committee, inviting particular comment on the draft performance indicators.

Done - January 2002.

· Feedback from Members following the training session to assess their understanding and confidence in the value of the performance indicators for their ongoing monitoring role.

This will take place after the training session in 2003.

    Success criteria

· Feedback from consultation positive, with support from schools and partners for the priorities and performance indicators in the plan.

Yes - success criteria met.

· EDP2 approved by Members.

Yes- January 2002.

· EDP2 accepted by DfES.

Yes - March 2002.

· Members are clear on the value and use of the EDP performance indicators in their Policy Review role.

Seminar in 2003 will aim to provide clarity for Members.

    LEA support for school improvement

Recommendation 2a. In order to improve support for school improvement:

ensure that all visits to schools by attached inspectors are followed up by a brief note of visit, showing the list of identified action points and identifying any relevant leadership and management issues at the school.

    Action

Responsibility: John Clarke with senior phase inspectors/advisers and area school improvement managers.

Start date

End date

1) Revise guidance to attached inspectors

a.

Blue

b. Ensure guidance sets out the procedures for writing notes of visits after each school visit.

Done

July 2001

Sept 2001

c.

Blue

d. Procedures to include requirement to include action points and relevant leadership and management issues in the notes of visits.

Done

July 2001

Sept 2001

e.

Blue

f. Guidance to include requirement to send the notes of visits to chairs of governors and headteachers within ten working days.

Done

July 2001

Sept 2001

g.

Blue

h. Include in guidance for attached inspectors the requirement to make provision for the chair of governors and headteacher of each school in receipt of targeted improvement grants to receive monitoring reports (action in response to additional comment in Ofsted report)

Done

April 2001

Ongoing

2)

Blue

3) Train attached inspectors in notes of visit

a. Ensure training covers content of notes of visit, and a common standard governing the leadership and management issues which will be deemed relevant for inclusion in notes of visit.

Training on category for primary and secondary. AIs included notes of visit.

Sept 2001

Nov 2001

b. Establish this training as part of attached inspector induction.

Done

Sept 2001

Ongoing

4)

Blue

5) Follow-up and collation

a. Ensure these reports reach Chairs of governors by separately enveloping and addressing them.

An established part of HIAS processes.

Sept 2001

Ongoing

b.

Blue

c. All notes of visits to be displayed electronically in the school file as it becomes available, and highlighted for action where necessary.

    The new system is now in use across HIAS, and integration of other services into the system has begun

Jan 2001

Ongoing

d.

Purple

e. As the electronic school file develops, explore the possibility of establishing an electronic alert where notes of visits are filed later than two weeks after scheduled visit to a school.

Blue

    Possibility explored - decision taken that this is not achievable - it would create too much bureaucracy.

Jan 2002

March 2002

f. Notes of visits considered alongside other monitoring information as part of the assessment of the strengths and weaknesses of a school.

    Part of remote monitoring from April 2002.

Sept 2001

Ongoing

g.

Blue

h. Analysis of notes of visits by area school improvement managers to identify actions the LEA needs to take, with individual schools or wider groups of schools.

    Part of remote monitoring from April 2002.

Sept 2001

Ongoing

    Blue

    Blue

    Monitoring and evaluation

Discussion between strategic school improvement managers and John Clarke at their half-termly meetings.

Ongoing

· Regular checks in the electronic school file to ensure that notes of visits are filed against visit dates.

Ongoing now school file is up and running

· Blue

· Regular monitoring of progress against actions by Education Department Management Team.

This task is undertaken by the John Clarke, Deputy CEO.

    Blue

    Blue

    Blue

    Blue

    Success criteria

· Consistency of approach between attached inspectors.

There is an annual survey of attached inspector practice and reports in the electronic school improvement file are sampled by the Strategic School Improvement Managers and the Deputy CEO.

· 100% of chairs of governors and headteachers of schools visited receive notes of visit.

Notes of visit are now sent to all chairs of governors and headteachers as a matter of course. No sampling to determine receipt has been undertaken.

· Through electronic school file, senior staff across the LEA aware of management and leadership issues in particular schools and take appropriate action.

SSIMs are responsible for this monitoring, and bringing together information on management and leadership issues in schools is a key part of their job.

· No Ofsted inspections discover issues related to leadership and management which have not already appeared in a note of visit with appropriate actions set out.

There have been no recent `surprises' and the systems are working well.

LEA support for school improvement

Recommendation 2b. In order to improve support for school improvement:

review the provision of centrally-funded visits by attached inspectors to the better performing schools in line with the Code of Practice.

    Actions

Responsibility: Gerry Price and David Woodward

Start date

End date

1)

Blue

2) Revise categorisation system

a.

Blue

b. Make interim changes to deployment of attached inspectors to one visit a year to successful schools.

Done

April 2001

April 2001

c.

Blue

d. Simplify categorisation system to four categories of school.

Done

April 2001

Nov 2001

e.

Blue

f. Used simplified categorisation system to redefine the notion of successful schools and the triggers for further support and intervention.

Done

April 2001

Nov 2001

g. Consult with schools on proposed new system and the triggers for support and intervention.

Done

July 2001

Oct 2001

3)

Blue

4) Implement and monitor effectiveness of new categorisation system

a.

Blue

b. Implement new categorisation system with every school categorised by Feb 2002.

Done

Oct 2001

Feb 2002

c. Implement new allocations of centrally-held attached inspector time.

Done

Jan 2002

April 2002

d.

Green

e. Review the effectiveness of the new categorisation system through monitoring Ofsted reports on schools and through analysis of weak departments.

Ongoing.

April 2002

April 2005

f. Develop further the system for monitoring the time allocations of attached inspectors to ensure they spend their time in accordance with the principles of inverse proportion to success.

Done

Jan 2002

April 2002

g. Quantify implications of new categorisation and trigger system on staff time.

Done

Feb 2002

April 2002

5) Strengthen remote monitoring systems to compensate for reduced visits

a.

Blue

b. Create an electronic school file where all reports and data relating to a school are lodged

The Electronic School Improvement File system is fully operational and all inspectors' visits to schools are recorded on the system.. Work is developing from the core of data and will extend to all school visits across the department.

July 2001

Jan 2002

c.

Green

d. Develop the electronic filing system to highlight indications of weaknesses or difficulties.

Ongoing work as part of the further development of the project.

Jan 2002

April 2004

e.

Green

f. Run a full database check in April 2003 (and thereafter annually) to ensure all appropriate data and reports are being filed.

Sample checking will take place

April 2003

May 2003

g.

Green

h. Determine a clear LEA strategy for school self-evaluation linked to the categorisation system, and promote this through local and county headteacher conferences (supports comment in Ofsted report text).

June 2001

Nov 2001

    Blue

    Blue

    Blue

    Blue

    Blue

    Blue

    Monitoring and evaluation

· Monitoring systems: regular meetings between Gerry Price and John Clarke to track progress.

These are no longer needed - ICT Board replaces these.

· Quarterly monitoring of Ofsted Action Plan progress by Education Department Management Team.

Monitoring 6-monthly and will continue on an exceptions basis until all activities are completed.

· Reports to Information Communications Technology Board meetings on the development of the school file on a quarterly basis.

Working as planned

· Ongoing monitoring by area school improvement managers, evaluated by database updates to Standards and Improvement Branch Management Team on a quarterly basis.

Now 6-monthly.basis.

· Area school improvement managers' ongoing analysis of the needs of each school reported regularly to the Standards and Improvement Branch Management Team and Education Department Management Team.

Reports made as part of the ASIM/SSIM reports on areas to EDMT

    Success criteria

· Over 80% of schools agree with the main thrusts of the new categorisation system.

· Blue

    Blue

    Blue

    Blue

    Blue

· 100% of schools categorised according to the new system by Feb 2002.

Work completed Jan 2002.

· System implemented as new time budgets for visiting each school adhered to by the LEA.

Done

· Successful schools only visited once by the LEA in the course of their core attached inspector work.

Done

· The department has a secure electronic file for each school containing all the information the LEA has on that school, thus enhancing the LEA's remote monitoring capacity.

The Electronic School Improvement File system is fully operational and all inspectors' visits to schools are recorded on the system. This is now an ongoing project, working from the core of HIAS data to include notes of visits from staff across the department.

· The department has sufficient knowledge about each school to allow the triggers for extra resources to be accurately identified.

Bringing this information together is an important part of the SSIM role and the categorisation system and school improvement file are key tools in this process.

    LEA support for school improvement

Recommendation 2c. In order to improve support for school improvement:

place a greater emphasis on judging attached inspector effectiveness through greater reference to pupil outcomes.

    Action

Responsibility: Area school improvement managers in liaison with Nigel Hill

Start date

End date

1)

Green

2) Ensure progress made by pupils in each school can be clearly identified

a. Formally identify a basket of outcome data for each school.

Blue

    Work in progress.

April 2001

Sept 2002

b. Update outcome data on an ongoing basis as new data are received.

May 2001

Ongoing

c.

Blue

d. Review the `basket' of data when the new common pupil record (Impulse) system is fully operational.

April 2002

Sept 2002

3) Establish pupil outcome based systems to assess attached inspector effectiveness

a.

Blue

b. Use information on the progress of pupils in school as part of the attached inspector performance review process (recognising that many other factors affect school performance).

    AI have targets which relate to the performance of their `challenging' schools. These focus on improvements in school effectiveness, focussing heads and middle managers.

Sept 2001

Ongoing

c.

Green

d. Explore the feasibility of developing systems to use value-added data to assess attached inspector and LEA impact. Correlate value added data with school categorisations.

    This will require sophisticated linkages between the common pupil record, value added data and school categorisations. Work will not begin until the CPR data is on line.

Jan 2002

Revised Sept 2002

Jan 2004

Revised Jan 2005

4) Green

5) Extend principles of the system to other staff

a. Investigate ways in which performance reviews of other school-focussed staff (e.g. other advisory service staff, staff involved in school buildings, educational psychologists, teacher advisers (special educational needs), the Bilingual support service staff) can be related to pupil outcomes.

    Early exploratory work on this has begun.

Jan 2002

Revised Sept 2002

Sept 2002

Revised Jan 2005

b.

Blue

c. All assistant county education officers to deliver a composite report to Education Department Management Team on the progress in extending this initiative to other staff.

    EDMT discussed the extension programme at the first 6-monthly action plan monitoring meeting.

Mar 2002

April 2002

    Monitoring and evaluation

· Blue

    Blue

· Area school improvement managers will report to John Clarke through regular work review meetings.

Ongoing

· Education Department Management team through quarterly monitoring of the Ofsted Action Plan.

Reports have been made - future Ofsted Action Plan reports will be on an exceptions basis.

· Green

· Assistant County Education Officers to report on progress of widening the initiative to other staff through regular work review meetings with Andrew Seber.

    Green

This is progressing in discussions with heads of service

· Establish process of routinely seeking headteacher and chair of governor assessments of the impact of the attached inspector work on pupil outcomes.

    Green

    Amber

    Amber

    Green

    Success criteria

· Systems are developed to enable the performance of the LEA to be judged partly on improvements in value added in schools.

This is underway. For the first time this Autumn we will have national value added data from Dfes performance tables and be able to judge the overall value added of Hampshire secondary schools.

· The performance of attached inspectors is judged partly by the progress (or maintained standards) of pupils in `their' schools.

The value added data that would enable this to happen is just beginning to become available. Judgements on schools where attached inspector visits are limited by Code of Practice restrictions are made through the categorisation process.

· The impact of attached inspectors in schools where they do the most work is clear.

The value added data is that would enable this to happen is just beginning to become available.

· Performance reviews of other staff in the Education Department are informed by information on pupil outcomes.

Work on this is underway.

    LEA support for school improvement

Recommendation 2d. In order to improve support for school improvement:

improve the support for literacy by:

1) encouraging schools to set more aspirational targets and

2) further developing links between attached inspectors / phase inspectors* and the English team. (*LEA addition)

    Action

Responsibility: John Clarke with senior inspectors/advisers

Start date

End date

Blue

1) Strengthen the target setting process and culture

a. Enhance the statistical model for target setting in both primary and secondary schools by using information about the prior attainment of pupils in each school.

Purple

Ongoing activity

July 2001

Nov 2001

b. Continue to develop the culture of target setting in primary schools by holding a series of meetings, setting it in a context of school improvement and the whole LEA.

    An assessment was made that these meetings were not needed for primary in 2002. Target setting was discussed at primary head's executive and progressed through discussion with individual headteachers.

Sept 2001

Nov 2001

c.

Blue

d. Provide further training for attached inspectors on target setting to ensure they continue to challenge schools to set aspirational targets.

Done

Sept 2001

Nov 2001

e.

Blue

f. Build training on target setting into the attached inspector induction programme.

Done

Sept 2001

Ongoing

g.

Blue

h. Bring greater clarity to the mechanisms for agreeing school targets and strengthen the role of the senior inspector/adviser and area school improvement managers in this process.

This has been done, and has been a big success.

Sept 2001

Sept 2001

2) Strengthen inter-team working

a.

Blue

b. Establish joint working opportunities for attached inspectors and the English team on county exercises for monitoring and support. April 2001 (primary and special) and April 2002 (secondary).

    Management monitoring by secondary team complements English team work. Secondary doing now and throughout summer term.

April 2001

Ongoing

c.

Blue

d. Provide regular opportunities for attached inspectors to be updated on literacy issues both on paper and face to face.

    The secondary team has regular input from Kate and Wendy. Progress with the primary arrangements is being pursued.

June 2001

Ongoing

Blue

3) Ensure continued improvements

a. Standards and Improvement Branch Management Team to monitor school target setting and receive annual reports from the senior primary and secondary advisers on the aspirational nature of the targets. Take action if schools appear to need greater levels of challenge.

Ongoing

Sept 2001

Ongoing

b.

Blue

c. Through attached inspector and English team performance review, establish which liaison opportunities have best enhanced links, and develop these systems. Extend good practice to other professional groups, particularly the links between attached inspectors and the mathematics team (action in response to additional comment in Ofsted report).

Blue

    Working well. Targeted support groups for coming year.

Sept 2001

Ongoing

d. Use workshop activity of primary phase inspectors in Sept 2001 to provide a baseline for a further survey in Sept 2002 to measure increased understanding and confidence in literacy activities. Establish areas for continued improvement.

Blue

Ongoing

Sept 2001

Sept 2002 and ongoing

e. To ensure continued improvement in standards of literacy, complete programme for leading literacy teachers and recruit new leading teachers to a max of 42 (action in response to additional comment in Ofsted report).

    Considerable progress has been made.

April 2001

April 2002

f.

Blue

g. Strengthen networking to support English subject managers in secondary schools (action in response to additional comment in Ofsted report).

    Work going on through KS3 strategy, Heads of Dept. Conference and identification of leading departments.

April 2001

Ongoing

    Monitoring and evaluation

· Blue

· The Head of Information and senior inspector/advisers will report to Standards and Improvement Branch Management Team and Education Department Management Team at the end of the target-setting process each year, beginning in January 2002.

The report to EDMT was via the draft EDP, which set out the match of LEA and school targets.

· Blue

· Feedback from primary headteacher conference on the value of meetings on target setting.

Feedback prior to the meetings was that these meetings were not necessary, and they were not held

· Blue

· Assessment of training impact in regular meetings and annual performance reviews for attached inspectors and English team.

Ongoing

· Reports on progress from Kate Marron to John Clarke.

As part of regular reviews.

    Blue

    Blue

    Blue

    Green

    Success criteria

· A match between the LEA targets for 2003 and 2004 and the aggregated schools' targets for those years.

The aggregated school targets for English and Maths at primary level for 2003 were within the ranges set by the LEA. Schools requiring targeted support for English and Mathematics were rigorously identified and benefited from LEA focused input as well as further work through the National Strategies.

For secondary, the LEA set milestone targets for 2003 and, in the case of Key Stage 4, has worked with schools in agreeing targets that would ensure they contribute to this interim indicator. In respect of Key Stage 3 in 2003, the LEA has no statutory responsibilities although it is monitoring data that have been received from schools against interpolated LEA targets.

· At least 92.5% of school targets lie inside the guideline range set by the LEA.

Achieved

· Reports of visits on literacy from attached inspectors in all phases show a good understanding of the detailed issues in improving standards in this area.

This is improving steadily as the literacy strategy embraces training and development for attached inspectors.

· Attached inspectors report they are confident in judging the quality of schools' work in improving standards in English and in providing them with practical strategies and advice in relation to improvement.

Work on this is progressing, and attached inspectors abilities to make judgements are improving.

    LEA support for school improvement

Recommendation 2e. In order to improve support for school improvement:

further strengthen the leadership and senior management expertise available to advise and support secondary schools.

    Action

Responsibility: Alan Rawlings with senior inspector/adviser and Louise Brierley

Start date

End date

1) Develop the proposed network of Hampshire Inspection and Advisory Service associates.

a.

Blue

b. Identify and release secondary headteachers to support the leadership and management of other secondary schools when:

      i) there are weaknesses in the leadership and management of a school as identified by its categorisation and it is judged that headteacher support would be beneficial

      ii) the headteacher has requested mentorship because of management or other staffing difficulties.

    The new models programme has achieved this.

    An independent evaluation of the programme was carried out in May 2002 by Brian Symons Consulting. The outcomes were overwhelmingly favourable. The specific feedback from those headteachers who were supported through the newly appointed Professional Adviser for Leadership and Management.

Sept 2001

Ongoing

2) Facilitate the sharing of good practice and expertise

   

a.

Green

b. Encourage experienced senior headteachers to share good practice in leadership and management through termly seminars for headteachers and summary information published on the web.

    The first planned session was not well supported. However, the intention is to reschedule this work into 2003/2004 by which time the outcomes from Activity 3 will have taken hold.

Sept 2001

Sept 2003 and ongoing

c.

Blue

d. Continue work to improve the structures and systems for developing and matching mentors (action in response to additional comment in Ofsted report).

    Evaluation indicates that take up of mentors is high. Past records show that only one mentor has needed to be changed. However, the uptake of mentors is not uniform across the county. Education Personnel is following this up to find out why. Feedback from headteachers does not indicate that any significant change is needed to arrangements.

June 2001

Sept 2001

e.

Amber

f. Through Hampshire Governors' Representative Group and County Governor Forum, work with governors to increase the awareness of the value of governor investment in headteacher training and development.

    At the level of individual appointments, contact has been made, and discussions taken place with secondary chairs to secure their commitment to support of the LEA's revised induction and purchased services for newly appointed secondary headteachers. Further work is needed to raise awareness generally.

Sept 2001

July 2002 and ongoing

3) Strengthen attached inspector leadership and senior management advisory skills

a.

Blue

b. Establish an action research group with volunteer headteachers to identify good practice in the leadership and management of secondary schools through joint headteacher/attached inspector activities.

    27 secondary headteachers attended an initial meeting of the research group in June. This is a high response rate. Seven research projects have been identified and dissemination/evaluation will take place in March 2003.

April 2002

April 2003

4) Monitor the effectiveness of the strategy

   

a.

Green

b. Review success of activities with secondary headteacher conferences and work with them to develop improved systems and ways of sharing the expertise that exists within the school community.

    This has been taken up by the Professional Adviser for Leadership and Management who, as at September 2002, is in discussion with the Chair of Conference about leadership development activities and how the work of the headteachers' own professional development group can be blended with that of the LEA.

Sept 2002

Sept 2003

     Monitoring and evaluation

· Progress of New Models Project with Vosper Thornycroft.

· Standing item on half-termly attached inspector meetings.

· Senior inspector/adviser will report to secondary team meetings on outcomes and issues at headteacher development sessions.

· Reports on progress will be made to Secondary Standing Committee.

· A private partner will evaluate the work under the New Models Programme.

· Views of headteachers and attached inspectors where schools have had mentoring and associate inspector time.

· Analysis of Ofsted inspection reports to establish long-term improvements.

· Headteachers will be invited to evaluate the programme through conferences and Standards and Improvement Secondary Standing Committee.

All monitoring activities achieved/ongoing.

    Blue

    Blue

    Blue

    Blue

    Blue

    Green

    Success criteria

· Mentor headteachers identified, trained and accredited as HIAS associates.

In respect of the headteachers who were supported under activity 1a), all four `mentor' headteachers were assessed and activated as planned.

· Leadership and management in schools where associate inspectors have contributed becomes more secure.

Evidence from categorisation is that this has occurred, especially in relation to the 5th criteria - capacity to improve.

· Target headteachers no longer in need of the assistance of the associate inspector.

None of the supported headteachers is in need of assistance at the level that was identified originally (one has been promoted to a non-headteacher role elsewhere).

· Stronger networking and sharing of expertise, especially for new headteachers.

The revised induction programme for new HT (secondary) held its first sessions in September 2002 . Existing HTs are contributing to, and participating in the programme and it included 1:1 sessions for the new HT with John Samuels in addition to the conventional mentor arrangements.

· Secondary attached inspectors exposed to best practice ideas of the County's most experienced headteachers.

This is occurring as part of the action research groups and John Samuels also intermittently attends the secondary team meeting.

· LEA best practice web site carries a developing resource on leadership and management for all headteachers.

Best practice web site has details of primary leadership and management, secondary is still in development.

    LEA strategic management

Recommendation 3a. In order to improve strategic management:

broaden the role of the Schools' Monitoring Sub-Committee to include the monitoring of the performance of schools more generally and improve its access to performance data to enable it to be more proactive.

    Action

Responsibility: Roger Mead and John Clarke

Start date

End date

1) Review after modernisation

a.

Blue

b. Examine the need for a schools' monitoring sub committee, which would be a sub-committee of the Education Policy Review Committee.

Blue

Panel now established

May 2001

June 2001

c. If the sub-committee continues, review the terms of reference to include responsibilities for monitoring the performance of all schools.

    TOR established, wider than those of schools monitoring committee.

Sept 2001

Nov 2001

2) Identify key performance information by which members can monitor overall and individual school performance.

a.

Blue

b. Offer Members training in the use an interpretation of performance information (linked to the Member training for recommendation 1(b)).

    Some training has already been offered to Members. Ongoing needs will be addressed, with link with EDP performance indicators training in 2003.

Mar 2002

April 2002

c.

Blue

d. Revise the information reported to Members as the Common Pupil Record information becomes available through the Impulse system.

Ongoing.

June 2002

Sept 2002

e.

Blue

f. Establish an annual review of the data being used by Members to ensure it offers the best picture of the performance of Hampshire schools.

Members are receiving the most comprehensive information the systems can offer.

Sept 2002

Thereafter annually

    Blue

    Monitoring and evaluation

· Timetable for regular reports on school performance (including performance information) to Members agreed by schools monitoring panel.

· Timetable for reporting of annual reviews of performance information agreed by schools monitoring panel

    Blue

    Green

Panel has received a paper and agreed these timetables.

    Success criteria

· Terms of reference of the schools' monitoring panel to reflect its role in monitoring the performance of all schools.

Terms of reference agreed.

· Members feel fully informed about the performance of all schools and feel able to make an effective contribution to school improvement.

Members are not yet fully informed about the performance of all schools, but the terms of reference of the panel and the timetable for 2003 are designed to ensure this is achieved. They are well informed on the culture of school improvement.

    LEA strategic management

Recommendation 3b. In order to improve strategic management:

produce a single strategic development plan for information management and ICT support covering planned activities, timescales, resource implications, performance indicators, and targets and circulate to all schools.

    Actions

Responsibility: David Woodward

Start date

End date

Blue

1) Develop an LEA ICT strategy

a. Discuss proposed main principles of a strategy with headteacher and officer groups.

Done. Proposals discussed at SISG and many other groups. All HTs were given the opportunity to comment.

April 2001

Oct 2001

b.

Blue

c. Circulate draft strategy for comment.

Done

Oct 2001

Dec 2001

d.

Blue

e. Ensure other major LEA strategies and plans reflect the principles and direction of the draft and final ICT strategy.

    Key links made with the Education Development Plan.

Sept 2001

Ongoing

f.

Purple

g. Develop detailed activities, timescales, resource needs, performance indicators and targets for the strategy.

    As the strategy development process has evolved it has become clear that the nature of ICT, which infiltrates every aspect of the work of the education service and involves many hundreds of budget holders and managers, makes the development of a single detailed action plan unmanageable. The decision has been taken to produce a high level document with clear aims to act as a direction setting document. The many managers of resources throughout the service will then be encouraged to develop detailed plans for the use of their own resources in line with the strategy.

Oct 2001

March 2002

h.

Blue

i. Seek Clear Language Award accreditation for the ICT strategy.

    Done

March 2002

April 2002

j.

Blue

k. Publish the ICT strategy on the Internet and Hampshire Education intranet and market its availability to all relevant partners, particularly schools. Provide paper versions where requested. Ensure all updates are publicised.

Done. No updates yet needed.

April 2002

April 2002

    Blue

    Monitoring and evaluation

· Performance indicators for the strategy will be developed as the strategy is developed. Work has already begun to establish a baseline for the total cost of ownership of ICT.

Baseline for total cost of ownership now complete. This and bullet three will form the key progress measurement tools.

    Blue

The LEA (with two other LEAs) and two Hampshire Schools have been working with a national DfES/BECTa project to develop an instrument to enable schools to measure their own total costs. Early feedback is very promising.

· The strategy will be monitored regularly by the Education Department Management Team, the Education ICT Board, the Schools Information Strategy Group and the Joint Education and IT Services Management Team.

EDMT : 25 October 2001, 20 February 2002; Education ICT Board : update at each 6 weekly meeting; SISG : 7 November 2001, 7 March 2002; Joint Education and IT Services Management Team - regular discussion with final draft presented 26 February 2002; Policy Review Committee : 19 March 2002.

· Green

· Use will be made of customer perception surveys and benchmarking.

The perception survey work has now started.

· Black

· An external evaluation of the effectiveness of the strategy will be made in January 2004.

    Green

Not yet appropriate.

· Support for the strategy from the Education Department Management Team and schools.

Full support given so far.

    Blue

    Blue

    Success criteria

· Clear English accreditation for the strategy documentation.

Achieved.

Measurement of the success of the following is dependent on the two performance strands identified above: a) the total cost of ownership of ICT and b) the perceptions of professionals across the service. There is anecdotal evidence that we are `heading in the right direction', but harder edged evidence will take longer to produce.

The management team of Hampshire Education ICT Support and Development Services has been recast to provide a much tighter management focus. The team is working with the Ofsted Inspection Framework, and the Ofsted/Audit commission inspection guidance, together with the regional ICT benchmarking group, to develop additional performance data to contribute to evaluation judgements.

· All managers throughout Hampshire's education service understand the rationale for the ICT strategy and its implications for their decision making.

General feedback to date has indicated a broad acceptance of the direction established through the Hampshire Education ICT strategy and welcome the leadership that it gives.

· Green

    Green

    Green

· Headteachers, teachers and other Education service staff reduce the amount of time spend considering and managing the technological infrastructure and instead are able to concentrate on exploiting the benefits of ICT to support learners, managers and administrators.

Early signs of the work being undertaken on the total cost of ownership in two Hampshire schools indicates that it will be possible to obtain indicative information to help with this judgement.

· A reduction in, or at least levelling of, the total cost of ownership of ICT across the education service.

See above.

· A steady improvement in the quality, consistency, availability and accessibility of data and information across the education service.

See above.

    LEA support for pupils with SEN

Recommendation 4a In order to improve support for pupils with SEN:

consider how key points of the SEN policy and action plan can be shared effectively with all stakeholders across the county.

    Action

Responsibility: Robin Thomas and Fliss Dickinson - a progress report on this area will be made to the next EDMT

Start date

End date

 

2)

Blue

3) Develop further materials covering the key points of the SEN policy and action plan and explore new ways to make them available

a. Develop the SEN policy and action plan as web pages linked to the existing Inclusion web site. Ensure they are also accessible through the LEA web library of policies and guidance, part of an LEA initiative to reduce the bureaucratic burden and volume of paperwork for schools.

Blue

    The SEN policy and action plan is on the web, (including a single A4-sheet summary) and held within the library of policies.

Sept 2001

April 2002

b. Run seminars for elected Members and health professionals to enhance their understanding of the role they can play in effective delivery of the SEN action plan.

    A seminar for members took place during the summer term 2002. Briefings for Health and other County Council service departments were delivered over the summer and autumn terms 2002.

April 2001

July 2001

c.

Blue

d. A summary leaflet targeted at parents of children with special educational needs has been developed to disseminate key points of the SEN policy. The information is available on the web site.

Blue

April 2002

July 2002

e. When the LEA web library is launched, ensure that the SEN policy and action plan are highlighted as key documents in the launch publicity.

The LEA web library is now available on-line and includes the SEN policy and action plan..

Jan 2002

March 2002

f.

Blue

g. Through the web library, ensure that the SEN policy and action plan are regularly updated, and changes notified to all schools.

    This will be built into the ongoing work on the web library.

Jan 2002

Ongoing

4) Establish regular progress updates for key stakeholder groups

a.

Blue

b. Prepare annual reports on progress against the SEN action plan for the Executive Member for Education Include relevant performance indicators in these reports.

Blue

This formed part of the briefing for elected members and also part of the report on Inclusion activities to Education PRC. It will be included in future reports on inclusion activities to Education PRC.

April 2002

Annually thereafter

c. Make termly updates on progress against key points in the SEN action plan to Headteacher Inclusion Standing Committees and Special Schools' Executive. Engage these groups in problem solving and further development of the action plan at these meetings

    Termly reports underway. Reports on individual activities within the SEN action plan are regularly made to these groups.

Oct 2001

Termly thereafter

d.

Blue

e. Encourage headteachers on special educational needs groups, including standing committees and executive, to disseminate information to and canvass ideas from all headteachers.

Blue

    Ongoing work - regular discussions on feedback responsibilities and methods.

April 2001

Ongoing

f. Run briefings on the SEN policy and action plan for the health authorities and Social Services Directorate staff. These will be designed to enhance awareness of their contribution to the speed and quality of the assessment of special educational needs process.

    Seminars run in summer term 2002. Further seminars are planned together with revised governor training modules and a programme of dissemination to HTs, SENCOs etc.

May 2001

July 2001

5) Establish baseline information

a.

Blue

b. Establish number of `hits' on the website in September 2001 as a baseline for measuring future access to the information in this way.

Ongoing monitoring

Sept 2001

Sept 2001

c.

Blue

d. Establish as a baseline the number of parents resorting to regional disagreement resolution and/or SEN and Disability Tribunals and review annually.

The numbers are known and published annually.

Sept 2001

July 2002

    Monitoring and evaluation

· Blue

    Blue

· Increasing access to the web site (10% increase a year).

A recent HMI survey of Hampshire schools identified ease of access by schools to SEN information.

· Annual reports to the Executive Member for Education and Headteacher Inclusion Standing Committees.

    Blue

    Green

    Blue

    Blue

    Blue

    Blue

    Blue

    Blue

There are two termly meetings with HT reps and an annual report on Inclusion activities was presented to Education PRC in 2002.

· Feedback from briefing sessions for Members and health authority professionals.

Verbal feedback has been very positive.

· Improved quality and timeliness of advice from all partners for statutory assessment reports.

A baseline is being established, and work is ongoing with the health service to make improvements.

· Performance reviews between the lead officers and Sheila Arney.

Ongoing as part of established performance review arrangements.

· 6-monthly reports to Inclusion Branch Management Team.

Ongoing.

    Success criteria

· Increased access to and understanding of the SEN policy and action plan for all stakeholders including parents.

This is difficult to quantify, but the policy and plan have been made more accessible, including the provision of web-based information.

· Elected members and headteachers fully informed of progress against the action plan.

This has been a focus of the seminars and information dissemination programme.

· Improved multi-agency provision for pupils with SEN in schools.

Joint discussions are at an advanced stage between Health, Social Services and Education on multi-agency provision. Pilots have been established throughout the county for children with disabilities and further developments in joint working will take place in the coming year.

· Increased number of children having their special educational needs met within Hampshire schools (1% per year increase).

There was a 5% reduction in out-county placements between Sept 01 and Sept 02.

    LEA support for pupils with SEN

Recommendation 4b. In order to improve support for pupils with SEN:

work with mainstream schools to extend the range of training so that teachers become more confident in managing pupils with challenging behaviour.

    Actions

Responsibility Cliff Turner, Tim Cooke and Jack Cawthra

Start date

End date

 

Blue

1) Build behaviour awareness into induction programmes

a. Provide basic training in classroom management for newly qualified teachers (NQTs) as part of the county NQT induction programme.

    Now incorporated into the EDP 2002 -2007

    This training was delivered (and well received) in September 2001. A similar programme will be offered this September and will include not only NQTs but training for teachers in the first three years.

Sept 2001

Annually

b.

Green

c. Develop the understanding of headteachers about behaviour difficulties and support services as part of the revised induction programme for newly appointed headteachers.

    This was delivered in the Summer of 2001, but not in 2002, because of a congested induction programme. Liaison is underway to re-establish the input to the HT induction programme.

April 2001

Ongoing

Blue

2) Provide a range of training in behaviour management

a. Develop an integrated system of behaviour management courses with courses starting in January 2002.

    Now incorporated into the EDP 2002 -2007

    Several presentations of this course have been made. Feedback has been very positive.

Sept 2001

Jan 2002

b.

Blue

c. Provide training to senior staff in mainstream schools in the management of challenging behaviour so that they are able to support teachers who may need to restrain pupils.

    Now incorporated into the EDP 2002 -2007

    Several presentations of this course have been made. Feedback has been very positive.

Sept 2001

Ongoing

d.

Green

e. Develop and provide training for schools in the management of emotionally vulnerable pupils.

    Now incorporated into the EDP 2002 -2007and supported by Standards Funding

    Materials are being prepared for delivery during the academic year 2002/3. A multi-agency conference is also being planned involving the Wessex child psychiatrists group.

Sept 2002

Ongoing

f.

Blue

g. By targeting schools in need, and through widespread advertising, raise to 20 per year the numbers of teachers accessing the Diploma of Advanced Educational Studies (Emotional and Behavioural Difficulties) provided in Hampshire. Ensure these teachers are drawn evenly from across the county.

    37 teachers have enrolled on the course for September 2002, bringing the total involved to 48 teachers.

Sept 2001

Annually

h.

Green

i. Raise the awareness of school governors to training on behaviour management available to school staff and governors.

    The programme for governors is currently under review.

Sept 2001

Termly

j.

Green/ Amber

k. Work with Emotional and Behavioural Difficulty (EBD) schools to assist them to develop their outreach skills to the stage where they meet the established quality criteria. This will enable them to provide outreach services to mainstream and other special schools. Target to have 2 EBD schools accredited by Dec 2002 (action in response to additional comment in Ofsted report).

    Training is now available for special school staff to develop their outreach skills. The six schools concerned are developing their internal systems and will be encouraged to apply for accreditation when they are ready.

Already begun

Dec 2002 and
ongoing

l.

Amber

m. Co-ordinate outreach from special schools with other measures set out within the Behaviour Support Plan Action Plan (action in response to additional comment in Ofsted report).

At present only one special school is providing outreach - in Andover, for behaviour, as part of the multi-agency behaviour support initiative. Work on this is vital as part of progress towards accreditation.

Ongoing

 

6)

Blue

7) Strengthen support to schools on behaviour management

a. Improve support to schools across the county on a cluster basis e.g. through twilight meetings for school co-ordinators of behaviour where they can problem solve and share good practice.

    The programme has continued, is now available across the county, and is accessed as required in local areas.

June 2001

County-wide Jan 2002

b.

Blue

c. Special educational needs inspectors to have as a focus the identification and sharing of good practice in inclusion and behaviour management.

This is now an activity in EDP2

Sept 2001

July 2002

d.

Green

e. Outline special educational needs and behaviour support information at induction sessions for newly appointed headteachers. Establish this as a regular part of the induction programme.

Green

    This was delivered in the Summer of 2001, but not in 2002. Liaison is underway to re-establish the input to the HT induction programme.

April 2001

Ongoing

f. Make negotiated interventions in schools with the highest incidents of behavioural difficulties and/or permanent exclusions.

Behaviour Support Teams are prioritising demands on their time. A consistent approach for the teams in place will be established by the end of 2003.

Sept 2001

Ongoing

    Monitoring and evaluation

· Blue

    Blue

    Blue

    Green

    Black

    Blue

· Monitor source schools of participants and attendance numbers on training and development.

Done

· Quantitative and qualitative feedback from course delegates, their headteachers and from recipients of support services. Including their perceptions of their ability to deal with difficult behaviour after training and other support activities.

Ongoing

· 90% skills acquisition against set objectives after training participation.

· 25% increased take-up on training courses and other development opportunities on behaviour management.

Staffing shortages have created difficulties in some schools in being able to release staff. (Not a problem unique to behaviour training).

· Through feedback from linked schools, evidence of integrated and improved support between special schools and mainstream.

This evidence will be sought once linked schools are established.

· Minimum of six participants from each local office area per year on the Diploma course.

Take-up fine.

· Amber

· 25% reduction per year (for two years) in number of weeks out of school for emotionally vulnerable pupils from September 2002.

A baseline is being developed from 2002/3. These are challenging targets and will need considerable assistance from the Health Authorities to enable them to be achieved.

    Black

    Purple

    Green

    Blue

    Green

    Success criteria

· Increased school attendance of pupils who are emotionally vulnerable

Not yet sufficient time from baseline to make judgements.

· Reduced fixed-term and permanent exclusions where headteachers have participated in induction programmes.

Exclusions issues are significant in Hampshire at the moment, and induction training for HTs is unlikely to be a significant factor in securing their reduction.

· 50% improvement in teacher perceptions of their confidence and ability to deal with difficult behaviour after training.

Data is currently being gathered.

· All newly qualified teachers start teaching work informed in basic behaviour management techniques.

Now established for the first three years for an NQT.

· Reduced numbers of restraint incidents in participating schools (over two years - initially recording of incidents may increase with improved awareness).

EDMT received a detailed report on restraint in the autumn 2002. It showed a complicated pattern of recording and incidents, with some interdependency between the two.

    LEA support for pupils with SEN

Recommendation 4c. In order to improve support for pupils with SEN:

Work with the health authorities and primary health care trust to improve the speed and quality of medical advice for the statutory assessment of pupils with SEN

    Actions

Responsibility: Education officers (SEN) and principal special needs officers

Start date

End date

Blue

1) Establish baseline information

a. Monitor speed of completion of medical appendices by Health authority area to establish any particular issues

Done

Sept 2001

Jan 2002

b.

Green

c. Liaise with Health to identify any particular issues, share the monitoring data and problem solve to improve the process where necessary.

Liaison completed and consultation initiated.

Feb 2002

April 2002

Blue

2) Work with Health on any areas identified as needing improvement

a. Work with Health to revise materials for statutory assessment.

Blue

Completed

May 2002

July 2002

b. Provide briefings for Health staff who contribute to the assessment process.

Completed and being addressed under 1b above.

May 2002

July 2002

d.

Green

e. Evaluate briefings with Health and decide whether they should become regular updates. Schedule further programme of briefings if appropriate.

Green

Annual consultation to be established.

Sept 2002

Nov 2002

f. Establish a system for regular monitoring of medical appendices, checking quality and timeliness and giving feedback to health managers.

Done on an ongoing basis as required.

April 2002

Ongoing

    Monitoring and evaluation

· Green

· Analysis of statutory assessments extending beyond the 18 week deadline to establish how many were delayed by lateness or poor quality of medical advice. This information to be shared with Health.

Initial review completed and work continues on an ongoing basis as required..

· Green

    Green

    Green

    Green

· Briefing sessions for Health delivered within the timescales set and evaluated with consideration given to repeating them if they proved useful.

Done

· Revised materials for statutory assessment produced to deadline.

Done

Success criteria

· Improved quality of content of medical advice and dialogue with medical professionals.

Quality being monitored and will be fed back to PCT representatives in April 2003.

· 10% reduction in assessments (in two years) delayed by late arrival of medical advice.

Difficulties with implementation of the SEN database have hampered this work, but evaluation is due in July 2003.

    The LEA and pupils' access to education

Recommendation 5a. In order to improve pupils' access to education:

improve asset management by more accurately assessing the requirements for repair, replacement and improvement expenditure against budgetary provision

    Actions

Responsibility: Mike Fitch and Bob Eardley

Start date

End date

1) Agree expenditure and funding priorities with schools

a.

Blue

b. Repairs and maintenance: work with headteacher liaison groups and individual schools to agree priorities for expenditure, and funding sources. Establish this process as an annual activity at the headteacher groups and at regular client meetings.

This activity is established as part of the Asset Management Plan group, including primary and secondary HTs and governors. They agree broad priorities and the management partnership meetings then deal with the detail.

Sept 2001

July 2002

c.

Blue

d. Replacement and improvements: work with individual schools to develop agreed priorities. Establish this process as an annual activity at the regular client meetings.

This is handled through management partnership meetings. There is a newsletter to schools to publish priorities and programmes of work. There is also an annual meeting with primary and special and two annual meetings with secondary HTs.

Sept 2001

July 2002

e.

Blue

f. Suitability (improvement) and sufficiency (provision of school places) elements of the Asset Management Plan: work with headteacher groups and dioceses to

        i. prioritise categories of project within the overall programme;

        ii. identify individual schemes for inclusion in the programme; according to priority need based on Asset Management Plan school survey data.

Consultation work ongoing, with consultation on priorities for the 2004 tranche funding, and reports back to DfES.

Sept 2001

Ongoing

g.

Blue

h. Agree with headteachers and governors the use of school delegated capital funding for addressing Asset Management Plan priorities.

This has been addressed through overall policy issues regarding the protocol for schools working with the LEA on the use of devolved capital. At school level the strategic planning unit authorises expenditure.

Sept 2001

Ongoing

2) Keep the Asset Management Plan information up to date

a.

Blue

b. Refine and update the school condition survey information through five-yearly assessments.

PBRS began a 20% annual re-survey in 2002/3. The same is being undertaken for suitability criteria.

Sept 2001

Ongoing

3) Increase understanding of responsibilities

a.

Blue

b. Work with headteacher representative groups and with individual schools and the LEA staff to increase awareness of the split of financial responsibilities for sites and buildings repairs and maintenance between the LEA as landlord and individual schools.

As for 1 above.

Sept 2001

July 2002

    Monitoring and evaluation

· Blue

    Blue

    Blue

    Blue

    Blue

    Blue

    Blue

· Regular reviews by the Asset Management Plan schools consultation group.

Ongoing

·

· Regular reviews through primary and secondary headteacher liaison groups.

Ongoing

· Reviews at regular meetings with individual schools.

Ongoing

· Feedback from schools through existing customer services arrangements on their level of satisfaction and understanding of the arrangements.

Ongoing

· Monitoring of complaints.

Formal feedback is arranged at the end of each project.

    Success criteria

· Schools and LEA staff clear about the split of repairs and maintenance responsibilities between the school and LEA as landlord.

A detailed split of responsibilities is contained in the repair and maintenance SLA. Copies have been provided to all schools and relevant staff. Staff briefings were held earlier in the year; these were evaluated as having successfully met their objective of improving understanding of the split of responsibilities.

A random telephone survey of schools last year, asked schools if they were clear about the split of responsibilities; over 90% responded that they were.

· Schools and LEA staff clear about the priorities for major repairs and maintenance initiatives and funding sources.

Priorities are clearly detailed in the AMP policy statement which was drawn up in partnership with schools representatives. These priorities are reinforced through regular written articles in Property Matters (a schools newsletter) and at termly meetings with HT representatives. The priorities are included in the annual plan for property management which is approved by the Leader of the Council. The annual plan establishes the high level objectives which feed into team and individual objectives.

    Blue

    Blue

Major planned programmes are published and in some cases presented to groups of schools. Feedback about the quality of information and project outcomes has been very positive.

· Headteachers and governors feel able to help influence priorities.

Communication and joint discussion is encouraged through the mechanisms already outlined. Meetings between property officers and individual schools are held at least annually and the focus of the meeting is to review and agree joint priorities. Evidence of the success of the relationship is the absence of any conflicts between the LEA and schools on what constitutes are repair and maintenance priority.

· Opportunities are maximised for schools and the LEA to address Asset Management Plan priorities through the use of schools' delegated capital funding.

Over the course of the last 5 months schools have contributed almost £4m of their devolved funding to jointly funded projects with the landlord. Opportunities to maximise such investment are discussed at the annual meetings mentioned above.

    The LEA and pupils' access to education

Recommendation 5b. In order to improve pupils' access to education, improve support for attendance by:

further developing schemes to recruit and retain high quality education welfare workers

    Actions

Responsibility: John Heath

Start date

End date

1) Increase the number and quality of recruits

a.

Blue

b. Review advertising strategy by assessing success of the media currently in use and exploring alternative arrangements. Contact other LEAs to compare strategies and seek staff suggestions.

    EWS is working with the County Council advertisers to maximise recruitment advertising value, and this is having a positive impact. Visits to other authorities have investigated approaches to this problem elsewhere.

Sept 2001

Dec 2001

c. Promote recruitment to the service in higher education establishments in Hampshire and the surrounding counties.

EWS is giving talks in higher education establishments and promoting student placements to encourage strong links between Hampshire and colleges in the region.

Sept 2001

Ongoing

d.

Blue

e. Explore the possibility of recruiting education welfare service assistants where qualified staff cannot be recruited.

Additional EWS posts have been created through LPSA pump-priming funds in schools in areas of relative social deprivation.

Jan 2002

March 2002

f. Introduce a more rigorous interview process, e.g. by incorporating Occupational Personality Questionnaires (OPQs), a case study/presentations as standard practice.

HTs are being involved in all interviews and the interview process has been strengthened with presentations and use of OPQ tests.

Sept 2001

Ongoing

2) Make further efforts to improve the retention of staff

a.

Blue

b. Complete the restructuring of the Education Welfare Service in order to give enhanced career structures and improved salaries.

Completed - report to Education Committee.

   

c.

Blue

d. Benchmark the Hampshire salary and benefits package structure against similar authorities.

This has been undertaken as part of the Best Value review.

   

e.

Blue

f. Ensure all education welfare officer performance reviews focus on their professional development needs and support post-qualifying professional development of staff.

All EWS staff are having regular performance reviews with a focus on competencies.

Sept 2001

Ongoing

g.

Blue

h. Improve the working environment for education welfare officers and review the use of accommodation.

Review completed. Building work undertaken in Winchester and Basingstoke offices and health and safety issues addressed.

Sept 2001

Sept 2003

i.

Green

j. Increase administrative support staff as resources allow.

Growth bid for 2002/3 not given, and will not happen for 2003/4. However, administrative support has been increased from vacancy management.

Sept 2001

Sept 2003

k.

Blue

l. Consider flexible pay and benefits packages and support job sharing and part-time working as part of the corporate review of pay and benefits.

This has been incorporated into the County Council role profiling exercise. EWO posts were selected as benchmark posts.

Sept 2001

Sept 2002 and ongoing

m.

Green

n. Increase IT provision by providing one laptop computer for each education welfare officer and suitable IT hardware for each team, ensuring full compatibility with IT2000.

Laptops have been provided for half of the EWS staff with training. Each team is now fully IT2000 compatible.

Sept 2001

Sept 2003

o.

Green

p. Provide IT training for staff in basic word processing, spreadsheet and e-mail packages and the windows environment.

This is ongoing with the provision of laptops.

Sept 2001

Sept 2003

    Blue

    Blue

    Blue

    Blue

    Blue

    Monitoring and evaluation

· Seek staff feedback on recruitment and retention initiatives via performance reviews and questionnaires.

A questionnaire to staff formed part of the Best Value review.

· In summer 2002, establish headteacher views on the quality and availability of the service and compare with information currently available.

A questionnaire was sent to all schools.

· Use exit interviews to build a picture of reasons for leaving.

An established process.

· Principal Education Welfare Officer to monitor the number of applications received from newly qualified social workers against benchmark of numbers for the summer term 2001.

Ongoing.

· % staff turnover and staffing profile (Full-time, part-time, numbers in posts etc) reported to Inclusion Branch Management Team on an annual basis.

Included in the annual report to BMT.

· Blue

    Blue

    Black

    Green

    Blue

    Blue

    Amber

    Blue

    Black

· Use performance reviews on an annual basis, or by exception, to assess individual training needs and evaluate the success of training and development to date.

Part of the annual process.

· Benchmark salaries and total pay and benefits packages annually against those of like counties.

Part of the Best Value review and Pay and Benefits work.

    Success criteria

· Schools' satisfaction with the level and quality of service from the Education Welfare Service is improved.

This will be reported in the Best Value review, due to be completed in March 2003.

· Fully staffed service with experienced staff group and turnover reduced to 10% per annum.

The vacancy rate is improving, but the service is not yet fully staffed (currently 2.5 vacancies).

· Staff perceive a positive career and personal development path for them.

A new post of senior EWO was established in the reorganisation of the service. Performance reviews have been changed to place greater emphasis on competency criteria, and arrive at a more consistent evaluation. The Best Value review questionnaire of staff showed that 6 our of 8 senior EWOs were positive about their career path.

· All education welfare officers able to access IT2000 from a computer convenient to their working day.

All staff have access to IT2000 and laptops are available.

· All education welfare officers have access to support staff time on a ratio of four education welfare officers to one member of the support staff.

Not yet achieved owing to budgetary constraints, however administrative support has been increased through vacancy management. The Best Value review is also considering this.

· Hampshire education welfare officers salaries are benchmarked with those of similar counties including neighbouring LEAs.

Salaries against benchmark authorities are at the average.

· Average retention of new starters in the Education Welfare Service increases to three years.

Not yet 3 years from benchmark.

    The LEA and pupils' access to education

Recommendation 5c. In order to improve pupils' access to education improve support for attendance by:

ensuring the updating of guidance to schools so that there are consistently effective procedures for early identification, referral and follow-up of absence.

    Actions

Responsibility: John Heath

Start date

End date

Green

1) Review content, style and production of written guidance materials

a. Publish revised guidance for schools on maintaining and improving attendance including guidance on referral criteria.

    The consultation process has taken longer than envisaged, but the revised guidance should be published early in the Spring term.

Sept 2001

Jan 2002

b.

Green

c. Publish the revised guidance and SLA on the web in the new `school library' and ensure all updates to the web documents are notified to schools with links to the site from e-mails.

The guidance will go onto the web early in the spring term.

Jan 2002

Ongoing updating

d.

Blue

e. Issue a termly `good practice' news-sheet for schools which draws on successful approaches and innovative ideas in schools across the county and beyond. Publish this on the web in the school library area.

The first new sheet was published in the autumn term 2002 and put onto the web.

Nov 2001

Jan 2002 for first issue

2) Review the support given to schools in dealing with absence

a.

Blue

b. In consultation with headteachers, review the support given to schools on absence matters through the Education Welfare service level statement.

The Best Value review is addressing this issue. The BV questionnaire to schools consulted on the formula for distribution of support and the majority of schools were in favour of maintaining the status quo.

Sept 2001

Jan 2002

c.

Blue

d. Through revised induction processes and revised guidelines for staff, establish consistency throughout the Education Welfare Service in how referrals are followed up.

This is now consistent across the county through the revised induction process and the revised guidance for schools to be published in the spring term.

July 2001

Sept 2001

e.

Blue

f. In view of the almost linear correlation between absence and pupil performance shown by the audit for Education Development Plan 2, work to raise the profile of absence issues with Hampshire headteachers and governing bodies.

A Best Value action is to integrate training on absence into the governor training calendar. A newssheet for all schools has been established to raise good practice awareness. Each of the 89 schools asked by the DfES to set targets for attendance improvement school has been given the opportunity to work with EWS on attendance planning and target setting .

Sept 2001

July 2002 and ongoing

g.

Blue

h. Education Welfare Service managers to attend local headteacher and governor meetings to raise the profile of absence issues within schools, share good practice and listen to feedback.

Team managers have met with some local groups and have offered to attend other meetings.

Sept 2001

Ongoing

    Monitoring and evaluation

· Blue

    Blue

    Blue

    Blue

    Blue

    Amber

    Green

    Green

· On a termly basis, measure rates of authorised and unauthorised absence at individual, group and whole school level in order to track progress in reducing absence.

This is undertaken annually on a county wide level as schools are not willing to work on a termly basis. However, in target schools with unauthorised absence is at its highest, rates are being monitored on a termly basis.

· Report referral levels, period between first absence and referral and speed of response to Inclusion Branch Management Team on a annual basis.

This is part of the EWS annual report to BMT.

· Feedback from headteacher and governor groups that shows a raised awareness of the importance of tackling absence.

Attendance is a regular item on Inclusion standing committees for primary and secondary HTs.

· Regular school attendance register checks by education welfare officers to ensure appropriate referrals.

EWOs check registers as a matter of course on school visits.

· Compare Hampshire absence rates with those of statistical neighbours and report to Inclusion Branch Management Team and Education Department Management Team annually.

This is done routinely as part of reporting on Best Value and CPA performance indicators.

    Success criteria

· Reduction in total and unauthorised absences from school.

There has been a national increase in absence in the last year, and Hampshire has followed that trend. Our position in relation to statistical neighbours has slipped slightly in the 2001/2002 data. The EWS is focussing on schools with higher than average levels of absence and supporting school action plans.

· Early and consistent absence referral and follow-up across the county.

All schools are being encouraged to refer at the right time. The new publication, maintaining and improving attendance gives clear guidance on referrals and benchmarks for referral points.

· All school confident in their use of the absence procedures and moving towards consistent implementation.

The Best Value questionnaire suggests the majority of schools are happy with the referral system.

The LEA and pupils' access to education

Recommendation 5d. In order to improve pupils' access to education, improve support for attendance by:

improving planning to detail how schools with the greatest need are identified, supported, monitored, challenged and provided with feedback on the effectiveness of their procedures.

    Actions

Responsibility: John Heath with Education Welfare Service Management Team

Start date

End date

1) Improve Education Welfare Service planning systems and processes

a.

Blue

b. Review all planning systems, processes and documentation for the Education Welfare Service work on attendance, particularly for the support aimed at schools with greatest need.

The new publication - Maintaining and Improving Attendance - which will be sent to schools early in the spring term, offers robust advice on target setting. EWO resources and support for schools now have greater focus on schools with greatest need.

Sept 2001

July 2002

c.

Blue

d. Revise the Education Welfare Service Development Plan so that it incorporates targets within the Education Development Plan and includes timescales, actions, outcomes and a clear strategy for helping schools reduce levels of unauthorised absence (action in response to additional comment in Ofsted report).

The Development Plan has been revised and published.

June 2001

Jan 2002

e.

Blue

f. Identify schools with higher than Hampshire average levels of absence. Provide additional support to them in fully implementing the revised procedures and in developing and implementing an action plan.

Done - support is ongoing.

Sept 2001

Oct 2001 and ongoing

g.

Blue

h. Review the agreed formula with schools for the allocation of education welfare officer time to support attendance.

Part of the Best Value review.

Sept 2001

Jan 2003

i.

Green

j. Establish use of tracking systems to monitor pupil attendance. Develop a module to analyse pupil attendance records within the new common pupil record (IMPULSE) system.

There are plans to incorporate a field into the IMPULSE system to enable this tracking to take place. In the meantime, every attendance referral is being tracked.

Sept 2001

Jan 2002

k.

Blue

l. Use outcomes of the tracking system to feed into performance reviews of education welfare officers.

Blue

This is underway. The impact of individual EWO work can be assessed.

Jan 2002

July 2002

m. Establish processes to monitor the attendance of children in public care and other vulnerable groups.

This is in place - the Looked After Children database can track all LAC attendance.

Sept 2001

Oct 2001

n.

Green

o. Undertake a Best Value review of the Education Welfare Service, exploring the core functions, delivery mechanisms and quality control arrangements for the service.

To report to Policy and Resources Committee in March 2003.

Sept 2001

April 2003

Blue

2) Establish a culture within schools of target setting for absence

a. Establish with schools challenging LEA targets on attendance for Education Development Plan 2.

Targets were set within EDP2.

Sept 2001

Dec 2001

b.

Green

c. Work with schools annually (within the strategy set out in the service plan) to set challenging targets for attendance at individual school level.

Work is ongoing with the 89 schools identified by the DfES as needing to set targets.

Sept 2001

July 2003

    Blue

    Blue

    Blue

    Blue

    Blue

    Monitoring and evaluation

· Revised Education Welfare Service development plan and associated processes and documentation reported to Inclusion Branch Management Team January 2002. Thereafter, an annual evaluation report including key data on the performance of the Education Welfare Service.

Done

· Attendance rates at pupil, school and LEA level monitored annually and reported to Inclusion Branch Management Team.

Ongoing

· Allocation of education welfare officer time to schools with greatest need monitored annually by the service management team.

Established process.

· Head of Education Welfare Service to report annually to Inclusion Management Team and through Education Development Plan 2, monitoring arrangements on the attendance of children in public care and other vulnerable groups.

Ongoing

· Termly reporting to Inclusion Branch Management Team on the progress of schools against their targets.

    Blue

Where schools have set targets, progress against these is reported.

· Feedback from schools on the quality and quantity of support for attendance received from the Education Welfare Service through Inclusion Branch Standing Committees.

Through these processes and also through the Best Value review.

    Amber

    Blue

    Blue

    Success criteria

· Improved attendance rates for individual pupils, schools and the LEA as a whole.

There has been a national increase in absence in the last year, and Hampshire has followed that trend. Our position in relation to statistical neighbours has slipped slightly in the 2001/2002 data.

· Education Welfare Service time focused in line with greatest need.

Yes- through the SLA processes.

· All Education Welfare Officers and schools clear about the planning and processes to support schools with greatest need of support on attendance.

Yes- through the SLA.

    The Lea and pupils' access to education

Recommendation 5e. In order to improve pupils' access to education improve support for pupil behaviour by:

ensuring that the revised Behaviour Support Plan has a detailed action plan for each activity.

    Actions

Responsibility: Tim Cooke, Cliff Turner and Jack Cawthra

Start date

End date

1) Write, consult on and publish detailed action plans for each activity

a.

Blue

b. Draft action plans to include responsibility, target groups, success criteria and monitoring and evaluation arrangements.

All achieved.

Sept 2001

Dec 2001

c.

Blue

d. Consult with schools through representative headteachers on the Social Inclusion Steering Group.

Done

Dec 2001

Feb 2002

e.

Blue

f. Publish final version on the web in the `school library' and make available as hard copy on request. Notify all schools of its publication and location.

Done

April 2002

May 2002

    Blue

    Green

    Monitoring and evaluation

· Termly review of progress against action plans by Inclusion Branch Management Team and the Social Inclusion Steering Group.

Ongoing

· Annual review of progress against the Behaviour Support Plan by Education Department Management Team.

Due in Spring term 2003. However, many of the BSP activities have already been reported to EDMT as part of the Education Development Plan monitoring report.

    Blue

    Blue

    Blue

    Success criteria

· Clear action plans in place to support Behaviour Support Plan activities.

Done

· Delivery of Behaviour Support Plan objectives and targets.

Ongoing - most are to time

· All partners support the action plans and know how to access them.

Yes

    The LEA and pupils' access to Education

Recommendation 5f. In order to improve pupils' access to education improve support for pupil behaviour by:

more consistently applying the criteria for triggering and accessing support for pupils with complex behaviour difficulties.

    Actions

Responsibility: Tim Cooke, Jack Cawthra and Cliff Turner

Start date

End date

Green

1) Review criteria and processes for triggering, accessing and providing support

a. Through discussion with representative headteachers, establish areas of concern or confusion within the school community relating to the criteria and the support for pupils with complex behaviour difficulties.

April 2001

Oct 2001

b.

Amber

c. In the light of 1a), review criteria and procedures to ensure consistent triggers for early consultation, identification, assessment and intervention, using available pupil and school related data. Ensure this also contains clear guidance for schools about who to contact to make referrals.

    This is a complex task, and is taking longer than initially anticipated due to cultural and technical issues. The end date has been revised from Jan 2002 to Jan 2004.

    New criteria and procedures are now out in draft form and being piloted in one area. Schools have had clear guidance about who to contact to make referrals.

    The achievement of greater consistency in the triggers has been held up by delays in developing IT systems to link to the common pupil record database. Systems are currently based around area databases and this will take some time to resolve.

Sept 2001

Revised date: Jan 2004

d.

Green

e. Develop and establish a reporting system to monitor referrals to the Behaviour Intervention Service, the speed of response and outcomes.

    A new system is in place.

 

July 2002

f.

Green

g. Publish the referral processes and criteria on the web in the `school library' area and publicise to schools and relevant LEA support services. Emphasise the need to follow the criteria to ensure consistency of approach. Provide hard copies on request.

    This will follow once the draft processes and criteria document (b) is finalised.

Jan 2002

Jan 2002

Revised

March 2003

h.

Green

i. Ensure teams are briefed so that all staff can operate to the criteria and can advise schools appropriately.

This is happening, and is the responsibility of the newly appointed county behaviour support team co-ordinator.

Jan 2002

March 2002

j.

Green

k. Ensure the criteria and response procedures are part of the induction programme for relevant staff.

Now an ongoing part of the induction process.

Jan 2002

Ongoing

2) Enhance the information on the support services available

a.

Green

b. Produce a cross-referenced directory of support services for each Local Education Office, and publish on the web (as above) making hard copy available on request.

    The new Behaviour Support Teams have been focussing on services and the development of networks. The directory will be produced on an incremental basis as these contacts and networks develop.

Sept 2001

Revised date: July 2003

c.

Green

d. Ensure new headteachers are made aware of the information on support services and the criteria as part of their induction programme.

    This was delivered in the Summer of 2001, but not in 2002, because of a congested induction programme. Liaison is underway to re-establish the input to the HT induction programme.

June 2001

Ongoing

    Amber

    Green

    Green

    Green

    Green

    Monitoring and evaluation

· Feedback from schools and other client groups on EBD criteria and their confidence in accessing support services - through Inclusion Branch Standing Committees and the Social Inclusion Steering Group.

The delayed introduction of the pupil database module has extended the deadlines.

· Reports to Inclusion Branch Management Team termly on the numbers of school referrals to the multi-disciplinary behaviour intervention teams, and the response rates.

Termly reports are being established.

    Success criteria

· Schools well informed about the support available and how to access it.

Understanding is developing as a result of the activities outlined above.

· Schools clear about the criteria and whom they should contact for referrals.

The draft criteria are now available to schools and schools are clear on contacts for referrals.

· Consistent response by LEA support services

This is improving steadily through the development of the Behaviour Support Teams and the work of the county co-ordinator

    The LEA and pupils' access to Education

Recommendation 5g. In order to improve pupils' access to education improve support for pupil behaviour by:

ensuring a better co-ordinated approach to supporting schools in the management of behaviour

    Actions

Responsibility: Sheila Arney and Jack Cawthra

Start date

End date

Blue

1) Review delivery structures

a. Restructure the Education Other Than at School service to incorporate the Behaviour Intervention Services in existing pilot areas.

Done

Sept 2001

April 2002

b.

Green

c. Rollout Behaviour Intervention Service outreach services within the Education Other Than at School service in other parts of Hampshire. The speed of rollout will be dependent on available resources.

Behaviour Support Teams are now established in four areas. In two further areas there are team leaders, but no budget for full teams, and in one area no structures are yet in place.

Jan 2002

Dec 2004

2) Review processes and management arrangements for service delivery

a.

Green

b. As the restructurings are implemented, ensure that processes and procedures for staff are developed and consistently implemented.

This is being achieved through the work of the recently appointed County Co-ordinator for the Behaviour Support Teams. That post is responsible for developing good practice and consistency of service provision across the teams.

Sept 2001

Revised date: Dec 2004

c. Ensure a clear co-ordination role for the Education Other Than at School management team through monitoring of performance indicators and regular reviews of practice and process with frontline managers.

Termly reports are coming onstream and co-ordination work on databases is ongoing.

Jan 2002

Ongoing

d. Ensure all staff are briefed on the new working arrangements, and include this briefing as part of the staff induction process.

Ongoing.

March 2002

Dec 2003

Blue

3) Involve and inform schools and other partners

a. Consult with schools and other partners on the local service delivery structures and processes that will operate within a county framework.

Green

The restructuring to form the Behaviour Support Teams was subject to extensive consultation and has now been implemented..

Sept 2001

April 2002

b. Brief schools on new arrangements as they are implemented, through presentations and written materials. Publish on the web in the `school library' and make available as hard copy on request. (Implementation schedule dependent on the availability of accommodation).

Regular updates and feedback are made to representative groups.

Jan 2002

Dec 2003

Green

4) Improve provision for pupils who have no school place

a. Through restructuring of the Education Other Than at School service provide improved support for the reintegration of pupils into mainstream schools and provide full-time education for all permanently excluded pupils (action in response to additional comment in Ofsted report).

Re-integration rates remain an important issue. EOTAs is working towards the targets set out in the Education Development Plan 2002 -2007.

Sept 2002

July 2003

b.

Green

c. Establish re-integration panels with area groups of headteachers to plan and implement reintegration for pupils identified as being ready for this (action in response to additional comment in Ofsted report).

Re-integration panels have been established in Andover and Basingstoke and there have been briefings to headteachers in Area 2 and Fareham and Gosport. Work to increase the geographical coverage of panels is continuing, and relies on active co-operation of headteachers.

Sept 2002

July 2003

d.

Blue/ Green

e. Establish current reintegration rates within six months of exclusion as a baseline and improve this by 25% in the 2002-3 academic year and then 20% per annum for the next two years.

The baseline is established. Work to improve re-integration rates is on-going.

Sept 2001

Sept 2004

    Monitoring and evaluation

· Green

    Green

· Analysis of referral and response reported to Inclusion Branch Management Team on a termly basis.

This is about to become a regular report to the BMT.

· Termly reporting of reintegration rates and average lengths of stay in Education Other Than at School by Heads of Service (Pupils) to Inclusion Management Team.

    Green

    Green

    Green

    Green

    Red

    Blue

    Blue

    Green

    Blue

A pattern of reporting the Executive member for Education has been established and this data will be seen by Inclusion Management Team prior to this.

· Termly reports to Inclusion Management Team on the percentage of excluded pupils receiving full-time education and the percentage of full-time education being provided for the remainder.

This was incorporated in the report on Inclusion to the Executive Member for Education.

· Termly consultation on the progress of multi-agency support teams with headteachers through Primary and Secondary Inclusion Steering Committees and Special Schools Executive.

Ongoing

· Termly consultations with multi-agency partners to identify areas for improvement in service co-ordination and delivery.

Ongoing

· Termly review of progress on restructuring and quality of support services for behaviour by the Social Inclusion Steering Group.

Ongoing

    Success criteria

· Fewer children permanently excluded from schools, in line with existing Hampshire targets.

Following 5 years of year-on-year reductions in permanent exclusions in Hampshire, figures rose (by 50%) in 2001/02. This reflects a rise nationally linked to changes to legislation and guidance by central government, and to recruitment and retention of staff issues

· Reduction in the time spent out of school by excluded pupils in Key Stage 1 to Key Stage 3.

Baseline established. Monitoring will ongoing from September 2002

· Improvement in reintegration rates.

Baseline established. Monitoring ongoing from September 2002.

· Better co-ordinated and consistent responses to schools in order to support behaviour management.

New referral forms and procedures agreed and circulated to schools during Autumn Term 2002.

· Full-time tuition for all permanently excluded pupils, and in conjunction with schools, for those who are temporarily excluded from school for more than 15 days.

Done.

    The LEA and pupils' access to education

Recommendation 5h. In order to improve pupils' access to education:

improve the support for minority ethnic pupils by collecting appropriate data on the achievement of these pupils to ensure that support can be more accurately targeted.

    Actions

Responsibility Bilingual learners: Liz Statham,

Travellers: Gill May

Children in Public Care: Denise Freeman and Linda Farrow

Start date

End date

Green

1) Collect and process appropriate data

a. Incorporate appropriate fields for ethnic minority and traveller pupils within the common pupil record (Impulse system). Base the ethnic minority sub-groups on the breakdown required by Education Development Plan 2 guidance.

    Fields for ethnic minority pupils are now established, in accordance with DfES guidelines.

Fields for traveller pupils are under development.

Sept 2001

Feb 2003

b.

Blue

c. Establish a database which has accurate information regarding children in public care, their placements, both residential and educational, and their academic achievements (action in response to additional comment in Ofsted report).

Done.

Jan 2002

Sept 2002

d.

Blue

e. Undertake detailed analysis of the data on children in public care and monitor their achievements over time (action in response to additional comment in Ofsted report).

This is ongoing work - ambitious targets for the achievements of children in public care are included in the PSA and progress against targets is being monitored closely.

July 2003

Ongoing

f.

Green Blue

g. Obtain baseline, Key Stage 1, 2 and GCSE results for ethnic minority (all sub-categories) and traveller pupils.

    There are no baseline figures for Ethnic Minority pupils yet, work is underway.

    Key Stage 1, 2 and GCSE results available are available for Travellers - baseline results are collected by TES from school's SEN departments.

Sept 2001

Feb 2002

h.

Blue

i. Provide accurate Hampshire returns to DfES from the improved data.

    Done

Sept 2001

Feb 2002

j.

Green

k. Develop the use of value added data to track the value added for ethnic minority and traveller pupils against the averages for a school and for all schools.

Jan 2002

Sept 2003

l.

Blue

Blue

m. Continue to analyse the termly Traveller questionnaire to schools.

    Termly questionnaire sent to schools

Sept 2001

Ongoing

n. Include the Bilingual Support Service collection and analysis of ethnic minority data in the established Hampshire Inspection and Advisory Service monitoring of the service.

    External inspectors working on monitoring of service.

Jan 2002

April 2002

o.

Blue

p. Monitor 18 schools not involved in the ethnic minority achievement project on race equality 2001 - 2002, including collection and analysis of ethnic minority performance data.

8 schools monitored.

Jan 2002

April 2002

Blue

2) Provide training for staff

j. Develop and implement training for administrative staff in schools on ethnic minority categories and data collection and on Traveller issues.

    Training carried out summer term 2002 (ethnic minority and traveller)

Sept 2001

July 2002

3) Management activities in response to the performance information

k.

Green

l. Develop a tracking system for all ethnic minority pupils at risk of underachievement.

    Models for schools to use being developed.

April 2001

Sept 2003

m.

Blue

n. Include ethnic minority and traveller achievement in School Improvement Branch targets.

Targets included in EDP.

Secondary schools targeted with an aim to incorporate Gypsy culture in Citizenship

    TES working with Ian Massey

Oct 2001

Feb 2002

o.

Amber

p. Work with attached inspectors to review ethnic minority performance in the Bilingual Learners Support Service `Achievement Project' schools.

    This work has been delayed, mainly because national PLASC data has not been available. This data will be available in 2003, and will enable closer workings with Standards and Improvement Branch to establish performance of ethnic minority pupils in individual schools.

Jan 2002

April 2002

q.

Amber

r. Establish processes for attached inspectors to monitor ethnic minority and traveller performance in all schools. This will be achieved through development of the electronic school file system.

    Regular reporting on the electronic school improvement file should be established by April 2003. The further developments of PLASC data etc outlined above should allow this work to be taken forward in 2003 with attached inspectors.

Jan 2002

April 2003

Green

Implement DfES criteria for supporting travellers - A national recommendation for travellers.

Government has not implemented the scheme but DfES is devising a formula to allocate the Traveller achievement grant . HTES responded 10.09.02

Sept 2001

June 2002

    Monitoring and evaluation

· Green

    Blue

· Annual report on children in public care to Education Department Management Team and Education Policy Review Committee.

    Success criteria

· Improved information and analysis leading to improved monitoring and achievements for children in public care.

    As a result of the Ofsted Action Plan a one year development plan was produced for the education of children and young people in public care. This development plan had 21 areas for action, the outcomes will be reported to CAPLAC (the Corporate Action Planning for Looked After Children, which consists of representatives of Social Services, Education and Recreation and Heritage Departments and involves a number of relevant officers from each.) in the Autumn term.

    Simultaneously CAPLAC will receive a further Development plan for September 2002 to August 2005 which builds upon the successes to date, identifies any further action necessary as a result of reviewing the first plan and sets targets for the next three years.

    Targets will be established in the following areas:

    Establishing joint working at all organisational levels.

    Ensuring data is useful accurate and shared.

    Establishing effective procedures and ensuring good practice.

    Providing advocacy and support for young people, and their carers.

    Ensuring that those working with looked after children are adequately trained and supported.

    To raise the public profile and create positive attitudes towards young people in public care.

    Green

    To ensure young people in public care are involved in developing and reviewing services for them.

· Attendance and achievements of children in public care improve.

    Targets in the EDP and PSA aim for considerable improvement in achievements for children in public care over the next few years.