Archived decisions
Hampshire County Council North East Hampshire Area Transportation Strategy Panel 4 February 2003 Capital Programme - Update Report of the Director of Environment |
Item 7 |
Contact: John Buckett, ext 6599
1. Summary
1.1 The County Council's Environment Capital Programme was approved by the Executive Member for Environment on 24 January 2003. The report included a revised integrated transport programme for 2002/03, a new programme for 2003/04 and proposed that all other integrated transport schemes be reassessed for possible inclusion in the 2004/05 programme (see attached appendix for North East Hampshire Transport Strategy (NEHTS) schemes).
2. Background
2.1 Hampshire County Council's first full Local Transport Plan (LTP) was produced in July 2000. It set out county-wide and area strategy objectives and targets, and a proposed five year plan for transport investment. The Government settlement letter, in December 2000, acknowledged Hampshire's LTP as one of the best in the country. The settlement letter allocated funding levels, definite for 2001/02 and indicative for the other four years of the programme.
2.2 The funding allocated under the new LTP system is at a much higher level than previously for integrated transport, and is no longer ring-fenced for certain topics or areas. For 2001/02 two years were available to spend the allocated funding money, but from 2002/03 the Government has moved to a one year spending regime.
2.3 The combination of the above factors has led to integrated transport spending as set out in the table below. Integrated transport spending includes investment in area transport strategies, casualty reduction and county-wide programmes.
Government Funded County Council Capital Expenditure on Integrated Transport
Year |
Spending (£'000) |
|
1998/99 |
2,894 |
Actual |
1999/00 |
2,545 |
Actual |
2000/01 |
4,936 |
Actual |
2001/02 |
7,775 |
Actual |
2002/03 |
18,600 |
Planned |
2003/04 |
14,393 |
Maximum |
2.4 The above table does not include expenditure on accepted major transport schemes (over £5 million) as these are separately funded, but does include preparatory and all other costs until a scheme is accepted by the Government.
2.5 The 2002/03 figure is particularly high because funding was carried forward from 2001/02. Such a carry forward is no longer allowed and from 2003/04 onwards funding is expected to be in line with the LTP settlement awards.
3. 2002/03 Programmes
3.1 The initial 2002/03 programmes for area transport strategies were set at a high level so that there was a good chance of achieving the spending target even if, for any reason, schemes were delayed. The County Council also wanted to be in a position to take advantage of any additional funding that might become available in 2002/03 or 2003/04 by having schemes prepared. It was also proposed that the A3 Bus priority scheme in Havant district would be taken up by the Government as a major scheme from 2003/04. It was important therefore to have enough schemes ready to take advantage of any funding released, should the A3 costs be covered elsewhere.
3.2 In the event, progress in 2002/03 has been such (together with increased consultation and construction costs of ongoing schemes) that the County Council had committed (by December 2002) sufficient projects to cover the £18.6 million available for 2002/03 spending. It has therefore been necessary to limit the 2002/03 programme to a total value of £18.8 million and defer the remainder of the programmed schemes to a 2003/04 or later start year. The implication for the timing of NEHTS is set out in the attached appendix.
4. 2003/04 Resources and Programme
4.1 The County Council has been allocated £14.39 million for integrated transport but, as yet, the A3 scheme has not been accepted for major scheme funding. Unless extra funding is found, it will be necessary to accommodate any new A3 work from the £14.39 million, as well as an expected £8 million of commitments carried forward from 2002/03, the new 2003/04 programme spend and the preparation costs of future schemes.
4.2 The consequence is that the funding available for schemes programmed to start in 2003/04 has been set at £9.39 million. Some of these schemes will be put on hold to start late in the year so that spending is kept within the allocation level pending a decision on the A3 scheme. The 2003/04 NEHTS programme, which includes developer and other externally funded schemes, is set out in the attached appendix.
5. 2004/05 and Beyond
5.1 No programme has yet been prepared for 2004/05. The Executive Member for Environment has requested that all schemes in the previous four year capital programme (but now not programmed in 2003/04 or before) are assessed in terms of their likely contribution towards LTP and corporate objectives. Following this assessment a report will be presented to the Environment Policy Review Committee on 9 July 2003 setting out a revised Capital Programme for each of the strategy areas.
6. Scheme Preparation and Design 2003/04
6.1 It is proposed that preparation work, including consultation and feasibility design, on some schemes already being progressed should continue. Within the funding to be made available it is suggested that work on the following NEHTS schemes be continued:
(i) North Camp Regeneration / Wider North Camp;
(ii) Village Traffic Management;
(iii) B3272 Route management Strategy;
(iv) Fleet Town Centre;
(v) A325/A30 Route 1 Corridor; and
(vi) Yateley to Blackwater Cycle Scheme.
7. Review of the Area Transportation Strategy Panels
7.1 There is to be a review of the way transport planning and investment is organised in the county to take account of developments with the regional transport strategy and sub-regional transport, economic and development planning approaches. It is proposed that this review is carried out during 2003, including consultation with district councils, and proposals presented to the Area Transportation Strategy Panels in the autumn, with any new arrangements being introduced in 2004.
8. Summary of Position
8.1 Government funded support for integrated transport, ie area transport strategy schemes, safety and county-wide programmes, remains high (£14 million per year). However, the over-commitment in 2002/03, resulting from the need to reach the spending target, and the fact that the A3 has not yet been accepted as a major scheme means that the new 2003/04 programme is much less than originally proposed. Resources are expected to continue at about £14 million per year and a new programme for 2004/05 will be produced following a reassessment of all schemes in the early part of 2003. Future programmes are likely to be affected by the County Council's review of its approach in the light of developments at the regional and sub-regional level, and the Area Transportation Strategy Panels.
Recommendation
1. That this report be noted.
2. That the North East Hampshire Transport Strategy schemes for 2004/05 and beyond be considered as part of the county-wide review of Transportation Strategy Areas to be presented to the Environment Policy Review Committee on 9 July 2003.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None |
7704/JWB
APPENDIX
North East Hampshire Transport Strategy (NEHTS)
Revised Transport Capital Programmes 2002/03 and 2003/04
2002/03 |
2003/04 |
2004/05 and beyond | |
A325/A30 corridor, Blackwater Valley bus service 1, priority route |
2,800+ |
_ | |
Fleet town centre corridors, including A3013 Fleet Road |
|
_ + | |
Aldershot - North Lane traffic management study/scheme |
|
_ | |
North Camp regeneration, with ROUA** project - Lynchford Road crossing |
|
50 |
_ |
Farnborough - Park Road area traffic management study/scheme |
|
_ | |
B3272 Route Management Study, including Yateley ROUA** project |
|
_ + | |
Intelligent Transport Systems |
80 |
|
_ |
Cycle and pedestrian network - Old Trunk Road (Fleet Road - Summit Avenue) - Yateley to Blackwater cycle route - Minley Road cycle route - cycle parking |
204+ 20 |
_ _ | |
Village traffic management |
|
50 |
_ |
Farnborough Town Centre signing |
125* |
||
Summit Ave (Southwood - Old Trunk Road) |
75* |
||
Ayling Lane Aldershot - traffic calming |
55* |
||
A327 Elles Road - street lighting |
120* |
||
A325 Farnborough Gate - borough boundary |
80* |
||
Galley Hill Road, Church Crookham |
32* |
||
A30 Blackwater |
75* |
||
Murrell Green public transport |
20* |
||
A287/Redfields Lane junction |
_ * | ||
Beacon Hill Road, Church Crookham |
_ * |
KEY:
50 change of year (2002/03 to 2003/04)
50 scheme deferred
+ partly externally funded
* externally funded
_ in 2004/05 and beyond pool
** Regeneration of Older Urban Areas