Archived decisions

Hampshire County Council

Basingstoke and Deane Highway Management Advisory Panel

19 March 2003

Street Lighting Programmes 2002/03 and 2003/04

Report of the Director of Environment

Item 7

Contact: Tony Stephens, ext 6938

1. Summary

1.1 This report covers:

      (i) Street Lighting Maintenance Contract;

      (ii) Column Replacement Programmes 2002/03 and 2003/04;

      (iii) Energy Contract;

      (iv) Community Safety Initiative 2002/03 and 2003/04; and

      (v) Street Lighting Policy.

2. Street Lighting Maintenance Contract

2.1 The Street Lighting Maintenance Contract continues to provide a high percentage of 'lights on' across the county. There are still some administrative issues to be resolved by the contractor, including completion of the supply of specialist vehicles.

2.2 In addition, the contractor is considering administrative changes which it is hoped will reduce overheads and ensure the consolidation of Southern Electric Contracting's lighting services within the county.

3. Column Replacement Programmes 2002/03 and 2003/04

3.1 The column replacement programme was instigated some 10 years ago to counter the problem of decaying street lighting columns. Initially, this was a problem with concrete columns, but it became apparent that steel columns were also corroding - some from within - and there was an urgent need to start a programme of replacement.

3.2 In 1997 a programme of detailed visual and tactile structural inspection was introduced as part of the cyclic maintenance programme. Since then the information gleaned from those inspections has been used to plan and prioritise the annual programme. Now the recording of these inspections has been transcribed onto the SLIMs computer database to provide a more easily accessible stream of information. This will also be supplemented by a system of electronic testing when a suitable, inexpensive system becomes available. In 2003/04 the budget for this work will, subject to confirmation, be £1.2 million.

3.3 This aspect of the county-wide maintenance contract is generally working well and, whilst there has been some overall slippage, the 2002/03 programme should be completed by the end of March 2003.

3.4 In addition to column replacements during 2002/03 the Churchill Way underpass lighting was replaced at a cost of £131,000. The new system of lighting is a single row of downward facing floodlights which will be controlled by two light sensitive cameras located approximately 70 metres from the approach portals. The new control system is not yet fully operational, hence all lighting units are on 24 hours a day at the present time. When the scheme is fully operational, the lighting units will be brought on in stages during the day, depending on the ambient light levels outside the underpass, reducing to a minimum level more suited for night-time operation.

3.5 During 2002/03 street lighting in the following roads has been replaced:

    - Quilter Road/Gershwin Road footpaths

    - Roentgen Road

    - Swing Swang Lane

    - Penrith Road

3.6 During the year 2003/04 street lighting in the following roads is due for replacement:

    - Bell Road

    - Whitney Road

    - Heather Way

    - Gershwin Road subway footpath (east)

    - Bernstein Road/Barry Way footpath

    - Carpenters Down

    - Popley Way

    - Buckland Avenue

    - Buckskin Lane

    - Queen Mary Avenue

    - Vyne Road

    - Armstrong Road

    - Wade Road

    - Faraday Road

    - Pinkerton Road

    - St Michael's Road

4. Energy Contract

4.1 The energy contract continues to operate in a satisfactory manner. A problem of underpayment due to inventory summary problems at Scottish and Southern Energy will be resolved by the end of February 2003.

4.2 Discussions with the Local Authority Central Buying Consortium will recommence in mid-summer to consider the form of a new supply contract for April 2004, when the possibility of increasing the `green' energy content of this contract will be considered.

5. Community Safety Initiative 2002/03 and 2003/04

5.1 The programme for 2002/03 for this popular partnership initiative has now been completed. New street lighting was added to Swains Close footpath in Tadley.

5.2 Letters requesting bids for the forthcoming financial year have been sent out, with the anticipation of a further programme of £120,000 county-wide for 2003/04.

6. Street Lighting Policy

6.1 Following a service review in 1999, the County Council revised its street lighting policy, which was confirmed by the Executive Member for Environment in early 2002. The document has now been published and engineering and planning departments of local authorities throughout Hampshire will be sent copies, which should assist them in dealing with planning applications. The aim is to reduce the effects of light pollution, light trespass and energy wastage. Further copies of the Policy Document will be supplied by the Lighting Section on request.

Recommendation

That this report be noted.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None.

7770/ALS