Archived decisions

CAPITAL PROGRAMME 2002/03

LIST OF SCHEMES NOT STARTED BY 31 MARCH 2003

Schemes

Value

Latest

Reasons for Delay

 

£000

Start Date

 

 

 

 

 

 

 

Education

 

 

 

 

 

 

 

 

 

 

 

Major Schemes :

 

 

 

 

 

 

 

 

 

 

 

Cherrywood Primary, Farnborough

1,312

 

 

September 2003

Delays associated with the land sale.

 

 

 

 

 

 

Prices Trust Schemes :

 

 

 

 

 

 

 

 

 

 

 

Henry Cort Secondary, Fareham

47

 

 

Unknown

'On hold' pending Sports College bid.

 

 

 

 

 

 

Redlands Primary, Fareham

40

 

 

Unknown

Time taken to agree scale and nature of works.

 

 

 

 

 

 

Wicor Primary, Portchester

147

 

 

January 2004

To be combined with New Deal for Schools (NDS) Funding in 03/04.

 

 

 

 

 

 

Minor Works :

 

 

 

 

 

 

 

 

 

 

 

Basingstoke Schools - use of earmarked

120

 

 

Various

Time taken to agree allocation and timing of schemes with the 6 Schools

contributions

 

 

 

 

involved.

 

 

 

 

 

 

Trosnant Junior, Havant

85

 

 

Unknown

To be combined with Neighbourhood Nurseries Initiative funding in 03/04.

 

 

 

 

 

 

Park Community, Havant

25

 

 

Unknown

Overall development strategy being programmed.

 

 

 

 

 

 

Staunton Park Secondary, Havant

114

 

 

Unknown

Lottery Bid unsuccessful - overall scheme to be reviewed.

 

 

 

 

 

 

The Bridge Centre, Colden Common

190

 

 

Unknown

Overall development strategy being programmed.

 

 

 

 

 

 

Hamble School (youth facility)

77

 

 

Unknown

Need to agree additional funding to progress the scheme.

 

 

 

 

 

 

Specialist School Status :

 

 

 

 

 

 

 

 

 

 

 

Various

800

 

 

Unknown

Time taken to finalise negotiations/schemes and identify additional funding.

 

 

 

 

 

 

Modernisation / Suitability :

 

 

 

 

 

 

 

 

 

 

 

Shepherds Spring Junior, Andover

21

 

 

May 2003

Time taken to agree scale and nature of work.

 

 

 

 

 

 

Brookfield Community, Sarisbury Green

105

 

 

July 2003

Funding added to 03/04 Basic Need allocation.

 

 

 

 

 

 

Park Primary, Aldershot - Early Years

128

 

 

Autumn 2003

On-going negotiation with School - funding to be combined with 03/04

 

 

 

 

 

Nursery Education in Disadvantaged Areas (NEDA).

 

 

 

 

 

 

Early Years - general

68

 

 

Unknown

Schemes to be identified.

 

 

 

 

 

 

Neighbourhood Nurseries Initiative

330

 

 

Unknown

Schemes to be identified.

 

 

 

 

 

 

Staff Workplaces - uncommitted

31

 

 

Unknown

Schemes to be identified.

 

 

 

 

 

 

Schools Access Initiative :

 

 

 

 

 

 

 

 

 

 

 

Various

779

 

 

Various

Various including difficulties resolving scope of schemes.

 

 

 

 

 

 

Seed Challenge

 

 

 

 

 

 

 

 

 

 

 

Netley Abbey Primary

160

 

 

June 2003

To align two projects into one contract.

 

 

 

 

 

 

Henry Beaufort Secondary, Winchester

102

 

 

May 2003

Time taken to finalise negotiations and agree funding.

 

 

 

 

 

 

Petersfield School

190

 

 

October 2003

Time taken to agree scale and nature of works.

 

 

 

 

 

 

Total Education

4,871

 

 

 

12.7% of schemes approved to start in 2002/03.

 

 

 

 

 

 

 

 

 

 

 

 

Environment

 

 

 

 

 

 

 

 

 

 

 

A3 Corridor Bus Priority - Stage 2A (Purbrook)

1,300

 

 

July 2003

Completion of consultation with local businesses and residents.

 

 

 

 

 

 

B2177/B3354 Fishers Pond Junction Improvement

450

 

 

Sept 2003

Need to avoid summer working in the vicinity of Marwell Zoo.

 

 

 

 

 

 

Jacobs Gutter Lane, Marchwood (net)

350

 

 

June 2003

Start delayed to take advantage of lower traffic volumes during school

 

 

 

 

 

holidays.

 

 

 

 

 

 

Basingstoke Real Time Information

170

 

 

May 2003

Need to co-ordinate with the implementation of the Real Time

 

 

 

 

 

Information Central System.

 

 

 

 

 

Lymington High Street

40

 

 

June 2003

Need for extensive consultation in environmentally sensitive area.

 

 

 

 

 

 

A33 Sherfield-on-Loddon Traffic Calming

40

 

 

June 2003

Need to fully assess effects of experimental measures.

 

 

 

 

 

 

Waterlooville Centre

25

 

 

March 2004

Need to co-ordinate with other works in the area.

 

 

 

 

 

 

Total Environment

2,375

 

 

 

5.0% of schemes approved to start in 2002/03.

 

 

 

 

 

 

 

 

 

 

 

 

Policy and Resources

 

 

 

 

 

 

 

 

 

 

 

Economic Prosperity

 

 

 

 

 

 

 

 

 

 

Gosport Enterprise Centre

64

 

 

October 2003

The County Council's contribution is being held pending the outcome

 

 

 

 

 

of negotiations between the South East England Development Agency

 

 

 

 

 

(SEEDA) and the private sector.

 

 

 

 

 

 

Defence, Heritage and Tourism

 

 

 

 

 

 

 

 

 

 

 

Fort Gilkicker

100

 

 

Unknown

Development options and partnership are still being sought.

 

 

 

 

 

 

M33 Minerva

145

 

 

Unknown

Subject to review of future management of M33 Minerva.

 

 

 

 

 

 

Coastal Conservation

 

 

 

 

 

 

 

 

 

 

 

Saline Lagoons

20

 

 

2003/04

Negotiations with English Nature and the Environment Agency are

 

 

 

 

 

delaying this scheme.

 

 

 

 

 

 

Coastal Defence

20

 

 

July 2003

The brief for a feasibility study is being finalised and the contract is

 

 

 

 

 

expected to be let early in 2003/04.

 

 

 

 

 

 

Salt Marshes

15

 

 

Unknown

New Forest District Council are responsible for this scheme, it is hoped

 

 

 

 

 

the project will start in 2003/04.

 

 

 

 

 

 

Land Management

 

 

 

 

 

 

 

 

 

 

 

Minor Schemes

6

 

 

Various

Various schemes, expected to be resolved in 2003/04.

 

 

 

 

 

 

Sites and Buildings

 

 

 

 

 

 

 

 

 

 

 

New Deals for Schools (NDS) condition funding

4,333

 

 

August 2003

Condition funding requires that resources are spent by the end of

 

 

 

 

 

August 2003. Programmes agreed with the Executive Member of

 

 

 

 

 

Policy and Resources will enable this to be fulfilled.

 

 

 

 

 

 

Capital and major repairs

2,827

 

 

Various

Priority has been given to NDS projects in 2002/03. The rescheduling

 

 

 

 

 

of repairs projects will enable planned works at schools, in particular,

 

 

 

 

 

to be undertaken. Access Initiatives are pending approval.

 

 

 

 

 

 

Improvements to older persons homes

1,792

 

 

June 2003

Funds have been earmarked for the major refurbishment of

 

 

 

 

 

Malmesbury Lawn in Havant, and fire precaution works, allocated to the

 

 

 

 

 

highest risk properties.

 

 

 

 

 

 

Office Accommodation

700

 

 

Various

To improve office accommodation provision, and for strategic impact,

 

 

 

 

 

more than one year's allocation is being accumulated.

 

 

 

 

 

 

Libraries

 

 

 

 

 

 

 

 

 

 

 

Balance of major scheme provision

782

 

 

n/a

The balance of the library provision in the 2001/02 capital programme

 

 

 

 

 

after deductions to fund other, mainly Recreation and Heritage, projects.

 

 

 

 

 

 

Other

 

 

 

 

 

 

 

 

 

 

 

Basing House

455

 

 

Unknown

This is a proposed in / out project, cash limited to the proceeds from the

 

 

 

 

 

sale of a farmhouse. The project is expected to start once funds have been

 

 

 

 

 

been received.

 

 

 

 

 

 

Advance fees and advantageous land

141

 

 

Various

n/a.

 

 

 

 

 

 

Uncommitted balance

124

 

 

Unknown

Uncommitted usable capital receipts from 2000/01 and 2001/02.

 

 

 

 

 

 

SimsMetals UK

3

 

 

April 2003

Required for future litigation costs.

 

 

 

 

 

 

Total Policy and Resources

11,527

 

 

 

28.1% of schemes approved to start in 2002/03.

 

 

 

 

 

 

 

 

 

 

 

 

Recreation and Heritage

 

 

 

 

 

 

 

 

 

 

 

Countryside:

 

 

 

 

 

 

 

 

 

 

 

Minor works and improvements

42

 

 

Various

Operational reasons, including legal disputes and assembling funding

 

 

 

 

 

from other sources.

 

 

 

 

 

 

Sport and Community:

 

 

 

 

 

 

 

 

 

 

 

Calshot - Keymer House

217

 

 

Unknown

Delay whilst further funding is being assembled.

 

 

 

 

 

 

Village Halls

100

 

 

Unknown

Assembling funding from other sources.

 

 

 

 

 

 

Community Recreation and Sport

15

 

 

Unknown

Awaiting lottery bid outcome.

 

 

 

 

 

 

Outdoor Centres

48

 

 

Unknown

Awaiting outcome of New Opportunities Fund application.

 

 

 

 

 

 

Arts:

 

 

 

 

 

 

 

 

 

 

 

West End Arts Centre Facilities

55

 

 

Summer 2003

Assembling funding from other sources.

 

 

 

 

 

 

Cricklade Theatre

5

 

 

Summer 2003

Work now planned for the summer.

 

 

 

 

 

 

Tower Arts Centre Facilities

45

 

 

Summer 2003

Work now planned for the summer.

 

 

 

 

 

 

Fairfields Arts Centre grant

32

 

 

Summer 2003

Improvement proposals not yet finalised.

 

 

 

 

 

 

Minor grants

6

 

 

Summer 2003

Assembling funding from other sources.

 

 

 

 

 

 

Total Recreation and Heritage

565

 

 

 

52.7% of schemes approved to start in 2002/03.

 

 

 

 

 

 

 

 

 

 

 

 

Social Services

 

 

 

 

 

 

 

 

 

 

 

Alton Day Services - replacement

1,124

 

 

May 2003

Design changes due to planning objections.

 

 

 

 

 

 

Social care information system

1,253

 

 

On-going

Balance of allocation for complex procurement strategy.

 

 

 

 

 

 

Information management system

13

 

 

On-going

Balance of allocation.

 

 

 

 

 

 

Information technology for looked-after children

13

 

 

On-going

Balance of allocation.

 

 

 

 

 

 

Minor works in residential and day care premises

142

 

 

Various

Balance of allocation.

 

 

 

 

 

 

Furniture and equipment in residential and day

97

 

 

Various

Expenditure linked with building works schemes.

care premises

 

 

 

 

 

 

 

 

 

 

 

Furniture and equipment in office bases

56

 

 

Various

Expenditure linked with building works schemes.

 

 

 

 

 

 

Supplementary credit approval (MH)

205

 

 

Various

Timing dependent on joint schemes with the Health Service.

 

 

 

 

 

 

Supported Housing

160

 

 

Various

Timing dependent on joint schemes with Housing Authorities.

 

 

 

 

 

 

Total Social Services

3,063

 

 

 

51.1% of schemes approved to start in 2002/03.

 

 

 

 

 

 

 

 

 

 

 

 

Total all Services

22,401

 

 

 

16.8% of schemes approved to start in 2002/03.

 

 

 

 

 

 

Add: Education and Environment schemes

 

 

 

 

 

previously approved for carry forward to 2003/04

6,905

 

 

 

 

 

 

 

 

 

 

Total value of schemes carried forward

29,306

 

 

 

20.9% of schemes approved to start in 2002/03.