1. Summary

1.1 The following decision is sought:

    That approval be given for the Harbour Authority to continue with the proposed Dredging Plan preparation and for the appropriate budget allocation of £12,130 to be made by the Harbour Authority as its contribution to the overall cost.

2. Reason

2.1 To produce a Dredging Plan for the river as a whole would enable better use of resources and manage the dredging activities in a more environmentally sustainable manner.

3. Other Options Considered and Rejected

3.1 Not to produce an overarching Dredging Plan for the river as a whole with the administrative and cost consequences of dealing with this incrementally.

4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer consulted - None.

5. Dispensation granted by the Standards Committee - Not applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.

Approved by: Date:

Councillor K B Estlin

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

7996/TC