Archived decisions
Hampshire County Council Executive Member - Environment 20 May 2003 River Hamble Dredging Plan Project Report of the Director of Environment |
Item 13 |
Contact: Tony Clatworthy, tel: 01489 576387
1. Summary
1.1 The following decision is sought:
That approval be given for the Harbour Authority to continue with the proposed Dredging Plan preparation and for the appropriate budget allocation of £12,130 to be made by the Harbour Authority as its contribution to the overall cost.
2. Reason
2.1 To produce a Dredging Plan for the river as a whole would enable better use of resources and manage the dredging activities in a more environmentally sustainable manner.
3. Other Options Considered and Rejected
3.1 Not to produce an overarching Dredging Plan for the river as a whole with the administrative and cost consequences of dealing with this incrementally.
4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer consulted - None.
5. Dispensation granted by the Standards Committee - Not applicable.
6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.
Approved by: Date:
Councillor K B Estlin
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None |
7996/TC