Archived decisions

Hampshire County Council

Executive Member - Policy and Resources

12 June 2003

Marchwood Junior School

Report by the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858

1

Summary

1.1

The following decisions are sought:

1.2

That approval be given to

    1) The design project appraisal for the construction of additional accommodation and replacement permanent teaching accommodation at Marchwood Junior School at an estimated cost of £606,000, excluding fees.

    2) The negotiation of a contract with Benson Ltd to complete the work at Marchwood Junior School

2

Reason

2.1

To provide additional basic need places to meet a growth in pupils attending the school and to provide replacement permanent teaching accommodation to replace temporary buildings which will be removed from site.

3

Other options considered and rejected

3.1

The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or a member or officer consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

.........................

Councillor K Thornber

EMP&R06/03gP&R