Hampshire County Council Appendix 1
Capital Strategy - Core Data
1 Revenue budget 2003/04
£m | |
Gross revenue budget |
1,293 |
Net budget after income and specific grants |
1,026 |
2 Assets values - by type of asset
Value | |
£m | |
Operational assets |
|
Council dwellings |
- |
Other land and buildings |
1,838 |
Vehicles, plant and equipment |
40 |
Infrastructure assets |
215 |
Community assets |
9 |
Non-operational assets |
64 |
Work in progress |
54 |
-------- | |
Net book value at 31 March 2003 |
2,220 |
-------- |
3 Assets - by service
Number |
Gross Floor |
Value | |
Area (GIA) |
31 Mar 2003 | ||
sq m |
£m | ||
Operational assets |
|||
Schools |
547 |
1,244,000 |
1,539 |
Libraries |
69 |
35,000 |
43 |
Residential homes and day centres |
89 |
88,000 |
89 |
Offices and administrative buildings |
63 |
90,000 |
36 |
Museums and art galleries |
26 |
28,000 |
31 |
Other land and buildings |
29 |
2,000 |
100 |
Vehicles, plants and equipment |
- |
- |
40 |
Infrastructure - roads and bridges |
- |
- |
215 |
Community assets - parks etc |
37 |
36,000 |
9 |
Non-operational assets |
57 |
73,000 |
62 |
Work in progress |
- |
- |
54 |
------------- |
------------- |
-------- | |
Totals |
917 |
1,596,000 |
2,218 |
------------- |
------------- |
-------- |
4 Maintenance liabilities - land and buildings
Total |
Priority levels | ||||
Cost |
1 |
2 |
3 |
4 | |
Urgent |
Essential |
Desirable |
Long-term | ||
to prevent |
within |
in |
beyond | ||
closure |
2 years |
3-5 years |
5 years | ||
£m |
£m |
£m |
£m |
£m | |
Education |
250 |
- |
50 |
124 |
76 |
Libraries |
7 |
- |
3 |
4 |
- |
Social services |
15 |
- |
5 |
9 |
1 |
Offices |
17 |
- |
6 |
9 |
2 |
Other services |
21 |
- |
7 |
12 |
2 |
---------- |
---------- |
---------- |
---------- |
---------- | |
Total |
310 |
- |
71 |
158 |
81 |
---------- |
---------- |
---------- |
---------- |
---------- | |
Maintenance liabilities - roads and bridges
£m |
|||
Principal and non-principal roads |
75 |
see note below | |
This estimate is based on visual assessments and the results of deflectograph surveys. It will be reviewed when the new Pavement Management System (UKPMS) is fully commissioned and a comprehensive Coarse Visual Inspection has been undertaken. Initial data from UKPMS results suggest that £75m is an understatement and that the figure may be as much as £200m. | |||
5 Capital programme
5.1 The County Council's four-year capital programme for 2003/04 to 2006/07 is summarised on the following page. Full details of the programme are published in the Council's Budget Book for 2003/04. The estimated capital payments on the programme and on schemes already in progress are also shown together with details of how the County Council expects to finance them. The minor shortfall of resources in 2004/05 will be addressed when the capital programme is reviewed later in 2003.
5.2 The Government's current spending plans SR2002 cover the period to 2005/06 only and so the Council's programmes for 2006/07 is currently set at a minimum level. It is likely to increase when the Government's detailed SR2004 spending plans are announced in 2004.
Capital programme - value of schemes starting 2003/04 to 2006/07 | ||||
2003/04 |
2004/05 |
2005/06 |
2006/07 | |
£m |
£m |
£m |
£m | |
Schools |
63.0 |
36.8 |
31.2 |
4.1 |
Local transport * |
36.1 |
156.0 |
32.3 |
61.8 |
Libraries, museums, arts, countryside, sport etc |
2.1 |
1.3 |
0.8 |
0.8 |
Social services # |
1.2 |
1.2 |
1.2 |
0.7 |
Capital repairs of buildings funded from the |
||||
County Council's own resources |
14.3 |
13.6 |
13.6 |
13.6 |
Regeneration of older urban areas, household |
||||
waste recycling centres, magistrates' courts |
||||
and other schemes |
4.8 |
4.2 |
4.2 |
4.2 |
Not yet allocated |
- |
- |
2.0 |
2.0 |
---------- |
---------- |
---------- |
---------- | |
Total starts programme |
121.5 |
213.1 |
85.3 |
87.2 |
---------- |
---------- |
---------- |
---------- | |
* includes the South Hampshire Rapid Transit scheme which is expected to involve both conventional and Private Finance Initiative funding | ||||
# the scheme to provide additional nursing care beds will be added to the capital programme | ||||
Capital payments and financing | ||||
2003/04 |
2004/05 |
2005/06 |
2006/07 | |
£m |
£m |
£m |
£m | |
Payments on the starts programmes for 2003/04 |
||||
to 2006/07 and works in progress |
140.2 |
144.6 |
150.0 |
128.9 |
---------- |
---------- |
---------- |
---------- | |
Financed by: |
||||
Loans |
51.6 |
47.8 |
42.8 |
44.3 |
Capital receipts, including in/out disposals |
11.2 |
4.7 |
6.2 |
6.2 |
Grants and contributions |
41.9 |
59.7 |
74.4 |
52.2 |
Contributions from revenue and reserves |
35.5 |
32.2 |
26.6 |
26.2 |
Resources still to be identified |
- |
0.2 |
- |
- |
---------- |
---------- |
---------- |
---------- | |
Total financing |
140.2 |
144.6 |
150.0 |
128.9 |
---------- |
---------- |
---------- |
---------- | |
6 Unsupported borrowing
6.1 The Government plans to introduce a new prudential capital control system that will allow local authorities to raise additional loans for capital purposes, unsupported by Government grant. Provided the unsupported borrowing is a last resort after other available funding sources and there is a strong business case, the County Council has agreed to use unsupported borrowing for the South Hampshire Rapid Transit scheme and the provision of additional nursing care beds, subject to the costs being contained within revenue cash limits.
6.2 Other uses of unsupported borrowing may include invest-to-save projects that generate ongoing savings to cover the additional costs of borrowing, and in/out projects for which investment in the replacement asset is required in advance of the capital receipt.
7 Hampshire - profile
7.1 Hampshire is a large county of 368,000 hectares with a mixture of significant urban and extensive rural areas. Although less than 10% of the county is urban, 87% of the population lives in urban areas.
7.2 Hampshire's population of 1,240,800 (mid 2001) ranks as the third largest for shire counties in England. The age-profile is similar to the national average.
7.3 Between 2001 and 2011, the population is forecast to grow by 3.5% to 6.2%, depending on the rate at which new households are formed. This growth will be higher for age groups over 45 with, for example, growth of over 20% expected in the over-85 age group. Household growth is projected by Central Government to be faster than in the other large counties. The number of households in Hampshire is forecast to increase by 9.6% between 2001 and 2011.
7.4 Further details of Hampshire can be found in "A Profile of Hampshire" published by the County Council in December 2001 and available from the address at the foot of the page.
Footnote [note: these links will be updated following the Cabinet meeting]
1 Links to the documents mentioned in the Capital Strategy and corporate AMP can be found on the County Council's Capital Strategy website at: http://www.hants.gov.uk/TC/capitalstrategy/contents.html
For further information, please write to Ian Howell, County Treasurer's Department, Hampshire County Council, The Castle, Winchester, Hampshire SO23 8UB, or send an e-mail to [email protected]