Hampshire County Council Appendix 1

Capital Strategy - Core Data

1 Revenue budget 2003/04

£m

Gross revenue budget

1,293

Net budget after income and specific grants

1,026

2 Assets values - by type of asset

Value

£m

Operational assets

Council dwellings

-

Other land and buildings

1,838

Vehicles, plant and equipment

40

Infrastructure assets

215

Community assets

9

Non-operational assets

64

Work in progress

54

--------

Net book value at 31 March 2003

2,220

--------

3 Assets - by service

Number

Gross Floor

Value

Area (GIA)

31 Mar 2003

sq m

£m

Operational assets

Schools

547

1,244,000

1,539

Libraries

69

35,000

43

Residential homes and day centres

89

88,000

89

Offices and administrative buildings

63

90,000

36

Museums and art galleries

26

28,000

31

Other land and buildings

29

2,000

100

Vehicles, plants and equipment

-

-

40

Infrastructure - roads and bridges

-

-

215

Community assets - parks etc

37

36,000

9

Non-operational assets

57

73,000

62

Work in progress

-

-

54

-------------

-------------

--------

Totals

917

1,596,000

2,218

-------------

-------------

--------

4 Maintenance liabilities - land and buildings

    Total

Priority levels

    Cost

1

    2

3

4

Urgent

    Essential

Desirable

Long-term

to prevent

    within

in

beyond

closure

    2 years

3-5 years

5 years

    £m

£m

    £m

£m

£m

Education

    250

-

    50

124

76

Libraries

    7

-

    3

4

-

Social services

    15

-

    5

9

1

Offices

    17

-

    6

9

2

Other services

    21

-

    7

12

2

    ----------

----------

    ----------

----------

----------

Total

    310

-

    71

158

81

    ----------

----------

    ----------

----------

----------

Maintenance liabilities - roads and bridges

    £m

Principal and non-principal roads

    75

see note below

This estimate is based on visual assessments and the results of deflectograph surveys. It will be reviewed when the new Pavement Management System (UKPMS) is fully commissioned and a comprehensive Coarse Visual Inspection has been undertaken. Initial data from UKPMS results suggest that £75m is an understatement and that the figure may be as much as £200m.

5 Capital programme

5.1 The County Council's four-year capital programme for 2003/04 to 2006/07 is summarised on the following page. Full details of the programme are published in the Council's Budget Book for 2003/04. The estimated capital payments on the programme and on schemes already in progress are also shown together with details of how the County Council expects to finance them. The minor shortfall of resources in 2004/05 will be addressed when the capital programme is reviewed later in 2003.

5.2 The Government's current spending plans SR2002 cover the period to 2005/06 only and so the Council's programmes for 2006/07 is currently set at a minimum level. It is likely to increase when the Government's detailed SR2004 spending plans are announced in 2004.

Capital programme - value of schemes starting 2003/04 to 2006/07

         
 

2003/04

2004/05

2005/06

2006/07

 

£m

£m

£m

£m

         

Schools

63.0

36.8

31.2

4.1

Local transport *

36.1

156.0

32.3

61.8

Libraries, museums, arts, countryside, sport etc

2.1

1.3

0.8

0.8

Social services #

1.2

1.2

1.2

0.7

Capital repairs of buildings funded from the

       

County Council's own resources

14.3

13.6

13.6

13.6

Regeneration of older urban areas, household

       

waste recycling centres, magistrates' courts

       

and other schemes

4.8

4.2

4.2

4.2

Not yet allocated

-

-

2.0

2.0

 

----------

----------

----------

----------

Total starts programme

121.5

213.1

85.3

87.2

 

----------

----------

----------

----------

         

* includes the South Hampshire Rapid Transit scheme which is expected to involve both conventional and Private Finance Initiative funding

# the scheme to provide additional nursing care beds will be added to the capital programme

         

Capital payments and financing

 

2003/04

2004/05

2005/06

2006/07

 

£m

£m

£m

£m

         

Payments on the starts programmes for 2003/04

       

to 2006/07 and works in progress

140.2

144.6

150.0

128.9

 

----------

----------

----------

----------

         

Financed by:

       

Loans

51.6

47.8

42.8

44.3

Capital receipts, including in/out disposals

11.2

4.7

6.2

6.2

Grants and contributions

41.9

59.7

74.4

52.2

Contributions from revenue and reserves

35.5

32.2

26.6

26.2

Resources still to be identified

-

0.2

-

-

 

----------

----------

----------

----------

Total financing

140.2

144.6

150.0

128.9

 

----------

----------

----------

----------

         

6 Unsupported borrowing

6.1 The Government plans to introduce a new prudential capital control system that will allow local authorities to raise additional loans for capital purposes, unsupported by Government grant. Provided the unsupported borrowing is a last resort after other available funding sources and there is a strong business case, the County Council has agreed to use unsupported borrowing for the South Hampshire Rapid Transit scheme and the provision of additional nursing care beds, subject to the costs being contained within revenue cash limits.

6.2 Other uses of unsupported borrowing may include invest-to-save projects that generate ongoing savings to cover the additional costs of borrowing, and in/out projects for which investment in the replacement asset is required in advance of the capital receipt.

7 Hampshire - profile

7.1 Hampshire is a large county of 368,000 hectares with a mixture of significant urban and extensive rural areas. Although less than 10% of the county is urban, 87% of the population lives in urban areas.

7.2 Hampshire's population of 1,240,800 (mid 2001) ranks as the third largest for shire counties in England. The age-profile is similar to the national average.

7.3 Between 2001 and 2011, the population is forecast to grow by 3.5% to 6.2%, depending on the rate at which new households are formed. This growth will be higher for age groups over 45 with, for example, growth of over 20% expected in the over-85 age group. Household growth is projected by Central Government to be faster than in the other large counties. The number of households in Hampshire is forecast to increase by 9.6% between 2001 and 2011.

7.4 Further details of Hampshire can be found in "A Profile of Hampshire" published by the County Council in December 2001 and available from the address at the foot of the page.

    Footnote [note: these links will be updated following the Cabinet meeting]

      1 Links to the documents mentioned in the Capital Strategy and corporate AMP can be found on the County Council's Capital Strategy website at: http://www.hants.gov.uk/TC/capitalstrategy/contents.html

              For further information, please write to Ian Howell, County Treasurer's Department, Hampshire County Council, The Castle, Winchester, Hampshire SO23 8UB, or send an e-mail to [email protected]