APPENDIX 2
Safer Routes to School programme 2003/04
Schemes in New Forest District
School name and description of works |
District and Transport Strategy Area |
Status of School Travel Plan |
Estimated Cost of works |
Progress |
Brangsore Primary - new signs needed, walking bus, footpaths need clearing, SCP / Junction improvements |
NFDC NFTS |
Survey completed |
£15k |
School Crossing Patrol improvements complete. WSA progressing further works to junction and footpaths (details still to be confirmed) |
Copythorne Infants - road surface / footways / signage improvements |
NFDC NFTS |
Travel assessment completed 2001 |
£12.5k |
HUW undertaking improvements to footway outside school. |
Hounsdown School, Totton |
NFDC SWHTS |
Complete |
TBC |
Scheme details still to be confirmed |
Lydlynch Infants, Totton - highway footpaths and signage |
NFDC NFTS |
Complete |
£5k |
Design under way |
Netley Marsh C/E Infant School -improved signage and highway surfacing. (proposed design within STP) |
NFDC NFTS |
Complete |
£40k |
Works in progress - see Item 8. |
Orchard I & J Schools - Water Lane improvements |
NFDC SWHTS |
None |
£50k |
No action as no commitment to developing a travel plan at present |
Poulner I & J Schools, Gorley Rd Ringwood. Pedestrian improvement scheme between the schools and local shops |
NFDC NFTS |
Being developed |
£40k |
WSA to design and implement |
Ringwood School - Southampton Road gateway feature |
NFDC NFTS |
Being developed |
£10k |
Design underway. |
St. Luke's Church of England Primary School, Sway |
NFDC NFTS |
Complete |
£50k |
WSA progressing to detailed design and implementation |
Tiptoe Primary School |
NFDC NFTS |
Being Developed |
TBC |
Awaiting outcome of STP before scheme details are confirmed |