Archived decisions

Hampshire County Council

Item 8

Executive Member - Education

16 October 2003

Fordingbridge Infant School

Report by the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858 e-mail: [email protected]

1

Summary

1.1

The following decision is sought:

1.2

That the Executive Member for Education advises the Executive Member for Policy and Resources that the project appraisal for the construction of two new classrooms, a Music Room, Library and IT area at Fordingbridge Infant School at an estimated cost of up to £566,000, excluding fees, be approved.

2

Reason

2.1

To provide additional teaching space consisting of two new classrooms, Music Room, Library and IT area, thus facilitating the removal of one temporary classroom currently on site.

3

Other options considered and rejected

3.1

The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or a member or officer consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

.........................

Councillor D Allen