Archived decisions

      HAMPSHIRE COUNTY COUNCIL

    BUILDING DESIGN PROJECT APPRAISAL

      EDUCATION BUILDINGS ADVISORY GROUP

      29 SEPTEMBER 2003

      EXECUTIVE MEMBER - EDUCATION

      16 OCTOBER 2003

      BUILDINGS, LAND AND CONTRACTS PANEL

      22 OCTOBER 2003

      EXECUTIVE MEMBER - POLICY AND RESOURCES

      13 NOVEMBER 2003

    PROJECT:

    BRUNE PARK COMMUNITY SCHOOL, GOSPORT

    NEW DANCE STUDIO AND DINING HALL EXTENSION

    COMMENCEMENT DATE:

    JUNE 2004

    COMPLETION DATE:

    FEBRUARY 2005

    PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

    2003/ 04

      RECOMMENDATION:

      That the building design project appraisal for the Brune Park Community School scheme be approved.

      1. FINANCE

    Capital Expenditure

    Current Estimate

    (at Nov '02 prices)

    £'000

    Capital Programme

    (at Nov '02 prices)

    £'000

    Buildings

    1,101

    849

    Fees

    169

    136

    TOTAL

    1,270*

    985

      * The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.

      Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total

    Cost

    £'000

    1. From Committee's own Resources:

    a) Capital Programme (as above)

    849

    136

    985

    2. School

    80

    5

    85

    3. From Other Resources:

    a) Public Service Agreement funding

    172

    28

    200

    TOTAL

    1,101

    169

    1,270

Anticipated Devolved Capital allocations £'000

                  2002/03 (10) overdrawn

              2003/04 113

              2004/05 128

TOTAL 231Landlord Funded Work connected with this Scheme

A review of maintenance and landlord liabilities is currently under way and consideration may be given to including some of this work in the contract should it prove economic and pragmatic to do so.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Net Cost = £1,524 per m2

      - Gross Cost = £2,280 per m²

Revenue Implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    -

    25

    -

    67

    92

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

(a) Energy Costs

        It is anticipated that the additional increase in fuel cost for the school will be in the order of £4.27 per m², or £1,924 per annum.

(b) Maintenance Costs

      The detailed design and choice of materials will minimise future maintenance liability.

      2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

          Following a successful bid to the DfES for borrowing authority, the scheme detailed in this report has been produced to increase the school capacity to 1,750 places in line with the forecast numbers on roll. On completion of this project the double temporary classroom on site will be removed.3. DETAILS OF SITE

          LOCATION

          Brune Park Community School is located at Military Road, Gosport.

          ADJOINING LAND AND BUILDINGS

          The site is bounded by allotment gardens to the east, playing fields to the north and industrial development to the west. The route of the proposed Light Rapid Transport railway system runs southeast to northwest along the western school boundary. To the south of the site is Fort Rowner.

          AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

          The total site area is 20.57 acres (8.32 hectares). The DfES guideline for a school of this size is 27.75-29.97 acres (11.23-12.13 hectares).

          PLANNING POSITION

          A formal planning application was submitted to the Environment Department during September 2003.

          SUITABILITY FOR PROJECT

          These proposals have been approved by the Headteacher and Governors of the School as meeting the accommodation requirements of the School.

          RESULTS OF TRIAL BORE HOLES

          The ground investigation revealed highly shrinkable clay over sand and gravel. It is recommended that suspended ground floor slabs are used for both buildings.

          Mass concrete strip footings which support the perimeter walls and precast concrete planks will be used for the Dance Studio extension.

          Strip footings with an in situ suspended concrete ground floor slab cast on clay board will be used for the Dining Hall extension.

          ACCESS

          Pedestrian and vehicular access to the site is from Military Road. For the duration of the works, a separate contractor's entrance will be formed from Military Road into a temporary compound on the site of the existing staff car park. The car park will be reinstated on completion of the works. Secure hoarding and safe crossing points will be formed within the school site to ensure the safety and separation of staff, visitors and pupils from the contractor's operations.

          COMMENTS ON SITE LAYOUT

          The school site is roughly diamond shaped with the school buildings situated to the south and along the eastern boundary. Vehicular and pedestrian access is from Military Road to the east and the school playing field extends to the north of the school buildings.

          The new dance studio will be located to the north of the existing school hall. The dining hall extension is located to the south of the existing dining hall.

          MAINS SERVICES POSITION

          The main incoming electricity supply requires reinforcement and the main electrical switchgear requires replacement.

          MAINTENANCE IMPLICATIONS

          The site will continue to be maintained in accordance with current County Council standards.

          LANDSCAPE PROPOSALS

          Dining Hall - minor landscaping consisting of a paved approach to the extended building, including dropped kerbs and ramps to improve accessibility.

          Dance Studio - the location of the building naturally forms a new courtyard area which will be enclosed by a new boundary wall. The new courtyard will be used as an external recreation area, bringing into use an area that was originally out of bounds to the students. There will be some associated tree/shrub planting in this area.

      4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION

          TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

          Dance Studio

          The new dance studio will provide the following accommodation:

          · 200m² dance studio with semi-sprung timber floor, dance barres and mirrors

          · Facility for Bleacher seating at a future date

          · Accessible wc/shower for use of staff, disabled pupils and visiting performers

          · Dance office

          · Store

          · Plant room

          · Mezzanine level control gallery and store

          Dining Hall extension

          The dining hall extension will provide the following accommodation:

          · 100m² extension to existing 235m² dining hall

          · Ramp to replace existing steps to provide access to accessible wc and former stage area, providing breakfast-bar style seating area

          · Lobby to be widened for better access to dining hall

          · Two new window openings for light and ventilation

          PLACES PROVIDED

          On completion of this project, the school will have a capacity of 1,750 places.

          PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

          The original school was built during 1964 with further accommodation being added during the late 1960's, 70's and 80's along with a teaching block constructed during 1994 and a science laboratory constructed during 1997. The latest addition was a drama block erected during 2001. The buildings are considered to be in good condition for their age and type.

          TEMPORARY BUILDINGS

          There is one double temporary building on site, which will be removed at the end of the contract.

          SITUATION ON SITE AND ENVIRONMENTAL IMPACT

          The proposed scheme has been sited and designed to have minimal environmental impact and to reflect the character of the existing school buildings. The new Dance Studio will naturally form a new courtyard area which will be enclosed by a new boundary wall, to be used as a play area, bringing into use an area that was originally out of bounds to the students. This scheme also facilitates the removal of one temporary classroom presently on site.

          TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

          Dance Studio - sand faced Fletton brick to match existing. Roof - copper to match the neighbouring building. High level glazed screen to provide natural north light and maintain privacy.

          Dining Hall - sand faced Fletton brick to match existing. Roof - combination of copper edge trims and high performance covering. Glazing to be aluminium framed clerestorey for ventilation and natural light.

          FACILITIES FOR THE DISABLED

          The Dance Studio scheme has been designed to provide level access throughout. An accessible wc/shower will be provided within the Dance Studio for use by staff, pupils and visiting performers. Ramping to replace existing steps in the dining hall will provide access to accessible wc and former stage area.

          HEATING AND VENTILATION SYSTEMS

          Dance Studio - a new mechanical supply and extract ventilation system will be provided to the main dance studio to maintain fresh air levels. A plant room located air handling unit will transfer the fresh air and remove the stale air via a ductwork distribution system and supply/extract grilles. Mechanical extract ventilation and a local instantaneous hot water heater will be provided to the wc's. A new gas fire boiler system will be provided to heat the studio building with heating distribution pipework feeding radiators and the dance studio ventilation system.

          Dining hall extension - mechanical ventilation will be provided by means of wall-mounted extract fans. Local modifications will be carried out to the existing unit heaters to cater for the new layout and new heaters will be provided to the extension to match.

          SPRINKLER SYSTEM

          This is not a stand-alone building on a green field site and, in addition, a risk assessment concludes this to be very low fire risk category buildings and therefore a sprinkler system will not be installed.

          ENERGY EFFICIENCY OF BUILDING

          The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

          ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

          These proposals have been approved by the Headteacher and Governors of the school and are considered to be the most appropriate way of providing the required accommodation.

          CAR PARKING

          No additional parking spaces will be provided as part of this scheme.

          CONSULTATIONS

          The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Director of Environment, Chief Fire Officer, local County Councillor.

      5. THE BUILDING DEVELOPMENT

          The proposals outlined in this appraisal will provide a dance studio and extended dining facilities to meet the needs of the school.

      6. BUILDING MANAGEMENT

          CLEANING

          Existing arrangements will apply.

          CATERING

          Existing arrangements will apply.

      7. FURNITURE AND EQUIPMENT

          From the block vote in the Education Committee's Capital Programme.

      8. STAFFING

          No change in staffing arrangements.

      9. FEES

          Architectural Services } Property, Business & Regulatory

          Quantity Surveying } Property, Business & Regulatory

          Electrical and Mechanical Engineering } Property, Business & Regulatory

          Structural Engineering } Price & Myers