Education Buildings Advisory Group 29 September 2003 Executive Member - Education 16 October 2003 Brune Park Community School, Gosport
Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
2.3 |
The new dance studio and dining room extension will be constructed of sand faced Fletton brick. The dance studio will have a copper covered roof to match the adjacent pitched roofs and the existing school. | |
2.4 |
Landscaping associated with this scheme includes the formation of a new courtyard area to be used as an enclosed external recreation area, improved accessibility to the school comprising dropped kerbs and ramps and some associated tree and shrub planting. | |
3. |
Funding and Timing | |
3.1 |
An allocation of £849,000, excluding fees, has been made in the Education Committee's 2003/04 Capital Programme, Public Service Agreement funding of £172,000, excluding fees, and a School contribution of £80,000, excluding fees, has been confirmed. | |
3.2 |
Subject to the necessary approvals it is anticipated that tenders will be invited during March 2004, work will commence on site during June 2004 and be completed during February 2005. | |
Conclusion |
||
The proposals outlined in this appraisal will provide a dance studio and extended dining facility to meet the needs of the School. Approval is accordingly sought to the attached building design project appraisal. | ||
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
TITLE LOCATION
Architect's plans PMIS file
Building Profile Reports TMH