Archived decisions

      HAMPSHIRE COUNTY COUNCIL

    BUILDING DESIGN PROJECT APPRAISAL

      EDUCATION BUILDINGS ADVISORY GROUP

      29 SEPTEMBER 2003

      EXECUTIVE MEMBER - EDUCATION

      16 OCTOBER 2003

      BUILDINGS, LAND AND CONTRACTS PANEL

      22 OCTOBER 2003

      EXECUTIVE MEMBER - POLICY AND RESOURCES

      13 NOVEMBER 2003

    PROJECT:

    HILTINGBURY JUNIOR SCHOOL, CHANDLER'S FORD

    FOUR CLASSROOM EXTENSION

    COMMENCEMENT DATE:

    JANUARY 2004

    COMPLETION DATE:

    AUGUST 2004

    PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

    2003/ 04

      RECOMMENDATION:

      That the building design project appraisal for the Hiltingbury Junior School scheme be approved.

      1. FINANCE

    Capital Expenditure

    Current Estimate

    (at Aug `03 prices)

    £'000

    Capital Programme

    (at Nov '02 prices)

    £'000

    Buildings

    426

    327

    Fees

    59

    49

    TOTAL

    485*

    376

      * The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.

      Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total

    Cost

    £'000

    1. From Committee's own Resources:

    a) Capital Programme (NDS funding)

    327

    49

    376

    b) School (devolved capital)

    30

        -

    30

    c) Schools Access Initiative funding

    43

    7

    50

    2. P&R Landlord's budget

    26

    3

    29

    TOTAL

    426

    59

    485

Anticipated Devolved Capital allocations £'000

              2002/03 2

              2003/04 29

              2004/05 32

TOTAL 63 Landlord Funded Work connected with this Scheme

Landlord funded works associated with this scheme include demolition and reinstatement of a double temporary classroom in very poor condition, removal of existing glazing and associated works, removal of an existing external wall and associated works and provision of a temporary classroom, including foundations, electricity and access path.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Net Cost = £1,319 per m2

      - Gross Cost = £1,421 per m2

Revenue Implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    -

    -

    -

    26

    26

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

(a) Energy Costs

        It is anticipated that the additional increase in fuel cost for the school will be in the order of £684 per year or £3.75 per m².

(b) Maintenance Costs

      The detailed design and choice of materials will minimise future maintenance liability.

      2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

          Hiltingbury Junior School has a capacity of 360 places including 120 provided in two double temporary classroom units (one in very poor condition and the other in fair condition). There are 388 pupils on roll at present and it is forecast to drop to 335 by 2007/08. The proposed project will replace the double temporary classroom in very poor condition and also provide an ICT suite and a language unit (which will complement the provision in the infant school). The remaining double temporary classroom will be left on site for the time being.3. DETAILS OF SITE

          LOCATION

          Hiltingbury Junior School is located at Hiltingbury Road, Chandler's Ford.

          ADJOINING LAND AND BUILDINGS

          Hiltingbury Junior Schools occupies a shared site with Hiltingbury Infant School. The western boundary is bordered by community recreational facilities, all other boundaries by residential development.

          AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

          The total site area is 3.39 acres (1.37 hectares). The DfES guideline for a school of this size is 4.52-4.99 acres (1.83-2.02 hectares).

          PLANNING POSITION

          A detailed planning application was submitted to the Environment Department during June 2003.

          SUITABILITY FOR PROJECT

          As part of the Education Department's Modernisation Programme, the scheme provides a permanent extension consisting of two general teaching classrooms, IT suite and a Language Unit, to replace one of the temporary classrooms currently on site.

          The proposals outlined in this appraisal have been prepared in consultation with the County Education Officer and the Headteacher and Governors of the School.

          RESULTS OF TRIAL BORE HOLES

          The site consists of 80cm of made ground overlying the natural clayey sands known as Whitecliff Sand Pebble Beds.

          Conventional concrete strip or pad foundations with suspended pre-cast concrete floor between sleeper walls and strip foundations is recommended.

          ACCESS

          Current pedestrian and vehicular access to the site is from Hiltingbury Road to the north of the site.

          There is only one main vehicular entry point into the school site from Hiltingbury Road, and this will therefore be managed as part of the Health and Safety Plan and co-ordination with the various user groups. Once on the site and for the duration of the contract, it is proposed to utilise an existing access gate at the southwestern boundary, thus allowing contractor's vehicles direct access to the area of the extension. This gate adjoins the Borough Council's community recreational and car parking facilities. Consequently, vehicular access to this point for the duration of the works has been agreed in principle by Eastleigh Borough Council.

          COMMENTS ON SITE LAYOUT

          The proposed extension will be sited on the current location of one of the temporary timber buildings. It will involve the demolition of the existing temporary building and the removal of two silver birch trees. It is proposed to provide a double temporary building for the duration of the construction of the extension, to be sited to the northeast of the school building.

          MAINS SERVICES POSITION

          The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.

          MAINTENANCE IMPLICATIONS

          The site will continue to be maintained in accordance with current County Council standards.

          LANDSCAPE PROPOSALS

          · The site will be regraded and reseeded to align with the existing site levels and current grassed landscape areas

          · New buff paving slabs will be used to form the external covered area with ramped access provided to align with the existing pavement levels

          · Where the existing temporary classroom block is removed, the ground surface will be made good and reseeded to match the current grassed landscape.

      4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION

          TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

          It is proposed to replace one temporary building currently on site with a permanent extension, providing:

          2 general teaching classrooms

          IT suite

          Language unit

          Classroom stores

          General store

          Corridor with cloakroom bays

          PLACES PROVIDED

          60 replacement.

          PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

          The existing main school building was constructed in 1969 and is SCOLA design. The building is considered to be in fair condition for its age and type.

          TEMPORARY BUILDINGS

          There are currently two temporary classrooms on site, one of which will be demolished on commencement of the works as it is located on the area of the proposed new classroom extension. The second temporary classroom to the southwest corner of the site will be retained. It will be necessary to site an additional temporary classroom to the northeast of the school building for the duration of the contract.

          SITUATION ON SITE AND ENVIRONMENTAL IMPACT

          The proposed extension is sited and designed to have minimum environmental impact. Pupils and staff will not be increased as a result of this extension and thus no additional car parking will be provided.

          TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

          The extension is designed to be a two-storey structure, generally to align with the height of the existing building.

          The extension will be constructed of red facing brickwork, with aluminium doors and windows, all to complement the overall appearance of the existing building. The proposals will incorporate a roof overhang and brise soleil, to provide solar shading to the south elevation, thus also providing an area of covered external play. Individual coloured glass blocks will be incorporated on both the west and north elevations as a feature to the brickwork panels.

          FACILITIES FOR THE DISABLED

          The proposed extension will adjoin at the floor level of the main school building, thus providing access to the main special needs facilities housed within the existing school.

          The extension will incorporate level thresholds generally and where necessary contrasting colours and materials will be incorporated, particularly for final exit and stair areas.

          HEATING AND VENTILATION SYSTEMS

          The proposed new classrooms will be naturally ventilated. Additional mechanical ventilation will be provided to the IT suite.

          The building will be heated by radiators.

          SPRINKLER SYSTEM

          This is not a stand-alone building on a green field site and, in addition, an assessment concludes this to be a very low fire risk category building and therefore a sprinkler system will not be installed.

          ENERGY EFFICIENCY OF BUILDING

          The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

          ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

          This scheme has been agreed by the Headteacher and Governors of the School as being the most appropriate design to provide the teaching accommodation required by the school.

          CAR PARKING

          Pupil and staff numbers will not increase as a result of this scheme and therefore no additional car parking will be provided.

          CONSULTATIONS

          The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Director of Environment, Chief Fire Officer, local County Councillor.

      5. THE BUILDING DEVELOPMENT

          The proposed classroom extensions will provide the teaching accommodation required by the school whilst facilitating the removal of one temporary classroom from the site.

      6. BUILDING MANAGEMENT

          CLEANING

          Existing arrangements will apply.

          CATERING

          Existing arrangements will apply.

      7. FURNITURE AND EQUIPMENT

          From the block vote in the Education Committee's Capital Programme.

      8. STAFFING

          The staffing requirement of the school will not change as a result of this scheme.

      9. FEES

          Architectural Services } Property, Business& Regulatory

          Quantity Surveying } Davies Langdon & Everest

          Electrical and Mechanical Engineering } Giffords

          Structural Engineering } WSP