Archived decisions
HAMPSHIRE COUNTY COUNCIL
BUILDING DESIGN PROJECT APPRAISAL |
EDUCATION BUILDINGS ADVISORY GROUP
29 SEPTEMBER 2003
EXECUTIVE MEMBER - EDUCATION
16 OCTOBER 2003
BUILDINGS, LAND AND CONTRACTS PANEL
22 OCTOBER 2003
EXECUTIVE MEMBER - POLICY AND RESOURCES
13 NOVEMBER 2003
PROJECT: |
LEE-ON-SOLENT JUNIOR SCHOOL | |
EXTENSIONS TO RECEPTION, ADMIN, TEACHING AND LIBRARY AREAS | ||
COMMENCEMENT DATE: |
MARCH 2004 | |
COMPLETION DATE: |
SEPTEMBER 2004 | |
PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME: |
2003/ 04 | |
RECOMMENDATION:
That the building design project appraisal for the Lee-on-Solent Junior School scheme be approved.
1. FINANCE
Capital Expenditure |
Current Estimate (at Nov '02 prices) £'000 |
Capital Programme (at Nov '02 prices) £'000 |
Buildings |
259 |
138 |
Fees |
33 |
22 |
TOTAL |
292* |
160 |
* The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.
Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total Cost £'000 |
1. From Committee's own Resources: |
|||
a) Capital Programme (as above) |
138 |
22 |
160 |
b) Capital Programme contingency |
13 |
2 |
15 |
c) Seed Challenge |
30 |
5 |
35 |
2. School contribution |
65 |
2 |
67 |
3. From other resources: Policy & Resources NDS Condition |
13 |
2 |
15 |
TOTAL |
259 |
33 |
292 |
Anticipated Devolved Capital allocations £'000
2002/03 19
2003/04 22
2004/05 26
TOTAL 67
Landlord Funded Work connected with this Scheme
Drainage and level issues are to be addressed and to be funded through NDS Condition money.
Value of Land already acquired for this Project
The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.
Building Cost - Net Cost (excluding abnormals) = £1,481 per m2
- Gross Cost = £2,240 per m2
Revenue Implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
- |
- |
- |
15 |
15 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
(a) Energy Costs
It is anticipated that the additional increase in fuel cost for the school will be in the order of £281 per year or £3.75 per m².
(b) Maintenance Costs
The detailed design and choice of materials will minimise future maintenance liability.
2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT
Owing to a projected growth in pupil numbers (rising to 350 by September 2007) there is a need to build a one classroom extension to bring the capacity of the school up to 360 places.
At the same time there is an opportunity to extend the library and provide a new entrance.3. DETAILS OF SITE
LOCATION
Lee-on-Solent Junior School is situated at Salisbury Terrace, Lee-on-Solent.
ADJOINING LAND AND BUILDINGS
The school occupies a shared site with Lee-on-Solent Infant School. The site and neighbouring common ground combine to form a large area of open space containing several community facilities which are surrounded on all sides by medium density residential developments dating from the early 20th century.
AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS
The total site area is 5.5 acres (2.2 hectares). The DfES guideline for a school of this size is 4.51-5.00 acres (1.83-2.02 hectares).
PLANNING POSITION
An application for detailed planning permission was submitted to the Environment Department during August 2003.
SUITABILITY FOR PROJECT
These proposals have been approved by the Headteachers and Governors of the School as meeting the accommodation requirements of the School.
RESULTS OF TRIAL BORE HOLES
Results of site investigations are awaited.
ACCESS
Pedestrian and vehicular access are from Hollybank Road. It is anticipated that the compound for the works will be sited on the site of the proposed new car park. The final surface of the proposed new car park will be laid on completion of the works on site.
COMMENTS ON SITE LAYOUT
The site is rectilinear in shape, the Junior School being sited to the south of the site, the Infant School to the north. Presently the School's entrance and administrations areas are too small and not ideally positioned. It is proposed that the new main entrance to the building is to be located immediately in front of the gates to the schools' grounds. This location provides the school with an additional level of security with clear views towards the site entrance and northwards to the route between the two schools. The position, combined with the clear visual signposting of the building, will make it clearer to visitors where the entrance is located.
MAINS SERVICES POSITION
The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.
MAINTENANCE IMPLICATIONS
The site will continue to be maintained in accordance with current County Council standards.
LANDSCAPE PROPOSALS
As part of the work to the car park extension, a low height fence will be erected around the car park to form a barrier between pedestrian and vehicular movements, which is currently a Health and Safety issue in this area. The only additional hard surfacing is to be a continuation around the extension of the existing paved strip surrounding the SCOLA block.
4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION
TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED
It is proposed to construct an extension for reception and administrative facilities to the original Edwardian school building, and an extension of teaching and library spaces on the later SCOLA wing. These extensions will be the final phase of the school's planned growth, bringing its capacity up to a 3 Form Entry. The existing car park is to be extended to reflect the additional demand from the school. The entrance and administrative areas are too small for the school's current needs and not ideally positioned. It is proposed that the new main entrance to the building be located immediately in front of the gates to the school grounds, providing an additional level of security with clear views towards the site entrance and northwards to the route between the two schools.
The works to the SCOLA building consist of one new classroom and the extension of the existing library. This will be linked to the recently constructed classroom extension.
PLACES PROVIDED
30 additional places.
PRESENT/REDUNDANT BUILDINGS AND FUTURE USE
The building consist of a traditional main school building, with classroom extensions added in 1975, 2002 and 2003.
TEMPORARY BUILDINGS
There are no temporary buildings on site and none are required for this scheme.SITUATION ON SITE AND ENVIRONMENTAL IMPACT
The extensions have been designed and materials chosen to match or complement existing buildings on site. The works to the SCOLA building and extension of the existing library will rationalise this area by bringing the building line out to result in a `complete' squared-off single storey block.
TYPE OF CONSTRUCTION, FINISH AND APPEARANCE
The new entrance and administration area are to be built using a timber frame with floor to ceiling glazing and entrance doors. A white rendered masonry wall with new signage complements the existing white-painted rendered wall adjacent to the entrance doors.
The new classroom and library extension are to be built in the same style as the recent extensions. The proposed materials are red brick with timber framed windows and doors and natural timber cladding. The roofs to both extension will be a high performance covering at the same level as the adjoining existing roofs.
FACILITIES FOR THE DISABLED
A new ramped access will be constructed to the new school entrance.
HEATING AND VENTILATION SYSTEMS
Admin extension - the existing heating system will be extended and modified to serve the new extension.
Classroom/Library extension - the existing heating system will be extended and modified to serve the new extension.
The roof of the new medical room will contain a ventilation extract system.
SPRINKLER SYSTEM
This is not a stand-alone building on a green field site and, in addition, an assessment concludes it to be a very low fire risk category building and therefore a sprinkler system will not be installed.
ENERGY EFFICIENCY OF BUILDING
The estimated annual energy consumption for the new building will meet that required by current Building Regulations.
ALTERNATIVE STANDARDS OF PROVISION CONSIDERED
These proposals have been approved by the Headteacher and Governors of the School as meeting the accommodation requirements of the School.
CAR PARKING
The existing car park is to be extended to reflect the additional demand from the school, from the current 12 spaces to a new total of 18 spaces (inc. one disabled space). As part of this work, the entire car park is to be surrounded in a low height fence in order to form a barrier between pedestrian and vehicular activity.
CONSULTATIONS
The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Environment Department, Chief Fire Officer, local County Councillor.
5. THE BUILDING DEVELOPMENT
The proposed scheme will provide improved reception, administrative, teaching and library facilities at the school, will rationalise recent additions to the SCOLA building, provide an additional level of security at the site entrance plus additional and improved car parking facilities.
6. BUILDING MANAGEMENT
CLEANING
Existing arrangements will apply.
CATERING
Existing arrangements will apply.
7. FURNITURE AND EQUIPMENT
From the block vote in the Education Committee's Capital Programme.
8. STAFFING
The staffing requirement of the school will not change as a result of this scheme.
9. FEES
Architectural Services } Format Milton
Quantity Surveying } John Watson & Carter
Electrical and Mechanical Engineering } EDP
Structural Engineering } R J Watkinson