Hampshire County Council Eastleigh Highway Management Advisory Panel 17 October 2003 Highway Maintenance and Minor Capital Works Report of the Director of Environment |
Item 6 |
Contact: Derek Goodchild, tel 023 80 68822
email:[email protected]
1. Summary
1.1 This report outlines progress with regard to the 2003/04 Highway Maintenance and Minor Capital Works programmes and gives an update on the 2003/04 Highway Maintenance budget.
2. Background
2.1 As previously reported, the Highway Maintenance programme is funded from both revenue and capital allocations.
2.2 The revenue maintenance programme funds minor works, such as pothole repairs and routine drainage work, including gully cleaning, signs and road markings, environmental maintenance of grass verges, trees and shrubs, weed control and highway emergencies. Minor bridge works and winter maintenance are also funded from revenue. Budget allocations are set at a level that ensures the safety and serviceability of the highway network.
2.3 The capital maintenance programme funds planned maintenance, including special maintenance, resurfacing and surface dressing, and also provides for essential repairs to the structure of the highway.
3. Highway Maintenance Budget and Programme 2003/04
3.1 The Highway Maintenance budget for 2003/04, approved by the Executive Member for Environment, is £46,889,000. This sum comprises £19,615,000 revenue funding and £27,274,000 funding from the capital programme provision.
Revenue Maintenance Budget and Programme
3.2 The total allocation for Eastleigh for 2003/04 is £518,000. Progress throughout the year has been in line with the spend profile and it is expected that the programme will be completed within time and budget constraints. A budget monitoring statement is attached as Appendix 1.
3.3 The revenue maintenance programme funds three main areas of highway maintenance:
(i) reactive minor repair works on the road and footway network;
(ii) minor traffic management improvements of signs and road markings; and
(iii) the environmental aspects of highway maintenance, including grass cutting, weed treatment, and tree and shrub maintenance.
3.4 Additional revenue budgets are held centrally for the performance elements of the County Council's term maintenance contract. The performance-based work contained in the contract includes:
(i) gully emptying;
(ii) visibility splay grass cutting;
(iii) winter maintenance;
(iv) routine bridge maintenance; and
(v) `A' road routine maintenance.
Capital Maintenance Budget and Programme
3.5 The total revised allocation for Eastleigh for 2003/04 is £1,311,000, which includes £195,000 from the £3.5 million county-wide additional funding previously reported. The funding allocation for the capital maintenance `planned works' programme is based on the proven HAMP rating system and reflects the agreed intervention levels. The HAMP rating intervention level directs funding to those maintenance schemes displaying a higher maintenance need. Planned structural maintenance repairs undertaken through the capital maintenance programme include surface dressing, special maintenance and resurfacing schemes.
3.6 This year's schemes are progressing well, with the expectation that the `planned' maintenance programme will be delivered within time and budget constraints. Some minor amendments to the programme have had to be made, as certain schemes have been completed well within budget and others have needed to be revised with new estimates, as the original scheme submissions had not been updated for a few years. Savings from a superseded carriageway stabilising scheme have been reallocated to emergency carriageway reconstruction works in another part of Hampshire Highways East. One resurfacing scheme will be deferred to 2004/05 once major development works affecting the road have been completed. Schemes identified by Members as local priorities have also been included in the current programme or for early inclusion in the 2004/05 programme. Progress on this year's schemes is shown in Appendix 2.
3.7 The capital maintenance programme also supports the centrally-controlled areas of work, including major maintenance schemes and bridge maintenance.
3.8 Surface dressing is an extremely cost-effective way of prolonging the life of the carriageway, sealing cracks and restoring skid resistance. The total budget county-wide of £3,297,000 is managed centrally and for 2003/04 supported a HAMP intervention level of 50 on the principal road network. High performance surface dressing on non-principal roads has a HAMP intervention level of 60 and 70 for the urban and minor roads programmes respectively. The sites on this year's programme for Eastleigh have now been successfully treated, although two roads were not completed because of problems of traffic disruption and inadequate access, and one site was not started because there were too many problems of parked vehicles. The footway surface dressing programme was also completed successfully. This year's schemes are listed in Appendix 2.
4. Minor Capital Works
4.1 The Minor Capital Works programme (also known as the Under £10,000 programme) is funded from the capital allocation based on the Local Transport Plan submission to the Department for Transport. A sum of £16,000 was allocated for the Eastleigh area in 2003/04 and the schemes included in the programme are:
Chestnut Avenue, Eastleigh - footway widening for £6,000
pedestrians and cyclists
Hound Road, Hound, at Church layby - upgrade £4,000
footway to include cycleway
Fair Oak Road, Fair Oak - provision of pedestrian £6,000
phase to Sandy Lane traffic signals
_______
Total £16,000
These schemes are scheduled to be completed by the end of the year.
Recommendation
That this report be noted.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None. |
8267/DG
APPENDIX 1
HAMPSHIRE HIGHWAYS EAST ( EASTLEIGH)
|
2003/04
|
2003/04 (revised) |
% committed | ||
Revenue Budget 2003/04 |
|||||
Routine Maintenance (carriageway, footway repairs) |
£202,000 |
£202,000 |
|||
Gully Cleansing |
£4,000 |
£4,000 |
|||
Aids to Movement (signs and road markings) |
£80,000 |
£80,000 |
| ||
Hazard Clearance |
£16,000 |
£16,000 |
| ||
Traffic Management Traffic Regulation Orders (Agency) |
£11,000 |
£11,000 |
| ||
Environmental (grass, trees, shrubs) (Agency) |
£152,000 |
£152,000 |
| ||
Weed Control |
£53000 |
£53000 |
|||
Total Revenue budget |
£518,000 |
£518,000 |
63% | ||
Capital Budget 2003/04 Principal Roads |
|||||
Principal Roads Routine Structural Repairs |
£18,000 |
£18,000 |
|||
Principal Roads Special Maintenance |
£76,000 |
£76,000 |
|||
Principal Roads Resurfacing |
£0 |
£0 |
|||
Total |
£94,000 |
£94,000 |
19% | ||
|
|||||
Capital Budget 2003/04 Non-Principal Roads |
|||||
Non-Principal Roads Routine Structural Repairs |
£364,000 |
£374,000 |
| ||
Non-Principal Roads Special Maintenance |
£417,000 |
£417,000 |
| ||
Non-Principal Roads Resurfacing |
£351,000 |
£312,000 |
|||
Footway Maintenance |
£195,000 |
£195,000 |
| ||
| |||||
Non-Principal Roads Tactile Paving Crossing Points |
£13,000 |
£13,000 |
|||
Total Total Capital budget all roads |
£1,340,000 £1,434,000 |
£1,311,000 £1,405,000 |
60% 57% | ||
Total Highway Maintenance Budget (Revenue and Capital) |
£1,952,000 |
£1,923,000 |
59% | ||