Archived decisions
WORKS |
CONTRACTOR(S) |
VALUE |
SELECTION METHOD |
REASON FOR PROCUREMENT STRATEGY | |
Framework Agreement for Major Schemes | |||||
Additional Nursing Care Beds (Phase 1) | |||||
Ticehurst Oakridge House |
Brazier |
4,540,000 (est) 4,560,000 (est) |
· Invitation to negotiate based upon Framework proposals following earlier involvement over design development |
· Essential to collaborate with selected firms to resolve programme and technical matters at an early stage · Jointly develop key supply chains in order to maximise the benefit of scale and the repetitive nature of the programme of works · Joint financial and risk management in order to ensure greater certainty related to issues of time, quality and cost. · Opportunity to investigate continuous improvement through the framework arrangements | |
Coldeast Hospital |
HBG |
5,720,000 (est) | |||
South Basingstoke Schools Reorganisation | |||||
Manor Field Infant and Junior Schools Hatch Warren Infant and Junior Schools Chalk Ridge Primary School |
Wates |
1,948,000 (est) 1,860,000 (est) 412,000 (est) |
· Invitation to negotiate based upon best value proposals |
· Collaborate with the selected framework contractor over design and programming of the works · Involvement of a contractor in resolving technical issues associated with a major reorganisation package · Achieve an economy of scale by combining the schemes as a single package of work · Early opportunity to involve a framework contractor with a major development | |
Social Services Re-investment Strategy | |||||
Malmsbury Lawn Home for the Elderly Refurbishment |
Balfour Beatty |
1,559,000 |
· Invitation to negotiate a second stage tender based upon best value proposals |
· Pre contract early contractor involvement desirable in order to resolve design and technical issues associated with this major refurbishment · Early involvement of a contractor regarding programme and phasing arrangements · Potential synergy with the DoH project (also through the framework) and the need to drive continuous improvement into that project | |
Partnered Projects (Major Schemes) | |||||
New Sports Halls Eastleigh Crestwood (including Drama and Fitness ) Alton Eggars (including Classrooms) Wyvern (including refurbishment of existing Sports facilities) This project is subject to an adjusted level of funding to be agreed with Sport England and County Education Officer Test Valley School (incorporating Basic Need Accommodation) Fernhill |
Brazier |
1,900,000 (est) 2,120,000 (est) 2,187,000 2,246,000 (est) 1,298,405 |
· Invitation to undertake further schemes on the basis of previous best value submission |
· Further collaboration with a preferred contractor over design and construction of a standard sports hall solution · Establish supply chains for key components and specialist designed elements · Consideration of package procurement to achieve economies of scale · Involvement of a preferred contractor with key enabling works in advance of the main contracts | |
Brookfield School Performing Arts Building |
Brazier |
1,460,000 (est) |
· Invitation to undertake further schemes on the basis of best value submission |
· Major contractor with Design Development expertise required to complete the design and to procure this scheme in line with the agreed programme · Early involvement of a preferred contractor desirable in order to carry out key enabling works in advance of the main contract · Early involvement of Key Specialist Subcontractors also desirable in order to procure these packages in line with the main building programme. | |
Wildern School New multi-use Sports Hall and Learner Pool |
HBG |
1,850,000 (est) |
· Invitation to negotiate based upon a cost limit for develop and construct tender partnership |
· Existing develop and construct contractor's team have recently successfully completed a major project at the same site · Need to procure this package of work in a short timescale to meet the agreed programme; this will involve some overlapping of the design and procurement and is best managed through these arrangements · Contractor with good track record in delivering complex projects through a partnership approach · Will be able to establish cost certainty in the shortest possible time | |
Best Value Single Stage Tendering | |||||
Alton Library |
Richardsons |
1,274,000 |
· Short list of three preferred firms invited to tender on the basis of best value proposals |
· Complex town centre project which would benefit from involvement of preferred contractor · Essential to incorporate evaluation of contractor's site management proposals as part of the tender evaluation process · Maximise programme and cost certainty | |
Elvetham Heath School Enlargement to 2FE |
H N Edwards Mansell Trant |
1,174,000 (est) |
· Short list of three major contractors invited to tender on the basis of best value proposals |
· Essential to evaluate contractors proposals as part of a best value tendering process for this significant project to extend the recently completed school · · Ensure a good understanding of the project, programme and the site Health and Safety management · Evaluation of supply chains and programme to assure effective delivery of this project | |
Negotiated Work | |||||
Warblington School Internal alterations to Technology Block |
Bensons |
1,098,260 |
· Negotiation based upon a two stage tendering process |
· Early contractor involvement in programming and phasing of work to achieve a short construction period in order that the facilities are operational at the commencement of the new academic year. · Contractor with established supply chains for this type of scheme who are able to mobilise at short notice · Previous good performance on similar projects | |
Henry Beaufort School Improvements to Dining Area, Kitchen, ICT and CDT |
Richardsons |
349,980 |
· Invitation to negotiate |
· Schemes transferred to an alternative preferred contractor following financial difficulties encountered by original firm · Contractor with capacity and resources to take on these projects and respond at short notice · Ensure continuity with original programme intact · Retain the benefit of tendered work to date including utilising existing supply chains, pricing and programme structure · Contractor has a successful track record of delivering similar schemes | |
Calthorpe Park School Additional Teaching Accommodation |
Richardsons |
1,201,500 · · | |||
Brune Park Community School Window/Cill replacements |
John Hobden |
103,500 (est) |
· Negotiation with existing contractor on site |
· Continuity with works already underway of a similar character · Single point of responsibility for all works being undertaken at the site · Existing rates and prices will form a sound basis for negotiation · Economy of scale through a larger package of work | |
Electrical Installation T&I Programme |
Caradas Technical Services |
250,000 (est) |
· Negotiation with preferred contractor based upon pricing for previously completed work |
· To resolve procurement and access issues at an early stage · Sensible to engage early with a preferred contractor who has successfully delivered similar work over recent years | |
Elson Infant School Library Extension |
Gregory Havant |
85,000 |
· Negotiation with preferred contractor on the basis of a develop and construct package |
· This contractor has combined successfully on a number of schemes with the same Architectural team to deliver projects for the County Council · Enables a fairly short pre-contract period in order to take advantage of project commencement over the Summer period · This contractor has achieved a good to excellent performance in the delivery of previous projects | |
Horndean and Noadswood Schools Fire Alarm Installation |
Prestige Fire Protection |
215,000 |
· Negotiation with preferred contractor |
· In order to meet the intended Autumn start it is sensible to engage with a preferred contractor over procurement and access · Consistency with work being done through Term Engineering Contracts with same specialist · Sound basis to negotiate using previous pricing models · This contractor has a track record of producing work to a high quality
| |
Fitting out Unit B, Winnall |
H N Edwards |
160,000 |
· Negotiation with preferred contractor |
· Further phase of work required which it would be sensible to undertake through original contractor · Established rates and prices to quickly agree cost · Pre-planning and programme management | |
Hounsdown School Dining Room Extension |
TAB |
176,000 |
· Invitation to negotiate |
· This project will be undertaken on a develop and construct basis owing to programme constraints · TAB have successfully undertaken work at the school under similar arrangements · · Contractor with resources available in the required timescale · Previous good working relationship with School and Department · Early cost and programme certainty required to launch scheme | |
The Hurst Community School Fire Alarm Installation |
W Churches |
90,000 |
· Invitation to negotiate |
· Continuity with other work undertaken with the same specialist throughout the County · Sound basis to negotiate using previous pricing models · Established preferred contractor for this type of work | |
Primary School Sites Playing Field Drainage Schemes comprising a Package of 13 Sites |
Swanwick Construction Kieron Beattie Landscaping |
167,000 (est) |
· Invitation to negotiate |
· Packages of work added to a competitively tendered larger package to ensure these further sites are completed over the summer holiday period · Both contractors have capacity in required timescale and the competitively tendered rates will form a sound basis for the negotiation | |
Serles House Winchester Phase 1b and 2 |
R V Dart Everest Construction Richardsons Tew Bros |
221,000 (est) |
· Competitively tendered Phase 1b to a short list of specialist contractors and negotiation of Phase 2 with successful contractor |
· Limited number of firms suited to this type of work · Would enable Phase 2 to be design developed for greater cost certainty with specialist firm working alongside the design team. · · Reduction in contractor set up costs by combining both schemes through a single contractor | |
Sharpes Copse Primary School Early Years Centre |
Brazier |
480,453 |
· Negotiation with preferred contractor |
· To involve a preferred contractor with the development of the scheme who has a good understanding of site security issues which may be faced · Established good working relations with school and work of a high standard · To resolve access and phasing issues at an early stage · Established pricing framework from earlier phase of work undertaken at the site | |
Woodcott Primary School Re-cladding and re-roofing |
D M Habens |
134,000 (est) |
· Negotiation with existing preferred Contractor |
· Further phase of work as a continuation of work already underway · More efficient programme delivery and cost certainty at an early stage through existing pricing structure · `open book' tendering for new works and reduced/lower site set up costs due to continuity of work | |
Marchwood Junior School Additional classrooms |
Bensons |
740,370 |
· Invitation to negotiation based upon previous partnering experience |
· Early involvement of preferred contractor required over enabling works phasing and implementation programme · · Established pricing frameworks from previous projects · Opportunity to engage with same contractor team who have just successfully delivered major partnership scheme for the County Council | |
Wildern School Science Laboratory Refurbishment |
HBG Construction |
156,201 |
· Negotiation with existing contractor on site |
· Continuity with works already underway of a similar character · Single point of responsibility for all works being undertaken at the site · Existing rates and prices will form a sound basis for negotiation · Economy of scale through a larger package of work | |
Single Stage Selective Tendering (Short List) | |||||
Laboratory Refurbishment Package 1 Crookhorn Community Purbrook Park Secondary Swanmore College of Technology Testbourne Community |
Benson |
1,155,492 |
· Short list of four preferred contractors |
· Proven track record required · To meet the needs of the school and achieve completion of the works during the school holidays. | |
Laboratory Refurbishment Package 2 Crestwood Community Noadswood Secondary Toynbee Secondary |
Nolan Davis Contracting |
310,299 |
· Short list of three preferred contractors |
· Proven track record required · To meet the needs of the school and achieve completion of the works during the school holidays. | |
Wavell Secondary Alterations to Library and ICT Areas |
Beavis & Partners |
130,169 |
· Short list of four preferred contractors |
· Proven track record required · To meet the needs of the school and achieve completion of the works during the school holidays. | |
Negotiated work NDS Projects for External Redecorations | |||||
Package one Audleys Resource Centre Buryfields Infant School Cliddesden Primary School Crookham Junior School Mottisfont Court The Butts Primary School The Clere School The Vyne Community School |
Pool & Son (Hartley Wintney) Ltd |
345,897 |
· Negotiation with preferred contractors |
· Demonstratable track record of delivering similar work to a high standard · Available resources in required timescale · Sensible to strategically package a group of projects with a reliable contractor · Established pricing frameworks will ensure value for money is achieved | |
Package 2 Birch House Fleet Library Grayshott Primary School Petersfield Secondary (F) School South Farnborough Infant School |
Belgravia Renovations |
241,993 · · | |||
Package 3 Locks Heath Infant School Locks Heath Junior School Northern Infant School Purbrook Park Community School Ranvilles Infant School 219 West Street - Fareham 110A West Street - Havant |
Mitie Property Services (Southern) Ltd |
427,515 · · | |||
Package 4 Emsworth Primary School Havant Registrars Meadowlands Infant School Padnell Junior School Sisken Infant School Siskin Junior School Warblington Secondary School |
Richardsons Decorating Contractors Ltd |
233,202 · · | |||
Package 5 Alton Registry Office Bungalow at Fort Nelson Porchester Community School St John the Baptist (Solomon's Lane) Three Minsters House The Mead Children's Home |
Robert G Warwick & Son |
264,494 |
· Negotiation with preferred contractors |
· Demonstratable track record of delivering similar work to a high standard · Available resources in required timescale · Sensible to strategically package a group of projects with a reliable contractor · Established pricing frameworks will ensure value for money is achieved | |
Package 6 Ashley Infant School Cranleigh Paddock Day Centre Fordingbridge Infant School Fordingbridge Junior School Langdown Infant School Langdown Junior School Masters House New Forest Family Resource Centre Romsey Infant School |
Ferris Painting |
198,427 · · | |||
Package 7 Acorns Early Years Harrow Way Community School Knights Enham Infant School Norman Gate School St Thomas Infant School |
Atkins Painting and Decorating (Contractors) |
131,448 · · | |||
Package 8 Chilcomb Sports Pavilion Freegrounds Infant School Freegrounds Junior School Gosport Day Services Gosport Family Centre Hook-with-Warsash Primary School Stoke Park Infant School Stoke Park Junior School Tower Arts Centre Wickham CE Primary School |
Tew Brothers Ltd |
318,847 · · | |||
SCOLA Re-cladding Strategy | |||||
Hamble Secondary School (completion) |
Benson Ltd and Wessex Windows |
288,000 (subcontract) |
· Competitive tendering with specialist windows package |
· Recladding works included in major Education Capital Programme project using an established preferred specialist to ensure continuity with previous phases | |
Alton Eggars (Phase 2) |
Drew Smith and Wessex Windows |
536,391 |
· Negotiation with preferred contractors |
· Both contractors have combined to give negotiated prices on Phase 1, working effectively together to minimise disruption to school · Continuity of utilising an established good working relationship to delivery this project | |
Flat Roof Maintenance Framework | |||||
Front Lawn Infant School Front Lawn Junior School Icknield Special School Kempshott Junior School Mill Rythe Junior School Petergate Infant School Poulner Junior School Preston Candover Primary School Romsey Junior School Saxon Wood Special School South View Junior School Wolverdene Special School |
Survey & Construction (Roofing) Ltd |
710,721 |
· Framework Agreement |
· Specialist contractor who can undertake a serial Contract for roofing work over an agreed term · Continuity of work and establishing common standards · Ability to `call off' schemes to an agreed programme · Value for money due to a larger package of work | |