    PROJECT:

    LEE-ON-SOLENT INFANT SCHOOL

    EXTENSIONS TO PROVIDE NURSERY AND MUSIC ROOM

    COMMENCEMENT DATE:

    MARCH 2004

    COMPLETION DATE:

    SEPTEMBER 2004

    PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

    2003/ 04

      RECOMMENDATION:

      That the building design project appraisal for the Lee-on-Solent Infant School scheme be approved.

      1. FINANCE

    Capital Expenditure

    Current Estimate

    (at Nov '02 prices)

    £'000

    Capital Programme

    (at Nov '02 prices)

    £'000

    Buildings

    293

    293

    Fees

    47

    47

    TOTAL

    340*

    340

      * The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.

      Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in the Education Committee's Capital Programme in the appropriate financial year.

    Financial Provision for Total Scheme

    Buildings

    £'000

    Fees

    £'000

    Total

    Cost

    £'000

    1. From Committee's own Resources:

    a) Capital Programme (as above)

    293

    47

    340

    TOTAL

    293

    47

    340

Anticipated Devolved Capital allocations £'000

              2002/03 12

              2003/04 20

              2004/05 22

TOTAL 54

Landlord Funded Work connected with this Scheme

There is no landlord funded work associated with this scheme.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Net Cost (excluding abnormals = £1,501 per m2

- Gross Cost = £2,180per m2

Revenue Implications

    (a)

    Employees

    £'000

    (b)

    Other

    £'000

    (a+b)

    Net Current

    Expenditure

    £'000

    (c)

    Capital

    Charges

    £'000

    (a+b+c)

    Total Net

    Expenditure

    £'000

    Revenue

    Implications

    Additional+

    /Reductions

    -

    -

    -

    18

    18

    Unit cost (£)

    (e.g. per place)

    -

    -

    -

    -

    -

    % variation to

    Committee's

    budget

    -

    -

    Number of

    additional

    Staff (fte)

    -

    -

(a) Energy Costs

        It is anticipated that the additional increase in fuel cost for the school will be in the order of £495 per year or £4.23 per m².

(b) Maintenance Costs

      The detailed design and choice of materials will minimise future maintenance liability.

      2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

          There is a growth in numbers at the school (projected to rise to 268 by September 2006) which requires a one classroom extension to take the capacity of the school to 270 places. The best way to achieve this is to relocate an existing playgroup in the school and provide them with a purpose-built unit. The space freed up by the playgroup will return to an infant classroom.

          At the same time, there is an opportunity to provide a music room, to provide the specialist accommodation for the delivery of that part of the national curriculum.3. DETAILS OF SITE

          LOCATION

          Lee-on-Solent Infant School is situated at Salisbury Terrace, Lee-on-Solent.

          ADJOINING LAND AND BUILDINGS

          The school shares a site with Lee-on-Solent Junior School. The site and neighbouring common ground combine to form a large area of open space containing several community facilities which are surrounded on all sides by medium density residential developments dating from the early 20th century.

          AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

          The total site area is 1.5 acres (0.6 hectares). The DfES guideline for a school of this size is 1.86-2.27 acres (0.75-0.92 hectares).

          PLANNING POSITION

          An application for detailed planning permission was submitted to the Environment Department during August 2003.

          SUITABILITY FOR PROJECT

          These proposals have been approved by the Headteachers and Governors of the School as meeting the accommodation requirements of the School.

          RESULTS OF TRIAL BORE HOLES

          Results of site investigation are awaited.

          ACCESS

          Pedestrian and vehicular access are from Elmore Road.

          COMMENTS ON SITE LAYOUT

          The site is rectilinear in shape, the Junior School being sited to the south of the site, the Infant School to the north.

          MAINS SERVICES POSITION

          The existing mains services are considered to be of sufficient capacity to be extended and adapted as required to serve the proposed additional accommodation.

          MAINTENANCE IMPLICATIONS

          The site will continue to be maintained in accordance with current County Council standards.

          LANDSCAPE PROPOSALS

          The nursery will benefit from a new external hard play area of approximately 90m². The existing paths around the school will be modified to maintain the existing paved route between the Infant and Junior schools. An existing seating area with planting which lies in the site of the proposed music room will need to be dismantled as part of the new works. It is proposed that the more mature plants are relocated and the timber sleepers that make up the seating area are utilised in the external works to the nursery.

      4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION

          TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

          It is proposed to construct two new extensions to the existing building on the northeast and southeast corners to house a new nursery and a new music room.

          The accommodation to be provided consists of:

          Nursery

          · nursery x 55m²

          · waiting area x 5m²

          · indoor store x 5m²

          · outdoor store x 4m²

          · outdoor play area x 90m²

          · outdoor covered area

          · reconfiguration of existing toilet area to provide 3 no wc to incl one accessible wc

          Music Room

          · music room x 45m²

          · indoor store x 5m²

          · outdoor store x 7m²

          · outdoor covered area

          · reconfiguration of existing toilet area to provide 3 no wc to incl one accessible wc

          PLACES PROVIDED

          30 additional places.

          PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

          The Infant School consists of a SCOLA main building, erected in 1974, and an office extension of traditional build, constructed in 2001. These buildings are considered to be in good condition for their age and type.

          TEMPORARY BUILDINGS

          There are no temporary buildings on site and none will be required for this scheme.SITUATION ON SITE AND ENVIRONMENTAL IMPACT

          The two new extensions will adjoin the existing main school building, the new nursery will extend from the northeast corner and the new music room from the southeast corner of the building. The buildings are designed to complement the existing school building, with roofs at the same level as the adjoining existing roofs.

          TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

          The music room and nursery are timber structures with cladding and fenestration to complement the existing school building. Both of the rectangular spaces have a main glazed aspect with the other three sides being mainly solid. The east and west walls are perforated by a sequence of small glazed openings which are intended to cast coloured light into the rooms.

          The structural system to be employed will consist of a timber frame with glulam beams and timber posts, all of which become external on the main aspects. The cladding is natural cedar board featuring double glazed coloured windows. The glazing and external doors are timber framed and double glazed, except for the music room external door which will receive the same cladding as the walls. The music room will receive an additional brise-soleil to control the solar gain on the south-facing aspect.

          FACILITIES FOR THE DISABLED

          There is level access throughout the Infant School and this theme will be continued in the nursery and music extensions. A reconfiguration of the toilet spaces adjoining both extensions will provide an accessible wc in both areas. In addition, two accessible toilets are presently provided in the main classroom areas.

          HEATING AND VENTILATION SYSTEMS

          New heating plant will be required to serve the new extensions. The present boiler room has insufficient space to accommodate further plant and space within the adjacent store is proposed for the new boiler and associated equipment. The existing heating system will be extended to serve the new extensions.

          SPRINKLER SYSTEM

          This is not a stand-alone building on a green field site and, in addition, an assessment concludes it to be a very low fire risk category building and therefore a sprinkler system will not be installed.

          ENERGY EFFICIENCY OF BUILDING

          The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

          ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

          This scheme has been designed to provide the nursery and music accommodation required by the school and has been agreed by the Headteacher and Governors of the school as being the most appropriate design solution.

          CAR PARKING

          There will be no additional provision of car parking spaces as part of this scheme.

          CONSULTATIONS

          The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Environment Department, Chief Fire Officer, local County Councillor.

      5. THE BUILDING DEVELOPMENT

          The proposed scheme will provide a purpose built nursery and a music room which will provide specialist accommodation for the delivery of that part of the national curriculum

      6. BUILDING MANAGEMENT

          CLEANING

          Existing arrangements will apply.

          CATERING

          Existing arrangements will apply.

      7. FURNITURE AND EQUIPMENT

          From the block vote in the Education Committee's Capital Programme.

      8. STAFFING

          Staffing requirements will not change as a result of this scheme.

      9. FEES

          Architectural Services } Format Milton

          Quantity Surveying } John Watson & Carter

          Electrical and Mechanical Engineering } EDP

          Structural Engineering } R J Watkinson