Archived decisions
Hampshire County Council New Forest Transportation Strategy Members' Panel 28 October 2003 Draft Transport Capital Programme 2004/05 and 2005/06 for Consultation Report of the Director of Environment |
Item 6 |
Contact: Jim Soutar, ext 6049 email: [email protected]
1. Summary
1.1 On 24 June 2003 the Executive Member for Environment considered a report on the indicative programmes for the Integrated Transport Capital Programme for 2004/05 and 2005/06. He requested that reports be presented to both the Environment Policy Review Committee, which took place on 3 September 2003, and the ten Area Transportation Strategy Panels to allow Members to consider priorities for inclusion in the Integrated Transport programmes from 2004/05.
1.2 Once the Department for Transport's (DfT) settlement letter is received in December 2003, which will include the funding available for 2004/05, the priorities identified by the Committee and the Panels will be used to finalise a firm 2004/05 programme and provisional programmes for 2005/06 and beyond. These will be submitted to the Executive Member for Environment in January 2004.
2. Background
2.1 The County Council's transport schemes are primarily funded by Government, either through specific grant and credit approvals, (for schemes costing over £5 million), or through the general allocation of credit approvals in the Local Transport Settlement, (for schemes costing less than £5 million). Additional funding is also available for specific schemes from external bodies, primarily contributions associated with major new development. These schemes are included in the capital programme when it is anticipated that the external funding (EF) will be available and a scheme is sufficiently developed for implementation. In some cases schemes may comprise both EF and Government funding.
2.2 The Annual Progress Report (APR) on the Local Transport Plan (LTP), which included an ongoing Transport Capital Programme, was submitted to the DfT on 31 July 2003. Although the County Council is exempt from the APR and LTP processes because of its `excellence' status, it was submitted so that the DfT can assess performance and award resources on the basis of that assessment.
2.3 At present the County Council has indicative allocations only on the likely funding available in 2004/05 and 2005/06. These suggest that it is reasonable, for planning purposes, to prepare new start programmes at a level of £12 million for 2004/05, (for LTP funding), and £13 million in 2005/06. The period beyond 2005/06 falls in the next five year LTP period, with funding less certain.
2.4 Thus any comments made by the Environment Policy Review Committee or the Area Transportation Strategy Panels which would require increased levels of funding, whether for additional or advancement of schemes or programmes, would have to be balanced by appropriate adjustments to the remainder of the programme unless additional funding were to be found.
2.5 The Proposed Capital Programme for 2003/04 to 2006/07 and the Revised Integrated Transport Programme for 2002/03 was reported to the Environment Policy Review Committee on 22 January 2003 and the Executive Member for Environment on 24 January 2003. The Executive Member requested that all LTP funded schemes not included in either the 2002/03 or 2003/04 Capital Programmes be reassessed for inclusion in future programmes.
2.6 This report on the draft Capital Programme 2004/05 and 2005/06 was presented to the Environment Policy Review Committee on 3 September 2003. The Committee expressed the view that increased support should be given to Safer Routes to School schemes and the promotion of School Travel Plans. It should be noted therefore that if there is an increase in budget allocation to the Safer Routes to school programme this would affect the budget allocation for the area strategies. These views, together with those of the Panels, will be considered further once the funding available for 2004/05 has been announced in the December 2003 settlement letter.
3. Five Year Local Transport Plan Programme 2001/02 to 2005/06
3.1 Summaries of expenditure for the whole of the five year LTP programme are shown in Appendices 1 and 2. Those for 2001/02 and 2002/03 are actual figures and those for 2003/04 to 2005/06 are forecasts based upon programmes currently approved by the Executive Member for Environment. Appendix 1 shows expenditure for the area strategies and county-wide programmes, and Appendix 2 shows investment in terms of specific policy areas, such as supporting buses, cycling, etc. Since some schemes are not completed within the initial programme year, the figures are not comparable with those shown in Appendices 4 and 5, which show start values.
4. Scheme Assessment Process
4.1 The scheme assessment requested by the Executive Member has been carried out by officers to take into account a variety of factors to fulfil DfT and County Council objectives. There is a degree of synergy between
these and the manner in which they have been collated under the five headings of Environment, Safety, Economy, Accessibility and Integration is shown in Appendix 3.
4.2 For the purpose of the assessment process, Accessibility was sub-divided into (a) social inclusion and (b) access to transport, and Integration was sub-divided into (a) public transport and (b) walking and cycling. An additional objective related to making the best use of the transport network. Thus under the general heading of Objectives there are eight headings, each of which has been given points between 1 and 5 for individual schemes.
4.3 Other considerations, which comprise value for money, deliverability/ engagement, local priority and contribution to modal shift have been assessed in a similar manner. With a total of 12 factors to be considered, each scheme therefore has a theoretical maximum score of 60.
4.4 No weighting has been applied to the various objectives. The results should not be taken as a definitive prioritisation method as factors such as feasibility, relative cost and issues, etc are all relevant to final prioritisation.
4.5 The points totals for individual schemes have been included in the appendices showing the draft Capital Programmes for the New Forest Transport Strategy (NFTS) and Coastal Towns Transport Strategy (CTTS) areas. The positions of schemes within LTP area programme are also shown. However, inevitably there are some apparent anomalies relating to points scored compared with a particular scheme's position in the programmes, and consequently appropriate notes have been included in the appendices.
5. Draft Programme for 2004/05 and 2005/06
5.1 A draft programme for 2004/05, 2005/06 and beyond for the NFTS area is shown in Appendix 4 and for the CTTS area in Appendix 5. These programmes have been drawn up almost entirely from schemes previously approved by the Panel. The most prominent exceptions are proposals for contributions towards Decriminalised Parking Enforcement, which are considered a high priority by the relevant District Councils.
5.2 The Appendices also show schemes which, although rated, have not been included in either the draft 2004/05 or 2005/06 programmes. It is suggested that the Panel considers its top (typically three) priorities for inclusion in a pool of schemes for early development for future years' programmes.
5.3 The A3 bus priority scheme has been submitted as a bid for funding as a major scheme. A decision on that bid was expected in 2002, however, at the time of writing, no decision had been made by Government. If the major scheme bid is successful then it will not be necessary to consider stopping the project or making financial provisions in the Capital
Programme for it to continue. If, however, the bid is only partially successful (ie only part of the 2003/04 and future costs are funded) then the impact to the project on the 2003/04 and future years' programmes will have to be reassessed. The 2003/04 programme was reviewed by the Executive Member for Environment on 16 September 2003.
5.4 In addition to the ten Area Transportation Strategy Programmes, there are county-wide programmes concerned with particular policy areas, eg pedestrian crossings and safer routes to school. Although they have not been rated as described in section 4, the provisional budgets for 2004/05 and 2005/06 have been included as Appendix 6 for completeness.
5.5 The draft Pedestrian Crossings Programme for 2004/05 was approved by the Executive Member for Environment on 24 June 2003, and this has been included in the appendices for information.
5.6 The provisional Safer Routes to School Programme was also approved by the Executive Member for Environment on 24 June 2003. This covers both 2003/04 and 2004/05, and each scheme will be progressed once a School Travel Plan has been approved by the County Council. Schools on this provisional list have been included in the appendices for information.
Recommendation
That the Executive Member for Environment be advised of this Panel's views, with formal responses to be received by the County Council no later than Friday 14 November 2003.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and have been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None. |
8231/JS
APPENDIX 1
Local Transport Plan Programme 2001/02 to 2005/06
Actual and Planned Expenditure - Area Transportation Strategies
Area Strategy |
2001/02 |
2002/03 |
2003/04 |
2004/05 |
2005/06 |
2001-2006 | ||||||||||||
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total | |
ATS |
395 |
14 |
409 |
416 |
203 |
619 |
530 |
517 |
1,047 |
478 |
60 |
538 |
230 |
200 |
430 |
2,049 |
994 |
3,043 |
BEST |
551 |
314 |
865 |
1,076 |
610 |
1,686 |
385 |
3,476 |
3,861 |
1,060 |
2,340 |
3,400 |
1,700 |
1,930 |
3,630 |
4,772 |
8,670 |
13,442 |
CHARTS |
501 |
49 |
550 |
773 |
84 |
857 |
497 |
202 |
699 |
542 |
550 |
1,092 |
360 |
64 |
424 |
2,673 |
949 |
3,622 |
CTTS |
205 |
0 |
205 |
176 |
0 |
176 |
144 |
63 |
207 |
377 |
5 |
382 |
340 |
0 |
340 |
1,242 |
68 |
1,310 |
NEHTS |
677 |
468 |
1,145 |
1,481 |
380 |
1,861 |
838 |
1,009 |
1,847 |
526 |
341 |
867 |
758 |
1,210 |
1,968 |
4,280 |
3,408 |
7,688 |
NFTS |
370 |
136 |
506 |
385 |
36 |
421 |
420 |
25 |
445 |
1,610 |
0 |
1,610 |
279 |
0 |
279 |
3,064 |
197 |
3,261 |
SEHTS |
333 |
1,115 |
1,448 |
1,907 |
803 |
2,710 |
1,934 |
1,150 |
3,084 |
1,938 |
2,053 |
3,991 |
2,066 |
1,702 |
3,768 |
8,178 |
6,823 |
15,001 |
SWHTS |
774 |
625 |
1,399 |
1,553 |
632 |
2,185 |
2,886 |
3,324 |
6,210 |
1,549 |
1,080 |
2,629 |
1,675 |
718 |
2,393 |
8,437 |
6,379 |
14,816 |
WHTS |
17 |
3 |
20 |
78 |
0 |
78 |
40 |
0 |
40 |
140 |
0 |
140 |
120 |
0 |
120 |
395 |
3 |
398 |
WMAP |
523 |
7 |
530 |
1,774 |
397 |
2,171 |
345 |
1,500 |
1,845 |
185 |
330 |
515 |
210 |
0 |
210 |
3,037 |
2,234 |
5,271 |
A3 Bus Priority |
630 |
0 |
630 |
4,587 |
0 |
4,587 |
3,960 |
0 |
3,960 |
2,200 |
0 |
2,200 |
1,100 |
0 |
1,100 |
12,477 |
0 |
12,477 |
Casualty Reduction |
1,667 |
0 |
1,667 |
1,846 |
0 |
1,846 |
1,809 |
0 |
1,809 |
1,382 |
0 |
1,382 |
1,600 |
0 |
1,600 |
8,304 |
0 |
8,304 |
County-wide/ Others* |
1,288 |
56 |
1,344 |
3,448 |
57 |
3,505 |
2,999 |
0 |
2,999 |
3,133 |
0 |
3,133 |
3,000 |
0 |
3,000 |
13,868 |
113 |
13,981 |
TOTAL |
7,931 |
2,787 |
10,718 |
19,500 |
3,202 |
22,702 |
16,787 |
11,266 |
28,053 |
15,120 |
6,759 |
21,879 |
13,438 |
5,824 |
19,262 |
72,776 |
29,838 |
102,614 |
Expenditure - £'000
* Includes Safer Routes to School (SRTS) Programme. Full investment in schools (SRTS and other local schemes) is shown in Appendix 2.
APPENDIX 2
Local Transport Plan Programme 2001/02 to 2005/06
Actual and Planned Expenditure - Specific Policy Areas
Scheme Type |
2001/02 |
2002/03 |
2003/04 |
2004/05 |
2005/06 |
2001-2006 | ||||||||||||
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total |
LTP |
EF |
Total | |
Bus |
1.4 |
0 |
1.4 |
6.5 |
0.6 |
7.1 |
5.8 |
4.2 |
10.0 |
4.5 |
1.7 |
6.2 |
3.2 |
0.1 |
3.3 |
21.4 |
6.6 |
28.0 |
Safety |
1.8 |
0 |
1.8 |
2.0 |
0.1 |
2.1 |
1.8 |
0 |
1.8 |
1.4 |
0 |
1.4 |
1.6 |
0 |
1.6 |
8.6 |
0.1 |
8.7 |
Cycles |
0.8 |
0.6 |
1.4 |
1.8 |
0.6 |
2.4 |
1.0 |
1.4 |
2.3 |
1.2 |
1.3 |
2.5 |
1.7 |
0.9 |
2.6 |
6.5 |
4.8 |
11.3 |
Highway Improvements |
0.3 |
0.9 |
1.2 |
1.3 |
0.5 |
1.9 |
0.9 |
2.1 |
3.0 |
2.1 |
2.2 |
4.3 |
2.2 |
2.4 |
4.6 |
6.8 |
8.1 |
14.9 |
Pedestrians |
0.8 |
0.1 |
0.9 |
1.6 |
0.1 |
1.7 |
0.8 |
0.1 |
1.0 |
0.8 |
0.2 |
1.0 |
0.7 |
0 |
0.7 |
4.8 |
0.5 |
5.3 |
Schools |
0.7 |
0.1 |
0.8 |
0.7 |
0.1 |
0.8 |
0.6 |
0.3 |
1.0 |
0.9 |
0.3 |
1.1 |
0.8 |
0.2 |
1.0 |
3.7 |
1.0 |
4.7 |
Integration |
0.3 |
0.1 |
0.4 |
1.5 |
0 |
1.5 |
2.1 |
1.2 |
3.3 |
0.3 |
0 |
0.3 |
0.5 |
0 |
0.5 |
4.6 |
1.4 |
6.0 |
Traffic Management |
1.4 |
1.0 |
2.4 |
3.7 |
1.1 |
4.8 |
3.3 |
1.9 |
5.2 |
3.2 |
1.1 |
4.4 |
2.0 |
2.2 |
4.2 |
13.6 |
7.3 |
20.9 |
Others |
0.4 |
0 |
0.4 |
0.4 |
0 |
0.4 |
0.5 |
0.1 |
0.6 |
0.7 |
0.1 |
0.8 |
0.7 |
0 |
0.7 |
2.7 |
0.1 |
2.8 |
TOTAL |
7.9 |
2.8 |
10.7 |
19.5 |
3.2 |
22.7 |
16.8 |
11.3 |
28.0 |
15.1 |
6.8 |
21.9 |
13.4 |
5.8 |
19.3 |
72.8 |
29.9 |
102.6 |
Expenditure - £ million to nearest £100,000
APPENDIX 3
Scheme Assessment Process - Objectives
Paragraph 4.1 refers
Government Transport White Paper Objective |
County Council LTP Objectives |
County Council Corporate Aims | |
Environment |
noise local air quality greenhouse gases landscape townscape heritage of local resources biodiversity water environment physical fitness journey ambience |
make best use of transport networks maintain transport networks partnership with the community |
stewardship of the environment |
Safety |
accidents security |
promote safety |
building strong and safe communities |
Economy |
transport economic efficiency reliability wider economic impacts |
widen travel choice make best use of transport networks maintain transport networks |
achieving economic prosperity improving services |
Accessibility |
option values severance access to transport system |
widen travel choice make use of transport networks partnership with the community |
maximising life opportunities improving services |
Integration |
transport interchange land use policy other Government policies |
widen travel choice make best use of transport networks partnership with the community |
building strong and safe communities developing councillors and staff |
APPENDIX 4
New Forest Transport Strategy - NFTS
Draft Capital Programme
Scheme |
2004/05 £'000 |
2005/06 £'000 |
Prep Pool |
Assessment Rating |
Notes | |||
LTP |
EF |
LTP |
EF |
Pts |
Psn | |||
Lyndhurst - Ashurst Cycles |
400 |
41 |
1 |
|||||
New Forest Decriminalised Parking |
120 |
31 |
= 6 |
1 | ||||
Ringwood Pedestrian and Cycles |
150 |
39 |
2 |
|||||
Demand Management |
100 |
38 |
3 |
|||||
New Forest Cycle Plan |
100 |
31 |
= 6 |
|||||
Car Free Tourism |
25 |
30 |
8 |
|||||
A36 West Wellow Traffic Management |
x |
37 |
4 |
2 | ||||
Lyndhurst Village Cycles |
x |
35 |
5 |
|||||
Village Initiatives |
x |
28 |
9 |
3 | ||||
Total |
520 |
375 |
||||||
Notes:
1. District Council priority
2. Awaiting de-trunking
3. Similar to existing programmes in BEST, CHARTS and NEHTS
Safer Routes to Schools (NFTS and CTTS) - 2003/04 and 2004/05 Provisional Programme
NB: subject to the preparation of a School Travel Plan at Level 3, to be approved by the County Council no later than 31 December 2003
School |
District |
STP Level |
Bransgore Primary |
New Forest |
1 |
Copythorne CE Primary |
New Forest |
1 |
Houndsdown School |
New Forest |
3 |
Lydynch Infants |
New Forest |
3 |
Netley Marsh CE Infants |
New Forest |
3 |
Orchard Infant and Juniors, Totton |
New Forest |
1 |
Poulner Infants and Juniors, Ringwood |
New Forest |
1 |
Ringwood Schools |
New Forest |
1 |
St Luke's CE, Sway |
New Forest |
3 |
Tiptoe Primary |
New Forest |
being developed |
APPENDIX 5
Coastal Towns Transportation Strategy - CTTS
Draft Capital Programme
Scheme |
2004/05 £'000 |
2005/06 £'000 |
Prep Pool |
Assessment Rating | |||
LTP |
EF |
LTP |
EF |
Pts |
Psn | ||
Station Road j/w Manor Road, New Milton Puffin Crossing |
65 |
15 |
42 |
1 | |||
A337 Milford Road (Pennington Cross-Stanford Hill) and Belmore Road Cycle Route, Lymington |
125 |
40 |
2 | ||||
North Street, Pennington |
50 |
36 |
4 | ||||
Lymington Southern Access - Rookes Lane and Ridgeway Lane |
150 |
35 |
5 | ||||
Pennington to Town Centre (Priestlands Road, Priestlands Lane, Highfield) Cycle Route |
150 |
37 |
3 | ||||
Whitefield Road/Station Road, New Milton |
175 |
34 |
6 | ||||
Bus Infrastructure and Information |
100 |
32 |
8 | ||||
Old Milton - North Milton Cycles |
x |
33 |
7 | ||||
High Street, Lymington |
x |
21 |
9 | ||||
Total |
390 |
15 |
425 |
||||
Pedestrian Crossings Programme 2004/05
A337 Stanford Hill, Lymington - Toucan £55,000 LTP
APPENDIX 6
Draft County-wide/Other Transport Capital Programme
Programme/Scheme |
2004/05 |
2005/06 | ||
LTP £'000 |
EF £'000 |
LTP £'000 |
EF £'000 | |
Low Cost Safety Programme |
1,000 |
1,000 |
||
Future Safety Schemes |
400 |
600 |
||
Pedestrian Crossings |
330 |
362 |
||
MIRACLES |
100 |
|||
Central Intelligent Transport Systems |
200 |
200 |
||
Community Safety Initiative (lighting) |
60 |
60 |
||
Community Transport Schemes |
250 |
250 |
||
Rural Partnership Schemes |
200 |
200 |
||
Minor Works |
250 |
250 |
||
Passenger Transport Information |
130 |
130 |
||
Safer Routes to School* |
700 |
800 |
||
Railway Stations/Interchanges |
100 |
100 |
||
Air Quality and Noise Monitoring |
50 |
50 |
||
Home Zones/Community Strategies |
100 |
100 |
||
LTP Monitoring/Initiatives |
200 |
200 |
||
Hythe Pier |
90 |
90 |
||
Recreational Cycling |
100 |
100 |
||
Total |
4,260 |
4,492 |
||
*NB: It is proposed that additional money will be put into the Safer Routes to School scheme, with corresponding reductions made elsewhere in the Programme.