Archived decisions

Hampshire County Council

Item

Executive Member - Policy and Resources

13 November 2003

Brune Park Community School

Report by the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858

1

Summary

1.1

The following decision is sought:

1.2

That approval be given to the project appraisal for Brune Park Community School at Gosport at an estimated cost of £1,101,000, excluding fees.

2

Reason

2.1

To provide Dance Studio and dining room extensions which will increase school capacity to 1,750 places in line with the forecast number on roll.

3

Other options considered and rejected

3.1

The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or a member or officer consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

.........................

Councillor K Thornber