    1. Summary

    1.1 This report outlines progress with regard to the 2003/04 Highway Maintenance and Minor Capital Works programmes and gives an update on the 2003/04 Highway Maintenance budget.

    2. Background

    2.1 As previously reported, the Highway Maintenance programme is funded from both revenue and capital allocations.

    2.2 The revenue maintenance programme funds minor works such as, pothole repairs and routine drainage work, including gully cleaning, signs and road markings, environmental maintenance of grass verges, trees and shrubs, weed control and highway emergencies. Minor bridge works and winter maintenance are also funded from revenue. Budget allocations are set at a level that ensures the safety and serviceability of the highway network.

    2.3 The capital maintenance programme funds planned maintenance, including special maintenance, resurfacing and surface dressing, and also provides for essential repairs to the structure of the highway.

    3. Highway Maintenance Budget and Programme 2003/04

    3.1 The Highway Maintenance budget for 2003/04, approved by the Executive Member for Environment, is £46,889,000. This sum comprises £19,615,000 revenue funding and £27,274,000 funding from the capital programme provision.

        Revenue Maintenance Budget and Programme

    3.2 The total revised allocation for Gosport for 2003/04 is £294,000, excluding those elements included in paragraph 3.4. Progress throughout the year has been in line with the spend profile and it is expected that the programme will be completed within time and budget constraints. A budget monitoring statement is attached as Appendix 1.

    3.3 The revenue maintenance programme funds three main areas of highway maintenance:

          (i) reactive minor repair works on the road, cycleway and footway network;

          (ii) maintenance of current traffic signs and road markings and minor traffic management improvements; and

          (iii) the environmental aspects of highway maintenance, including grass cutting, weed treatment, and tree and shrub maintenance.

    3.4 Additional revenue budgets are held centrally for the performance elements of the County Council's term maintenance contract. The performance based work contained in the contract includes:

        (i) gully emptying;

        (ii) visibility splay grass cutting;

        (iii) winter maintenance;

        (iv) routine bridge maintenance; and

        (v) `A' road routine maintenance.

    3.5 It is noted that this year there have been more footway damage incidents due to tree roots; Jamaica Place, High Street Gosport and Bury Road, in particular there is also still significant damage caused by vehicle overrun on footways and verges.

        Capital Maintenance Budget and Programme

    3.6 The total allocation for Gosport for 2003/04 is £831,000, which includes £63,000 from the £3.5 million county-wide additional funding previously reported. The funding allocation for the capital maintenance `planned works' programme is based on the proven HAMP rating system and reflects the agreed intervention levels. The HAMP rating intervention level directs funding to those maintenance schemes displaying a higher maintenance need. Planned structural maintenance repairs undertaken through the capital maintenance programme include surface dressing, special maintenance and resurfacing schemes.

    3.7 This year's schemes are progressing well with the expectation that the planned maintenance programme will be delivered within time and budget constraints. Progress on this year's schemes is shown in Appendix 2.

    3.8 The capital maintenance programme also supports the centrally controlled areas of work, including major maintenance schemes and bridge maintenance.

    3.9 Surface dressing is an extremely cost-effective way of prolonging the life of the carriageway, sealing cracks and restoring skid resistance. The total budget county-wide of £3,297,000 is managed centrally and for 2003/04 supported a HAMP intervention level of 50 on the principal road network. High performance surface dressing on the non-principal roads has a HAMP intervention level of 60 and the intervention level is 70 for the urban and minor roads programmes. Footway surface dressing sites are usually selected on the recommendation of the engineers who carry out highway inspections and areas that have a poor skid resistance, are heavily patched or affected by utility trenches are the preferred choices for treatment. All sites on this year's programme for Gosport have now been successfully treated. This year's schemes are listed in Appendix 2.

    4. Minor Capital Works

    4.1 The Minor Capital Works programme (also known as the Under £10,000 programme) is funded from the capital allocation based on the Local Transport Plan submission to the Department for Transport.

    4.2 A sum of £10,000 was allocated for Gosport in 2003/04. In addition, developer funding was allocated which enabled cycleway lighting enhancements to be carried out between Whitworth Road and Holbrook. These works are referred to in the Street Lighting report and are substantially complete.

    5. Other Works

    5.1 Hampshire Highways Gosport has carried out design and supervision on other schemes during the current financial year funded by developers, Groundworks Trust and for the Regeneration of Older Urban Areas programme. These are set out on Appendix 3.

    Recommendation

    That this report be noted.

    Section 100 D - Local Government Act 1972 - background papers

    The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

    NB the list excludes:

    1.

    Published works.

    2.

    Documents which disclose exempt or confidential information as defined in the Act.

    TITLE

    LOCATION

    None.

    8388/AP

    GOSPORT

    APPENDIX 1

    2003/2004

    Percentage

    Committed

    (Sep)

    Original

    Allocation

    Revised

    Allocation

    Revenue Budget 2002/03

    Routine Maintenance (carriageway, footway repairs)

    126,000

    112,000

    30

    Gully Cleansing

    4,000

    4,000

    50

    Aids to Movement (signs and road markings)

    40,000

    40,000

    50

    Traffic Management TROs (GBC)

    7,000

    7,000

    30

    Environmental (grass, trees, shrubs) (GBC)

    81,000

    81,000

    50

    Weed Control (GBC)

    26,000

    26,000

    50

    Hazard Clearance

    10,000

    24,000

    50

    Total

    294,000

    294,000

    43

    Capital Budget 2002/03

    Principal Roads

    Principal Roads Routine Structural Repairs

    6,000

    6,000

    50

    Principal Roads Special Maintenance

    47,000

    47,000

    40

    Principal Roads Resurfacing

    Nil

    Nil

    0

    Total

    53,000

    53,000

    41

    Capital Budget 2002/03

    Non-Principal Roads

    Non-Principal Roads Routine Structural Repairs

    229,000

    229,000

    70

    Non-Principal Roads Special Maintenance

    237,000

    237,000

    36

    Additional footway works

    63,000

    63,000

    0

    Non-Principal Roads Resurfacing

    185,000

    185,000

    75

    Non-Principal Roads Tactile Paving Crossing Points

    14,000

    14,000

    80

    Total

    728,000

    728,000

    55

    Total Maintenance Budget Allocation Gosport

    1,075,000

    1,075,000

    51

    APPENDIX 2

    SPECIAL MAINTENANCE PROGRAMME 2003-2004

    Gosport

     

    Estimate

    Start

    Finish

    Footway/Kerbing -Principal Roads

     

         

    Forton Road

    South side Bedford Street to Anns Hill Road

    6,400

    Complete

     

    Fareham Road

    West side - bus stop adjacent Fraser Road

    8,600

    Complete

     

    Fareham Road

    East side - Hoeford

    3,300

    Complete

     

    Drainage - Principal Roads

           

    Fareham Road

    Near Holbrook

    14,000

    Nov

    Dec

    Fareham Road

    Near Brockhurst roundabout

    15,000

    Nov

    Dec

    Footway/Kerbing

           

    Military Road

    East side near footbridge

    2,800

    Complete

     

    Bury Road

    Near Bury Crescent

    6,500

    Complete

     

    Wootton Road

    East side 14 - 72, west side 57 - 65

    67,000

    Nov

    Jan

    Sherwood Road

    East side

    22,000

    Complete

     

    Lyndhurst Road

    East side

    18,000

    Complete

     

    Peel Road

    Both sides - Grove Avenue to Strathmore Road

    21,500

    Ongoing

     

    Tichborne Way

    Both sides of Tichborne Arch

    26,000

    Complete

     

    Marine Parade East

    North side Woburn Court to Queens Road

    5,000

    Nov

    Nov

    Long Drive

    49 - 100

    27,000

    Complete

     

    Additional Footway

           

    Portsmouth Road

    North side 56 - 112, 184 - 190

    63,000

    Nov

    Dec

       

    Estimate

    Start

    Finish

    Tactile Paving

           

    Various locations

     

    14,000

    Apr

    March

    Carriageway Resurfacing

           

    Walton Road

    Entire Road

    42,000

    Complete

     

    St Andrews Road

    Rear access 2 - 22

    9,000

    Complete

     

    Kingston Road

    Rear access 31 to Middlecroft Road

    22,000

    Nov

    Nov

    Elson Road

    Brockhurst roundabout to 21a

    38,000

    Complete

     

    Rowner Road

    Rowner Lane east - 69 Charden Road

    93,000

    Complete

     

    Group 2 Carriageway Surface Dressing

           

    Mumby Road

    Harbour Road to Ferry

     

    Complete

     

    Group 3 Carriageway Surface Dressing

           

    Eastbourne Avenue

    Whole length

     

    Complete

     

    Mill Pond Road

    Whole length

     

    Complete

     

    Fieldmore Road

    Whole length

     

    Complete

     

    Brewers Lane

    Whole length

     

    Complete

     

    Dayshes Close

    Whole length

     

    Complete

     

    St Lukes Road

    Whole length

     

    Complete

     

    Stoners Close

    Whole length

     

    Complete

     

    Coulmere Road

    Whole length

     

    Complete

     

    Pettycott Crescent

    Whole length

     

    Complete

     

    Maple Close

    Whole length

     

    Complete

     

    Northcott Close

    Whole length

     

    Complete

     

    Tribe Road

    Whole length

     

    Complete

     

    Skipper Way

    Whole length

     

    Complete

     

    Harcourt Road

    Whole length

     

    Complete

     

    Green Lane

    Whole length

     

    Complete

     

    Lyndhurst Road

    Whole length

     

    Complete

     

    Cheyne Way

    Whole length

     

    Complete

     

    Rowan Close

    Whole length

     

    Complete

     

    Cherry Close

    Whole length

     

    Complete

     

    South Place

    Whole length

     

    Complete

     

    Milvil Road

    Whole length

     

    Complete

     

    Virginia Park Road

    Whole length

     

    Complete

     

    Richmond Road

    Whole length

     

    Complete

     

    Shackleton Road

    Whole length

     

    Complete

     

    Clanwilliam Road

    Whole length

     

    Complete

     

    Tedder Road

    Whole length

     

    Complete

     

    Carlyle Road

    Whole length

     

    Complete

     

    Rowner Close

    Whole length

     

    Complete

     

    Ham Lane

    Whole length

     

    Complete

     

    Grange Close

    Whole length

     

    Complete

     

    Gregson Avenue

    Whole length

     

    Complete

     

    Meadow Walk

    Whole length

     

    Complete

     

    Richmond Road Gosport

    Whole length

     

    Complete

     

    St Thomas's Road

    Whole length

     

    Complete

     

    Fisgard Road

    Whole length

     

    Complete

     

    Shaftesbury Road

    Whole length

     

    Complete

     

    Selsey Avenue

    Whole length

     

    Complete

     

    Camp Road

    Whole length

     

    Complete

     

    Footway Surface Dressing

           

    Hastings Avenue

    Whole length

     

    Complete

     

    School Road

    Whole length

     

    Complete

     

    Selsey Avenue

    Whole length

     

    Complete

     

    Worthing Avenue

    Whole length

     

    Complete

     

    Bournemouth Avenue

    Whole length

     

    Complete

     

    Sedgeley Road

    Whole length

     

    Complete

     

    Elson Lane

    Whole length

     

    Complete

     

    Exmouth Road

    Whole length

     

    Complete

     

    Richard Grove

    Whole length

     

    Complete

     

    Wandesford Place

    Whole length

     

    Complete

     

    Ham Lane

    Whole length

     

    Complete

     

    Stanley Place

    Whole length

     

    Complete

     

    Goodwood Close

    Whole length

     

    Complete

     

    Goodwood Road

    Whole length

     

    Complete

     

    Grove Road

    Whole length

     

    Complete

     

    Palmyra Road

    Whole length

     

    Complete

     

    Dunkeld Road

    Whole length

     

    Complete

     

    Grange Crescent

    Whole length

     

    Complete

     

    Northcroft Road

    Whole length

     

    Complete

     

    Clyde Road

    Whole length

     

    Complete

     

    Virginia Park Road

    Whole length

     

    Complete

     

    APPENDIX 3

Developer Funded Road Improvements

Frater Gate traffic signals and junction improvements - supervision (S278)

Gunners Way/Heritage Way Industrial area junction - supervision (S278)

Whites Place Improvements on Frater Road and sewer works for £35,000

new surgery

Ferrol Road/Forton Road/Parham Road development - footway works £8,000

Regeneration of Older Urban Areas

Stoke Road - Peel Road to Elmhurst Road - design and supervision £100,000

Groundworks Trust

Crossways - Mill Pond Road to Forton Road Improvements £30,000

and landscape features