4 December 2003 Whitewater Primary School, Hook Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 email: [email protected]
3. |
Funding and Timing | |
3.1 |
An allocation of £351,000, excluding fees, has been made from Education's 2004/05 Capital Programme NDS Modernisation fund, with a School contribution of £35,000, additional transfers of £2,000, a local business contribution of £21,000, excluding fees and a contribution from the Ecclesiastical Trust of £2,000. | |
3.2 |
Subject to the necessary approvals it is anticipated that tenders will be invited during February 2004, work will commence on site during April 2004 and be completed during November 2004. | |
Recommendation |
||
That the Executive Member for Education approves the design project appraisal for Whitewater Primary School, Hook. | ||
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
TITLE LOCATION
Architect's plans PMIS file
Building Profile Reports TMH