Archived decisions

Hampshire County Council

Item 3(ii)

Executive Member - Policy and Resources

11 December 2003

Frogmore Community College, Yateley

Report by the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858 [email protected]

1

Summary

1.1

The following decision is sought:

1.2

That the Executive Member for Policy and Resources approves the design project appraisal for the refurbishment of existing internal areas and a new extension to provide two seminar spaces to accommodate class sizes of approximately 16 students in each at Frogmore Community College, at an estimated cost of up to £648,000, excluding fees.

2

Reason

2.1

To provide two specialist CACHE Diploma in Childcare seminar spaces and two Sixth Form Seminar rooms plus associated refurbishment works.

3

Other options considered and rejected

3.1

The need of the school and local community for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or a member or officer consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

.........................

Councillor T K Thornber