Summary

1.1

The following decision is sought:

1.2

That the Executive Member for Education advises the Executive Member for Policy and Resources that the project appraisal for the construction of a Youth Building and refurbishment of the Newbold Building at Hamble Community School at an estimated cost of up to £752,000, excluding fees, be approved.

2

Reason

2.1

To provide a purpose-built Youth Building at Hamble Community Sports College, and to refurbish the Newbold Building to provide CDT and classroom accommodation.

2.2

This decision supports Aims 1 and 5 of the Corporate Strategy by providing a youth facility which will benefit the school and the local community.

3

Other options considered and rejected

3.1

The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or a member or officer consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

.........................

Councillor D Allen