Archived decisions

        HAMPSHIRE COUNTY COUNCIL

      BUILDING DESIGN PROJECT APPRAISAL

        EDUCATION BUILDINGS ADVISORY GROUP

        6 JANUARY 2004

        EXECUTIVE MEMBER - EDUCATION

        22 JANUARY 2004

        BUILDING LAND AND CONTRACTS PANEL

        27 JANUARY 2004

        EXECUTIVE MEMBER - POLICY AND RESOURCES

        19 FEBRUARY 2004

      PROJECT:

      HILTINGBURY INFANT SCHOOL, CHANDLERS FORD

      TWO CLASSROOM EXTENSION AND REMOVAL OF TEMPORARY ACCOMMODATION & RE-CLADDING OF EXISTING BUILDING

      COMMENCEMENT DATE:

      APRIL 2004

      COMPLETION DATE:

      NOVEMBER 2004

      PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME:

      2003/ 04

        RECOMMENDATION:

        That the building design project appraisal for the construction of permanent teaching accommodation and the removal of temporary classrooms along with the external re-cladding of the existing school building at Hiltingbury Infant School, Chandlers Ford be approved.

        1. FINANCE

          Capital Expenditure

      Current Estimate

      £'000

      Capital Programme

      (at Nov '02 prices)

      £'000

      Buildings

      729

      329

      Fees

      95

      49

      Land to be purchased

      _

      _

      TOTAL

      *824

      378

        * The means by which the difference between the Current Estimate and the Capital Programme allocation is to be met is shown in the table below.

        Furniture and Equipment: subject to the County Education Officer's assessment of need with the Headteacher, together with the availability of funding, a furniture and equipment allocation will be made from the block vote in Education's Capital Programme in the appropriate financial year.

      Financial Provision for Total Scheme

      Buildings

      £'000

      Fees

      £'000

      Total

      Cost

      £'000

      1. From Committee's own Resources:

      a) Capital Programme: New Deal for Schools (NDS) Modernisation 03/04

      329

      49

      378

      2. From Other Resources:

      a) Policy and Resources Committee's NDS Condition fund 03/04

      380

      46

      426

      b) School

      20

      0

      20

      TOTAL

      729

      95

      824

Anticipated Devolved Capital allocations £'000

                    2002/03 16

              2003/04 23

              2004/05 26

TOTAL 55

Landlord Funded Work connected with this Scheme

A contribution of £380,000, excluding fees, will come from the Policy and Resources Committee's 2003/04 NDS Condition budget towards the external re-cladding of the existing SCOLA school building.

Value of Land already acquired for this Project

The land forming the site of the development is an integral part of the school campus and is incapable of disposal in isolation. The land was acquired at historic cost and its current value to the County Council is as part of the ground of the establishment.

Building Cost - Net Cost = £1,301 per m2 (excluding abnormals)

- Gross Cost = £1,627 per m2 (excluding abnormals)

Revenue Implications

      (a)

      Employees

      £'000

      (b)

      Other

      £'000

      (a+b)

      Net Current

      Expenditure

      £'000

      (c)

      Capital

      Charges

      £'000

      (a+b+c)

      Total Net

      Expenditure

      £'000

      Revenue

      Implications

      Additional+

      /Reductions

      -

      -

      -

      42

      42

      Unit cost (£)

      (e.g. per place)

      -

      -

      -

      -

      -

      % variation to

      Committee's

      budget

      -

      -

      Number of

      additional

      Staff (fte)

      -

      -

(a) Energy Costs

          It is anticipated that the additional increase in fuel cost for the school will be in the order of £300 per annum of £3.70 per m².

(b) Maintenance Costs

        The detailed design and choice of materials will minimise future maintenance liability.

        2. STATEMENT OF NEED/JUSTIFICATION FOR PROJECT

            The original double temporary classroom was in very poor condition and was scheduled for replacement by using NDS Modernisation funding. However, before it could form part of the Capital Programme, the unit was condemned in April 2002. In order not to disadvantage the school, it was agreed that replacement of the unit should go ahead in a permanent build. Funding was allocated from the NDS Modernisation budget to replace the two classrooms and, at the same time, provide the school with a music/drama space and an accessible wc.

        3. DETAILS OF SITE

            LOCATION

            Hiltingbury Infant School is located at Hiltingbury Road, Chandlers Ford.

            ADJOINING LAND AND BUILDINGS

            Hiltingbury Infant School shares a site with Hiltingbury Junior School. Pine Road borders the site to the south with the residential accommodation of Chandlers Ford beyond. Hiltingbury Road boarders the site to the north with the residential accommodation of Hiltingbury beyond. To the east of the site is a Youth Club and further housing and to the west is a recreation ground.

            AREA INCLUDING COMPARISON WITH LOCAL/NATIONAL STANDARDS

            This is a shared site with the junior school at a total size of 6.78 acres (2.79 ha). The DfES guideline for schools of this size is 6.37 acres (2.47 ha).

            PLANNING POSITION

            A formal detailed Planning Application was submitted to the Environment Department during November 2003.

            SUITABILITY FOR PROJECT

            These proposals will enable the construction of new general teaching classrooms and specialist teaching accommodation (music/drama) along with accessible WC facilities. The scheme will provide sufficient permanent accommodation to allow a double temporary building to be removed from site.

            RESULTS OF TRIAL BORE HOLES

            A site investigation was undertaken earlier in 2003 for a scheme to extend Hiltingbury Junior School, the results of which have been used in the preparation of this report.

            The site consists of 80cm of made ground overlying the natural clayey sands known as Whitecliff Sand Pebble Beds. It is proposed to use conventional spread foundations with ground bearing floor slabs.

            ACCESS

            The main vehicular and pedestrian access to the school is from Hiltingbury Road to the north.

            For the duration of the contract it is proposed that access for light vehicles will be via the Youth Club access road at the north-east corner of the site. This arrangement will enable direct access to the contractor's compound located adjacent to the site of the proposed extension and will minimise disruption at the main school entrance. The main entrance will, however, be required for large deliveries and arrangements will be made with the school to deliver at specific agreed times which cause minimum disruption to the school.

            COMMENTS ON SITE LAYOUT

            The Infant and Junior School share a site, with the Infant School lying to the north-east corner with playground to the front and rear of the building. The main entrance to the site is from the north-west corner with adjacent car parking. The Junior School is located to the west of the site with its playground extending to the east and the school playing fields are located to the south of the site.

            The proposed new extension to the Infant School will be located to the east of the building and will adjoin the existing hall and a classroom.

            MAINS SERVICES POSITION

            The existing mains services are considered to be of a sufficient capacity to be extended and adapted as required to serve the proposed new accommodation.

            MAINTENANCE IMPLICATIONS

            The site will continue to be maintained in accordance with current County Council standards.

            LANDSCAPE PROPOSALS

            Landscaping associated with these works is minimal and comprises perimeter paving to the new building and reinstatement of the area occupied by the temporary classrooms. The playground will be extended to compensate for the loss of play area due to the new extension.

        4. THE PROPOSED BUILDING/RATIONALISATION/CONVERSION

            TYPE OF PROJECT, LAYOUT AND FACILITIES PROVIDED

            The proposed scheme will enable the construction of permanent accommodation and the removal of temporary buildings from site.

            The extension to the east of the existing Infant School will provide the following accommodation:

            - two general teaching classrooms

            - music/drama classroom (with acoustic folding screen to main hall)

            - shared /practical area

            - accessible WC

            Also, as part of this scheme, it is proposed to re-clad the main SCOLA building.

            PLACES PROVIDED

            60 replacement places.

            PRESENT/REDUNDANT BUILDINGS AND FUTURE USE

            The original school building was constructed in 1967 and is of a SCOLA construction. A classroom extension was added in 1996 and a new library was completed in 2002. The existing buildings are considered to be in a good condition.

            TEMPORARY BUILDINGS

            There is currently one double temporary classroom on the school site located to the east of the Infant School, adjacent to the area of the proposed new extension.

            Upon completion of the work the temporary classroom will be removed from site and the area reinstated.

            SITUATION ON SITE AND ENVIRONMENTAL IMPACT

            The extension has been designed and materials chosen to complement the design of the original school building. The new accommodation will be positioned to the rear of the existing building, with minimal visual impact from the entrance of the site or the road. Although there are a number of trees in this area no trees will be lost due to the new development.

            TYPE OF CONSTRUCTION, FINISH AND APPEARANCE

            The proposed new accommodation will be of a traditional brick and block construction with full height aluminium section glazed elevations to the shared/practical area and music/drama room, below a high-performance covered roof. Aluminium framed windows with low energy glazed panels will be provided in the new extension.

            Additional natural light and ventilation will be provided in the new classrooms via north-facing roof lights.

            ACCESSIBLE FACILITIES

            The new accommodation will have level access throughout and an accessible wc will be provided in the new accommodation.

            HEATING AND VENTILATION SYSTEMS

            The existing gas fired boiler serving radiators will be extended and adapted as necessary to serve the new accommodation.

            Ventilation to the classrooms will be by natural means via opening windows with extract ventilation to the new accessible wc.

            SPRINKLER SYSTEM

            The proposal is to provide extensions to the existing schools building and as such the works do not constitute new stand alone buildings on a green field site and, in addition, a risk assessment concludes this to be a very low fire risk category building and therefore a sprinkler system will not be installed.

            ENERGY EFFICIENCY OF BUILDING

            The estimated annual energy consumption for the new building will meet that required by current Building Regulations.

            ALTERNATIVE STANDARDS OF PROVISION CONSIDERED

            These proposals have been agreed by the Headteacher and Governors of the school as being the most appropriate form of development to provide permanent teaching accommodation to enable the removal of temporary classrooms.

            CAR PARKING

            No additional car parking spaces will be required as a result of this scheme.

            CONSULTATIONS

            The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Environment Department, local Councillor.

        5. THE BUILDING DEVELOPMENT

            This scheme has been designed to provide two replacement classrooms to enable temporary classrooms t o be removed, along with the provision of a music/drama room and shared/practical area.

            The existing building will also be enhanced by the external re-clad of the main SCOLA building.

        6. BUILDING MANAGEMENT

            CLEANING

            Existing arrangements will apply.

            CATERING

            Existing arrangements will apply.

        7. FURNITURE AND EQUIPMENT

            From the block vote in Education's Capital Programme.

        8. STAFFING

            No change.

        9. FEES

            Architectural Services } Property, Business and Regulatory Services

            Quantity Surveying } Davis, Langdon & Everest

            Electrical and Mechanical Engineering } Giffords Ltd

            Structural Engineering } WSP Consultants