1. Summary
1.1 This report outlines progress on the Casualty Reduction Programme, Hampshire Safety Camera Partnership and Safer Routes to School.
2. Casualty Reduction Programme
2.1 The 2003/04 low cost/high yield casualty reduction engineering programme consisted of 62 schemes throughout the county with a combined value totalling approximately £1.1 million. Appendix 1 shows the list of schemes featured in that initial programme for the Fareham Borough area, with the current implementation/study position for each scheme. The provisional Low Cost Casualty Reduction Programmes is detailed in Appendix 2.
2.2 For the last quarter of the 2003/04 financial year and following the award of major scheme funding for the A3 bus priority corridor in Havant Borough, the County Council has supplemented the initial casualty reduction engineering programme with an additional £750,000. The total low cost programme value for 2003/04 is approximately £1.75 million out of a total enhanced programme value of around £2.75 million. The remainder of the programme includes significant safety schemes at the B2177/B3354 junction, Fishers Pond (Winchester District), A30 Southwood Corner, and Basingstoke District and Lymington High Street (New Forest District).
2.3 The additional funding for the lower cost/high yield casualty reduction programme enables the County Council to implement early additional schemes at locations with a record of high severity casualties. Some of these sites are being identified through the County Council's Casualty Reduction Partnership investigations with Hampshire Constabulary at locations that have recently experienced high severity collisions. The treatments being proposed are broadly similar to the well established low cost programme and include measures such as improved signing, carriageway markings, retexturing and resurfacing. In addition, the enhanced funding enables early carriageway repair works to be undertaken ahead of an increased surface dressing programme in the 2004/05 financial year for roads with a proportionally high occurrence of loss of control incidents.
3. Hampshire Safety Camera Partnership
3.1 Installation of fixed safety (speed) cameras is progressing and are operational (February 2004) at the following sites:
(i) B3037 Bishopstoke Road, Eastleigh;
(ii) Highlands Road, Fareham;
(iii) A337 Setley, New Forest;
(iv) A35 Totton;
(v) A32 Gosport Road, Fareham; and
(vi) A36 (T), West Wellow (on behalf of the Highways Agency).
3.2 New sites approved as part of the 2003/04 Safety Camera Partnership operational case submission to Government have included:
(i) A3090, Crampmoor (Test Valley Borough);
(ii) Marine Parade, Lee-on-the-Solent (Gosport Borough); and
(ii) A339 (detrunked route) north-east of Wootton St Lawrence (Basingstoke Borough).
3.3 Cameras are currently being installed at these sites and are expected to be operational by the end of 2003/04 financial year. A former proposed fixed camera site on A325 at Holt Pound (East Hampshire) is being replaced with a speed reactive signing scheme. This is due to technical difficulties in finding an acceptable location that would fully accord with the Government's camera conspicuity criteria.
3.4 The 2002/03 Annual Review of the Hampshire Safety Camera Partnership will be made available to Members with the meeting papers.
3.5 For the 2004/05 Operational Case year, approval has been sought from the Department for Transport for the placement of a further fixed safety (speed) camera at Southampton Road, Hythe (New Forest District). Subject to final detailed analysis it is expected that this would be installed during the autumn of 2004.
4. Safer Routes to School Programme
4.1 The current position of identified schemes within Fareham Borough for the 2003/04 Safer Routes to School (SRTS) programme, together with the status of associated School Travel Plans is outlined in Appendix 3. A number of schemes in the county-wide programme were carried forward from the 2002/03 programme following adjustments required to the capital programme to keep within 2002/03 spending limits.
4.2 It was reported to Members during the autumn round of the former Highways Management Advisory Panel meetings, that it is the County Council's intention to require all Safer Routes to School schemes from the 2004/05 financial year to be associated with the development and publication of School Travel Plans by the directly affected schools. This approach will ensure that schools, their pupils, parents and carers will fully benefit from the infrastructure measures installed. These include offering improved levels of child travel safety, opportunities for increased levels of cycling, walking and passenger transport usage. The current position regarding the development of School Travel Plans by schools in Fareham is shown in Appendix 4.
4.3 The full list of schemes comprising the 2004/05 Safer Routes to School programme has at present not been set. As a consequence it will be reported to Members at the autumn Highway and Transport Advisory Panels. Nevertheless, in anticipation of an increasing pace of publication of Travel Plans by Hampshire Schools during the coming year, the county-wide Safer Routes to School programme is being increased from the 2003/04 value of £0.5 - £1.25 million in 2004/05 and £1.5 million in 2005/06.
Recommendation
That this report be noted.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None. |
8559/TC
APPENDIX 3
Safer Routes To School Programme 2003/04
Schemes in Fareham Borough Council Area
School Name and Description of Works |
District and Transport Strategy Area |
School Travel Plan Level |
Estimated Cost of Works |
Progress |
Brookfield Community School |
Fareham Borough Council SEHTS |
2 |
TBC |
Scheme carried forward from 2002/03 South East Hampshire Transport Strategy (SEHTS) programme. Awaiting School Travel Plan before progressing. |
Portchester Community School |
Fareham Borough Council SEHTS |
3 |
TBC |
Scheme to tie in with Home Zone. |
Sarisbury Infant School |
Fareham Borough Council SEHTS |
3 |
TBC |
Scheme being progressed by Fareham Borough Council. |
St Anthony's RC Primary School |
Fareham Borough Council SEHTS |
3 |
£15,000 |
Meeting with Governors/school held in December 2003 - design work in progress. |