Archived decisions

Hampshire County Council

Solent Transport Strategy Panel

8 March 2004

Capital Programme

Report of the Director of Environment

Item 8

Contact: Jim Soutar, ext 6049 email: jim [email protected]

1. Summary

1.1 This report sets out the finalised Capital Programme for 2004/05, the draft programme for 2005/06 and the preparation pool of schemes to be considered beyond 2005/06, focusing particularly on the Solent area. The Panel is asked to note the 2004/05 programme and to endorse the 2005/06 draft programme.

2. Integrated Transport Capital Programme

2.1 On 23 January 2004 the Executive Member for Environment agreed the County Council's Environment Capital Programme being submitted to Cabinet on 23 February 2004. The report updated progress on and proposed amendments to the 2003/04 Integrated Transport Programme and set out the proposed Capital Programme for 2004/05 to 2007/08. These programmes were submitted for approval to the County Council on 25 February 2004.

2.2 The Integrated Transport Capital Programme is primarily funded by Government, either through specific grant and credit approvals (for schemes costing over £5 million) or through the general allocation of credit approval in the Local Transport Plan Settlement (for schemes costing less that £5 million). Additional funding is also available for specific schemes from external bodies, primarily contributions associated with major new developments, but in some cases from district councils' own Capital Programmes. Relevant schemes are included in the capital programme when it is anticipated that this external funding (EF) will be available and a scheme is sufficiently developed for implementation. In some cases schemes may be funded through both EF and Government funding.

2.3 On 19 December 2003 notification was received from the Government Office for the South East on its assessment of the County Council's Annual Progress Report submitted in July 2003 and its allocation of resources. The total block allocation is £31.179 million, comprising £15.783 million for integrated transport and £15.396 million for maintenance. This compares with indicative allocations of £13.120 million and £7.893 million respectively, notified in the December 2000 LTP settlement. The integrated transport total includes £900,000 for schemes in the A27 corridor, and reward funding of £1.763 million for the County Council's continued strong performance. A ring fenced allocation for 2004/05 of £7.5 million has also been made for the A3 Bus Priority Corridor which was accepted as a major scheme by the Government on 28 October 2003.

2.4 The new programme has been produced on the basis that, from the £31.2 million available for 2004/05 through the LTP process, £17.3 million will be spent on highway maintenance and bridges, and £13.9 million on integrated transport. In 2005/06 the forecast resource totals are £17 million for highways maintenance and bridges and £14 million for integrated transport. The 2005/06 figures anticipate that the allocations will continue to be well in excess of the previously published indicative allocations for those years (as in 2004/05). The years 2006/07 and 2007/08 will be the first two years of the next five year LTP. For planning purposes it has been assumed that the allocations will be the same as 2005/06. For integrated transport the 2004/05 resources will need to cover expenditure required to complete the 2003/04 and earlier programmes and development costs of post 2004/05 projects, including major schemes as well as the cost of implementing the 2004/05 programme. A 2004/05 starts programme has been approved by the County Council, which will be managed to deliver the required spending during the financial year.

2.5 The new programme is based on the draft programmes presented to the former Area Transport Strategy Panels in autumn 2003. Each scheme was assessed against LTP objectives, the County Council's Corporate Objectives and the Government's ten-year transport objectives of economy, environment, accessibility, safety and integration. These Panels supported the programmes as submitted. However, some additional schemes had been added or brought forward where they are specifically related to the County Council's Public Service Agreement with regard to promoting bus patronage (a total of £4 million) and reducing road accident casualties (a total of £2.6 million). There is also additional funding for the Safer Routes to School Programme (a total of £1.25 million) which was identified as a priority by the Environment Policy Review Committee. In some cases LTP funding has been introduced to supplement schemes which are largely funded from developers' contributions but there is a shortfall. Some schemes have been delayed, either from 2003/04 into 2004/05 or from 2004/05 into 2005/06, because of programme slippage either on that particular scheme or a related project.

2.6 The integrated transport capital programme for the Solent Transport Strategy area is shown in Appendices 1 to 4. Appendix 1 shows the casualty reduction and county-wide/other programmes for 2004/05 and 2005/06. Details of some county-wide programmes will be subsequently submitted to the Executive Member for Environment for approval. Appendix 2 shows, for information, the 2004/05 programme, and includes the previous strategy areas together with the current status of individual schemes. In some cases the title has been amended as compared to previous reports. These are primarily to clarify matters given that the new programme includes schemes previously reported to the former ten Transport Strategy Panels. Where appropriate details are given in the remarks column. The proposed programme for 2005/06 shown in Appendix 3 is based upon the draft programmes presented to the former Area Panels last autumn. The current list of Preparation Pool schemes is shown in Appendix 4. The development of the new LTP for 2006-2011 could lead to significant amendments, including proposed deletions of schemes because of poor ratings against objectives and new schemes resulting from the development of the new LTP. A report will be presented to the autumn meeting of the Panel.

3. Proposed Planning Obligations Reform

3.1 The Office of the Deputy Prime Minister issued a consultation paper in November 2003 on the reform of the planning obligations policy. Such a change would affect the way in which developers contributions towards transport improvements are assessed and collected. Developers currently pay a contribution towards appropriate infrastructure and other improvements or measures following a negotiating process with the relevant local authority. The Government is minded to introduce a change whereby applicants for development could instead pay a 'planning charge'. This would lead to a tariff based approach to contributions from development. Draft regulations and a revised circular will be published for consultation in March/April 2004.

Recommendation

That the Panel notes the approved programme for 2004/05 and endorses the proposed programme for 2005/06.





Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

8548/MJS

APPENDIX 1

2004/05 and Draft 2005/06 Casualty Reduction Programme

The object of the programme is to meet the County Council's Public Service Agreement targets for casualty reduction.

Scheme

LTP Allocation £'000

Remarks

2004/05

2005/06

Low cost safety programme

1500

1500

Site specific schemes, usually comprising signing, road markings and surfacings

Water Lane, Totton (plus 130,000 EF)

120

Initial design under way

Future Safety Schemes

1000

1000

Programme to be determined

TOTAL (plus £130,000 EF)

2620

2500

APPENDIX 1 (continued)

2004/05 and Draft 2005/06 County-wide/Other Capital Programme

Programme

LTP Allocation £000

Remarks

2004/05

2005/06

Pedestrian Crossings

500

300

Continuing programme of new Pelican and Zebra crossings

MIRACLES

100

EU supported project for Winchester City, including air quality, freight distribution and alternatives to car use

Central Intelligent Transport Systems

200

200

Continuing programme of new computer based traffic management systems

Community Transport Schemes

650

650

New and replacement vehicles

Rural Partnership Schemes

200

200

Continuing programme of local traffic management schemes

Minor Works

250

250

Continuing programme of schemes costing less than £10,000 to meet local priorities

Passenger Transport Information

130

130

Contribution to national computer based public information systems

Safer Routes to Schools

1250

1500

Infrastructure improvements associated with approved School Travel Plans

Railway Stations/Interchanges

200

100

Continuing programme. Schemes to be determined

Air Quality and Noise Monitoring

50

50

Continuing programme of new remote stations

Home Zones/Community Strategies

100

100

Programme to be determined

LTP Monitoring/Initiatives

200

200

Continuing programme of new remote survey sites

Hythe Pier

90

90

Continuing programme of contributions to structural maintenance

Recreational Cycling

100

100

Continuing programme. Schemes to be determined

TOTAL

4080

3930

APPENDIX 2

2004/05 Capital Programme - Solent Transport Strategy Area

(FOR INFORMATION ONLY)

Scheme

Previous LTP Area

Allocation £'000

Remarks

LTP

EF

B2177/B3354 Corridor-Bishop's Waltham - Traffic Management

CHARTS

30

90

Initial study under way.

Denmead Traffic Management

CHARTS

200

20

Previous title `Denmead Village Centre'. Consultation complete. Detailed design under way.

Clanfield Village Initiative

CHARTS

25

Formerly part of CHARTS-wide programme. Consultation under way.

Funtley Road Footway

CHARTS

75

Feasibility complete.

Knowle Village to Funtley Footpaths

CHARTS

40

Feasibility under way.

Wickham to Fareham Bridleway

CHARTS

20

Feasibility under way.

Fareham-Gosport Quality Bus Partnership - Gosport Bus Departure Information System

SEHTS

100

Sub-division of Fareham-Gosport QBP. Preliminary design underway.

Fareham-Gosport Quality Bus Partnership - Bus Infrastructure Improvements - Phase 2

SEHTS

150

50

Sub-division of approved 2004/05 allocation. Continuation of 2003/04 programme.

Havant Route 21 Quality Bus Partnership

SEHTS

200

Previous title `Havant BQP'. Infrastructure improvements to compliment those completed on Route 23.

Havant Decriminalised Parking

SEHTS

100

Administrative procedures under way.

Havant Bus Station

SEHTS

1200

80

Detail design under way.

St Margaret's Lane, Titchfield-Traffic Management

SEHTS

60

Initial studies under way.

Park Lane, Fareham-Traffic Management

SEHTS

30

Preliminary design complete.

Lee-on-the-Solent Sustainable Suburbs

SEHTS

100

Preliminary design complete. Consultation early 2004.

Gosport Urban Centre Improvements

SEHTS

100

Preliminary design under way.

Hayling Billy Route - Havant Railway Station Cycleway- Phase 2

SEHTS

250

Preliminary design complete.

A27 Corridor, Fareham - Traffic Management

SEHTS

400

Feasibility studies under way.

Broom Way, Fareham - Cycleway

SEHTS

250

Feasibility study complete. Detailed design under way.

Salterns Lane, Fareham - Traffic Management

SEHTS

32

Consultation under way.

A27 Southampton Road/Lower Church Road, Locks Heath - Toucan Crossing

SEHTS

100

Additional funding from pedestrian Crossings Programme. Preliminary design under way.

Fareham Western Wards - Western Distributor Road: Schooner Way to Warsash Road

SEHTS

1025

375

Detailed design complete. Land negotiations under way.

Yew Tree Drive, Whiteley - Bus Link

SEHTS

250

250

Initial design being discussed with developer.

Havant Accessibility

SEHTS

85

Initial designs complete.

Rookery Avenue, Whiteley - Link Road

SEHTS

500

Land issues being investigated.

Witherbed Lane, Segensworth - Link Road

SEHTS

1800

Preliminary design complete.

Barnes Wallis Road, Segensworth - Footway and Cycleway

SEHTS

120

Detailed design complete.

Telford Way - Southampton Road, Park Gate - Cycleway

SEHTS

150

Feasibility required.

Newgate Lane - Tukes Avenue, Fareham - Cycleway

SEHTS

70

Detailed design complete.

Gosport Road - Stubbington Green Cycleway

SEHTS

50

Previous title `Stubbington North to South'. Preliminary design under way.

Westbury Road, Fareham - Cycleway

SEHTS

8

Preliminary design complete.

Rumbridge Street, Totton - Traffic Management

SWHTS

600

Previous title `Totton Town Centre'. Initial consultation complete.

A27/Botley Road, Hedge End - Bus Access

SWHTS

300

100

Preliminary design under way.

Factory Road, Eastleigh - Traffic Management

SWHTS

375

250

Initial consultation complete. Detailed design under way.

Eastleigh Quality Bus Partnership - Bus Infrastructure Improvements

SWHTS

200

Continuation of 01/02 and 02/03 programmes. Initial design complete.

Romsey Route 15 Quality Bus Partnership - A27 Junction Alterations

SWHTS

100

Sub-division of previous title `Southern Test Valley BQP'. Detailed design underway.

Romsey Route 15 Quality Bus Partnership - Bus Infrastructure Improvements

SWHTS

50

Sub-division of previous title `Southern Test Valley BQP'. Initial design under way.

Eastleigh Quality Bus Partnership - Leigh Road Selective Vehicle Detection

SWHTS

70

Detailed design complete.

Southampton Road, Dibden -Cycle Refuge

SWHTS

20

Feasibility study complete.

St John's Road/Lower Northam Road/Grange Road, Hedge End - Cycleway

SWHTS

200

Preliminary design complete.

Hythe Town Centre Link Road

SWHTS

150

Review to be reported to New Forest Highways and Transport Panel 16/03/04.

Hound Road, Netley - Cycleway

SWHTS

125

Feasibility study complete.

Romsey Road/Twyford Road Roundabout, Eastleigh

SWHTS

36

Detailed design under way.

Hamble Lane/Portsmouth Road, Bursledon - Toucan Crossing

SWHTS

50

Additional funding from Pedestrian Crossings Programme. Site start Spring 2004.

Redbridge Lane/Brownhill Way, Nursling - Cycleway

SWHTS

40

Feasibility study under way.

Water Lane, Totton - Traffic Management

SWHTS

See Appendix 4: 04/05 Casualty Reduction Programme.

TOTAL

6020

5031

APPENDIX 3

2005/06 Draft Capital Programme - Solent Transport Strategy Area

Scheme

Previous LTP Area

Allocation £'000

Remarks

LTP

EF

B2177/B3354 Corridor - Wickham - Traffic Management

CHARTS

120

Previous title `B2177 Corridor : Twyford - Wickham (Stage 3): Feasibility study required.

Fareham-Gosport Quality Bus Partnership - Bus Priority Measures

SEHTS

400

Continuation of 04/05 programme.

Havant Quality Bus Partnership

SEHTS

100

Discussions to be held with operator and Havant BC.

Hayling Billy Route - A3023 Langstone - Cycleway

SEHTS

300

Previous title `Hayling Billy Route, Havant'. Preliminary design complete.

Havant Pedestrian and Bus Improvements

SEHTS

200

Discussions to be held with operator and Havant BC.

Gosport Decriminalised Parking

SEHTS

100

Study by Gosport BC under way.

Fareham Decriminalised Parking

SEHTS

100

Study by Fareham BC under way.

Stokes Bay, Cycleway, Gosport

SEHTS

300

Previous title `Stokes Bay to Gosport Cycles'. Preliminary design under way.

Lee-on-the-Solent Pedestrian and Bus Improvements

SEHTS

70

Initial discussions with Gosport BC and operator under way.

M27 Junction 9, Whiteley - East Bound Filter

SEHTS

500

Feasibility study required.

Whiteley to Park Gate Cycleway

SEHTS

354

Consultation complete.

Hill Coppice Link Road, Whiteley

SEHTS

200

Associated with M27 Junction 9 scheme.

Eastleigh Quality Bus Partnership - Bus Infrastructure Improvements

SWHTS

200

Continuation of 04/05 programme.

Romsey Route 15 BQP - Bus Infrastructure Improvements - Phase 2

SWHTS

100

Previous title `Southern Test Valley BQP'. Continuation of 04/05programme.

Hythe Interchange

SWHTS

450

Preliminary design complete. Discussions with White Horse Ferry and other land owners under way.

North Baddesley - Rownhams Cycleway

SWHTS

350

Detailed design under way.

Valley Park to Hiltingbury Cycleway

SWHTS

200

80

Preliminary design complete.

Eastleigh Quality Bus Partnership - Riverside /Bishopstoke Road

SWHTS

150

Feasibility study under way.

Hardley to Hythe Cycleway

SWHTS

150

Detailed design under way.

Eastleigh Quality Bus Partnership - Derby Road/Passfield Avenue

SWHTS

100

Detailed design under way.

Winchester Road/Cupernham Lane, Romsey - Traffic Signals

SWHTS

200

100

Preliminary design complete.

Leigh Road Corridor, Eastleigh - Traffic Management

SWHTS

200

Consultation on Eastleigh Central Area Strategy complete.

Nursling and Rownhams Traffic Management

SWHTS

50

Initial study complete.

Turnpike Way, Hedge End. - Traffic Management

SWHTS

250

Feasibility study required.

West End Road/Church Hill, West End - Traffic Signals

SWHTS

250

Initial feasibility study complete.

TOTAL

3840

1734

APPENDIX 4

Preparation Pool - Solent Transport Strategy Area

Scheme

Previous LTP Area

Remarks

Marine Parade, Lee-on-the-Solent Cycleway

SEHTS

Feasibility study required.

A259 Warblington to Emsworth Cycleway - Stage 3

SEHTS

Feasibility study complete.

Fareham, Gosport & Havant - Cycles & Pedestrians

SEHTS

Previous title `SEHTS Cycles & Pedestrians'. Investigations required.

Fareham Urban Centre

SEHTS

Investigation required..

Lee - Stubbington - Gosport Bus & Cycle Route

SEHTS

Investigation required.

Whiteley and Swanwick

SEHTS

Investigation required.

A32/Salterns Lane, Fareham

SEHTS

Feasibility study complete.

Eastleigh Town Centre, Traffic Management - Stage 3

SWHTS

Previous title `Eastleigh Central Area - Town Centre Management'. To follow Factory Road in 2004/05 and Leigh Road Corridor in 2005/06.

Romsey Movement & Access - Traffic Signals

SWHTS

To follow Winchester Road/Cupernham Lane in 2005/06. Investigation required..

Chilworth to Southampton Cycleway

SWHTS

Feasibility study complete.

Woodside Avenue, Eastleigh - Cycleway

SWHTS

Feasibility study complete.

STS Intelligent Traffic Systems

SWHTS

Previous title `SWHTS ITS'. Investigation required.

A326/A35 Totton, Bus Priority

SWHTS

Investigation required.

Hamble Area

SWHTS

Consultation on Area Strategy complete.

Hamble Station Access

SWHTS

Investigation required.

Doncaster Drove, Eastleigh - Cycleway

SWHTS

Feasibility study complete.

Romsey - Nursling Cycleway

SWHTS

Feasibility study complete.

North Baddesley - Chilworth Cycleway

SWHTS

Feasibility study complete.

Shannon Way, Knightwood - Bus Link

SWHTS

Feasibility study complete.

Electron Way, Chandlers Ford - Bus Link

SWHTS

Feasibility study (with Shannon Way) complete.

Totton and Waterside Cycles

SWHTS

Feasibility study complete.

A27 Corridor, Eastleigh

SWHTS

Investigation required.

A3057 Greatbridge Road, Romsey - Low Bridge Warning System

SWHTS

Investigations required.