Blackwater Valley Bus Service 1 Priority Route - Phase 1 A325 Farnborough Road, Farnborough

Report of the Director of Environment

Item 5

Contact: Syd Sadro, ext 6099 email: [email protected]

1. Summary

1.1 The following decision is sought:

      That the virement of £384,000 additional funding from the Local Transport Plan to meet the forecast final expenditure figure of £3.384 million be approved.

1.2 On 14 May 2002 the capital allocation of £3 million for the Blackwater Valley Bus Service 1 Priority Route in Farnborough was approved. This report details additional costs expected to be incurred with the completion of the scheme and seeks approval for adjustments to the Capital Programme to accommodate the necessary additional funding.

1.3 This report was submitted on 10 February 2004, when it was referred to the Environment Policy Review Committee meeting on 3 March 2004 to scrutinise and comment on the detailed decisions made which led to the revised forecast for the scheme going over the 10% variation limit of costs, before a decision is made by the Executive Member for Environment. A verbal update on the outcome will be given at the meeting.

2. Reason

2.1 This project supports Aim 2 of the Corporate Strategy, Stewardship of the environment, by improving travel choices for all through the provision of bus lanes to ensure more reliable, attractive and accessible alternatives to the car to assist achieving an increase of 4% by 2005 in the number of bus passengers per year for local journeys.

2.2 The Blackwater Valley Bus Service 1 Priority Route and A325 major maintenance scheme received support from the former North East Hampshire Transportation Strategy Panel on 26 September 2001 and the Environment Policy Review Committee on 17 September 2001 to

    proceed. On 14 May 2002 the Executive Member for Environment approved the capital allocation of £3 million. The scheme is now virtually complete but costs are expected to exceed this budget by an estimated £384,000.

2.3 The scheme incorporates carriageway maintenance work and is partly funded from developers' contributions. The agreed budget of £3 million for the project was divided up as follows:

      (i) Capital Programme (Integrated Transport) £1,900,000;

      (ii) Capital Programme (Maintenance) £400,000; and

      (iii) developer funding of £700,000.

      The additional funding required can be met by Local Transport Plan capital and does not affect schemes in the committed programme, due to the late award of major scheme funding for the A3 bus priority corridor.

3. Other Options Considered and Rejected

3.1 Not to approve the virement to meet additional costs could result in legal action in respect of legitimate claims from contractors. Developer funding could have been used, but the late award of funds for the A3 project makes the Local Transport Plan the preferred source.

4. Conflicts of Interest Declared by the Decision Maker or a Member or Officer consulted - None.

5. Dispensation granted by the Standards Committee - Not applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.

Approved by: Date:

Councillor K B Estlin

7. Details

7.1 The four main areas of overspend are identified below:

        (i) Disruption to work - £150,000; includes for acceleration of works over the railway bridge in order to limit the disruptive effects of the works on residents and traffic, general disruption to contract works, disruption due to uncharted services and changes to works sequence to carry out the most disruptive works to traffic during school holidays.

        (ii) Increased fees for design and supervision of some £70,000. Additional resources were allocated to deal with large public interest in the scheme which resulted in some changes to the design. The dedicated website for the scheme generated a large volume of correspondence with the public.

        (iii) An increase of some £80,000 in the costs of traffic signals over the original estimates as reported on 14 May 2002 to the Executive Member for Environment. It was revised following:

                (a) the inclusion of a new Toucan crossing in Victoria Road;

        (b) the upgrade of equipment at several Pelican crossings;

        (c) to meet the new regulations for Puffin crossings; and

                (d) costs for closed circuit television cameras for real-time traffic monitoring.

        (iv) A contingency sum for the settlement of contractual claims by the contractor.

7.2 Other areas of increased cost included:

        (i) additional landscaping of the corridor as requested by Rushmoor Borough Council as partner to the project; and

        (ii) changes to signs following a change in policy to allow taxis to use the bus lane.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

Capital Programme 2002/03 as reported to the Executive Member for Environment on 14 May 2002

Environment Department

8610/SS