Archived decisions

Hampshire County Council

North Hampshire Transport Strategy Panel

23 March 2004

Local Transport Plan and Transport Strategy Development

Report of the Director of Environment

Item 6

Contact: Peter Syddall, ext 6050 email: [email protected]

1. Summary

1.1 The transport strategies for North Hampshire and the other three areas will form part of the next Hampshire Local Transport Plan (LTP). Hence, it is intended to develop the transport strategies for the new areas in tandem with the next LTP. These will take account of the issues carried forward from the previous area transport strategies and will provide the framework within which currently identified/new schemes and initiatives will be assessed and considered for implementation. The transport strategies will be integrated with policies formulated for the county as a whole and the region, but will also address issues at a local level.

1.2 Members are asked to comment on the approach set out in the report which envisages the adoption of the area transport strategies in spring 2005.

2. Introduction

2.1 Work is now commencing on the preparation of the second LTP to be submitted to Central Government in summer 2005. This report outlines the process and timescales for the preparation and delivery of the LTP and the Annual Progress Report (APR) (2004). The area transport strategies are the mechanism through which transport schemes and initiatives are promoted and delivered. A transport strategy will be developed for each of the four areas in Hampshire within the LTP. The development of the strategies involve the participation of the key stakeholders, including transport providers and operators as well as local authorities, the business community, interest groups, organisations and local residents.

3. Second Local Transport Plan 2006-2011

3.1 It is expected that the County Council will need to produce its second LTP by 31 July 2005. The Department for Transport (DfT) is likely to produce draft and then official guidance for the preparation of this LTP in spring and summer 2004 respectively. However, details are beginning to emerge about the new processes that will be added to the LTP, including the requirements for accessibility audits and strategic environmental assessments (discussed in section 4 below). It is likely that the broad principles will be similar to those applied to the first LTP.

3.2 The present LTP is based on the Government's five overarching policy areas relating to Integration, Economy, Environment, Safety and Accessibility. In setting out its guidance for the next LTP the Government is expected to place emphasis on measures to improve accessibility and tackling congestion.

3.3 It is intended that the following principles form the basis for the County Council's LTP:

        (i) it should be a `whole of council' strategy that is owned by all parts of the Council and helps to deliver a wide range of non-transport objectives. This reflects the fact that transport contributes to most of the Council's objectives;

        (ii) it should exceed Government guidance, in order to achieve a `well above average' status and number one LTP rating;

        (iii) it should be developed following thorough consultation to reflect the public's needs and views;

        (iv) as part of the County Council's `centre of excellence' status, that information is shared with other authorities about the steps being taken to produce the LTP, in particular the Solent Transport authorities of Portsmouth, Southampton and the Isle of Wight; and

        (v) the LTP strategy should be an appropriate balance of the effective delivery of core services and innovative transport solutions.

3.4 The Hampshire LTP is developed in conjunction with the LTPs of neighbouring authorities, including Dorset, Wiltshire, West Berkshire, Wokingham, Surrey, West Sussex, Isle of Wight, Portsmouth and Southampton. Joint working between authorities on LTPs is encouraged by Government.

3.5 A management structure and programme to deliver the LTP is being developed, which will ensure involvement of the Transport Panels at key stages of the production of the document. In particular they will be able to consider the overall vision and strategies of the LTP. The key stages in the process are likely to be as shown in Appendix 1.

4. Strategic Environmental Assessments

4.1 The preparation of Strategic Environmental Assessments (SEAs) is a requirement from Central Government that applies to a range of plans produced by the County Council, including the LTP. The objective of the SEA Directive, laid down from Europe, is to "provide a high level of protection of the environment and to contribute to the integration of environmental considerations into the preparation and adoption of plans ... with a view to promoting sustainable development".

4.2 The SEA for the LTP needs to commence at the start of the preparation process of the document and continue to be applied through the consultation and production phases. The DfT issued draft guidance in December 2003 covering how SEA should be applied to LTPs, including the relationship with other plans, the development of objectives and indicators, identifying problems and opportunities, consideration of options and monitoring.

4.3 An officer forum has been set up to look at the implications of this Directive on the work of the Environment Department and the County Council as a whole. The forum is currently in the process of appointing external consultants to support work in this area, with the preparation of protocols. This will provide an additional resource to support the SEA work during the preparation and production of the LTP.

5. Annual Progress Report 2004

5.1 The County Council will need to consider its 4th Annual Progress Report (APR) prior to a submission to Government on 31 July 2004. Government guidance on APRs currently requires the authority to demonstrate performance against three main criteria:

        (i) the effectiveness of the authority's spending programme, including how closely actual spending for the year matched its plans;

        (ii) the number of schemes delivered in the year, and how closely this compared with the authority's plans for that year; and

        (iii) progress against targets and performance indicators, including an assessment of which targets are on track and those which are not.

5.2 In addition to a statistical analysis of these three points, the APR will provide a commentary on spending, scheme delivery and performance targets. Where targets are not being met, the commentary explains why and what the authority has done, or is planning to do, to rectify the situation.

6. Relationship with Community Strategies

6.1 Community Strategies are at the heart of the Government's inclusion and delivery agenda. They are seen as the practical tool for councils and their partners to ensure the economic, social and environmental well-being of the community. Increasingly they are promoted by Government as the basis for dealing with life-style matters such as accessibility. They are expected to be dynamic documents dealing with current issues within a long-term framework. Their action plans need to be flexible in order to respond promptly to changing circumstances. Not surprisingly, traffic and congestion feature highly in the issues identified in Community Strategies.

6.2 It is important to link the aims and objectives of Community Strategies with those of the LTP. The issues that they seek to address are similar. They share a common feature in the importance both processes attach to community involvement and partnership working.

7. Developing the Area Transport Strategies

7.1 Government guidance on producing the next round of LTPs will not be published until 2005. However, indications are that the approach taken by the County Council for its current LTP will continue to be welcomed. Each of the previous area transport strategies formed, in effect, a mini LTP covering its area, taking into account local views and circumstances.

7.2 As a first step each transport strategy will need to determine a vision for the area so that the policies and initiatives can have direction. Objectives will need to be determined although these can, to some extent, be updated from those for the former areas.

7.3 The involvement of stakeholders in addition to local authorities is a vital element in the preparation of a strategy. These are likely to include:

        (i) transport infrastructure providers (eg Highways Agency, Network Rail);

        (ii) interest groups (eg cycling and walking organisations);

        (iii) business interests (eg Hampshire Economic Partnership, commuter forums, Chambers of Commerce and Industry, town centre managers);

        (iv) public transport operators (rail, bus and ferry operators);

        (v) freight interests (eg local operators, Freight Transport Association); and

        (vi) representatives of disabled people, residents associations, parish councils, developers, health authorities, schools, etc.

7.4 Realistic targets will need to be set with appropriate, measurable performance indicators. A monitoring framework will need to be determined so that data can be provided for the performance indicators. This monitoring will need to include information from a range of transport and economic sources as well as attitude surveys where possible. Base data for the area will be consolidated so that future changes, trends and the impacts of policies can be demonstrated.

7.5 As the strategy is developed, a programme of measures will need to be agreed. This will include a range of schemes to support the objectives of the strategy that will be assessed to indicate priorities. The programme will need to include initiatives to promote alternatives to car use in addition to physical schemes. A five year outline of proposed measures will need to be determined so that the funding from both LTP and external sources can be identified in the County Council's capital programme. Once the shape of the programme has been determined, then individual measures can be taken forward through the process of feasibility studies, surveys, design and implementation.

7.6 The inclusion of the area transport strategies in the LTP will require them to be agreed in early 2005, and therefore initial drafts should be considered in autumn 2004. Consultation with stakeholders and the wider public is required prior to submission. In order to complete the initial draft, work will commence in spring 2004 with the views of the main contributors being invited at an early stage. The LTP process envisages extensive dialogue on the area transport strategies and on specific themes, eg bus services, freight, school travel, etc, and this will be reflected in the development of the area strategies.

7.7 The area transport strategies form one layer in a hierarchy of plans. At a regional level, the Regional Spatial Strategy and the Regional Transport Strategy (RTS) will set the direction for land use and transport planning across the South East (these were discussed further under Agenda item 5). LTPs are expected to conform with the RTS.

7.8 The area transport strategies should be strongly related to development plans, either ongoing Local Plans or emerging Local Development Frameworks (LDFs). This will ensure the integration of transport and land use considerations. The Regional Spatial Strategy will supersede Structure Plans and the direction for LDFs.

7.9 Within each strategy area, specific policies and initiatives for key settlements/areas will be carried forward or developed. Within North Hampshire these are likely to include Basingstoke, Farnborough and Aldershot and Fleet.

8. Base Data and Targets

8.1 The LTP requires the setting of a range of targets against which progress is reported annually. These need to be considered in the context of the revised strategy areas, particularly where there are urban concentrations - maintaining distinct targets for some smaller areas may be appropriate within wider areas. Regular monitoring is a requirement of the LTP and the requirements are being extended, where possible, to include all modes of transport and related economic and social indicators. These requirements, and the regular cycle of Transpol household questionnaire surveys and other attitude surveys, need a considerable resource input.

8.2 Traffic data for major routes is shown in Appendix 2. This indicates that on the trunk road network there are significant flows, particularly on the M3 towards London, with increasing demands in recent years. The A34(T) has the highest growth in Hampshire over the past five years from around 29,000 vehicles per day near Whitchurch in 1997 to around 41,000 in 2002. The A3 and A303(T) also demonstrate high growth in recent years.

8.3 Although there has been an overall increase of 7.5% in traffic flows between 1997 and 2002 on the A and B roads within the North Hampshire Strategy Area, there was a 10% rise on the motorway network over the same period. The largest increase in North Hampshire, excluding the A34, was on the relatively new A331 Blackwater Valley Road at 18%. There have been some reductions in traffic on the A33. This follows the building of the Newbury by-pass and the detrunking of the A33. The year 2000 saw a dip in traffic levels which coincided with the fuel shortage of that year. However, the previous trend of rising traffic has now been resumed.

9. Key Issues and Actions from the Former Transport Strategy Areas

9.1 Many of the key objectives and themes from the former area transport strategies will be carried forward to the new areas for consistency. A number of themes have emerged for North Hampshire that will need to be considered within the new arrangements including the following:

      (i) congestion;

    (ii) bus priority;

        (iii) greater use of demand management measures such as travel planning; and

      (iv) road safety.

10. Conclusion

10.1 The development of revised transport strategies provides an opportunity to consider issues on a wider basis in tandem with the preparation of the Hampshire LTP. While the former areas have been amalgamated, specific issues will be considered in the new strategies ready for inclusion in the next LTP in 2005. To achieve this, initial work to draft the strategies will take place prior to the autumn 2004 meeting of the Panel.

Recommendation

That the Panel endorses the approach and timetable of developing strategies for the newly established transport strategy areas.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

8677/PCS

APPENDIX 1

LOCAL TRANSPORT PLAN DRAFT PREPARATION PROGRAMME

Consultation

Autumn 2004 and spring 2005

Area Transport Strategy Panels

Summer 2004

Stakeholders consultation, including district councils

Autumn 2004

Public consultation, exhibitions, website, events, focus groups, surveys

Spring 2005

Report to Executive Member for Environment

Every two months

Steering group with district council officers

Publication schedule

2004/early 2005

Establish LTP contents and structure

2004/early 2005

Agree contents and structure with stakeholders

April/May 2005

Executive Member approves structure and content

29 July 2005

LTP 2006-2011 and summary document publication

Post-publication

December 2005

LTP settlement letter from GOSE with funding allocation for 2006/07 and indicative allocation for period to 2010/11

January 2006

Setting of Capital Programme

APPENDIX 2

NORTH HAMPSHIRE TRAFFIC TRENDS

National

Location

1997

1998

1999

2000

2001

2002

last 5 yrs

last 2 yrs

M3 Junctions 4 to 4a

97026

101529

101977

100492

104703

105964

109.2

105.4

M3 Junctions 5 to 6

91293

94215

95701

95806

97250

98816

108.2

103.1

M3 Junctions 7 to 8

84645

87723

89501

89867

94185

95560

112.9

106.3

Total

272964

283467

287179

286165

296138

300340

110.0

105.0

last 5 yrs

last 2 yrs

County

1997

1998

1999

2000

2001

2002

(1997=100)

2000=100)

A339 Kingsclere

13064

13497

14146

13868

13867

14232

108.9

102.6

A339 north-west of Basingstoke

12132

12269

12842

12562

12611

12965

106.9

103.2

A33 Stratfield Saye

18255

18578

18583

19117

19494

19284

105.6

100.9

A325 Farnborough

22535

22643

23164

24032

24828

24963

110.8

103.9

A325 Hawley Link

34925

35755

35692

35946

38028

37193

106.5

103.5

A327 Eversley

11054

11558

12258

11364

11206

11602

105.0

102.1

A331 Blackwater Valley Road

44907

49186

51044

51159

51804

53139

118.3

103.9

A30 Yateley

15577

15698

15339

14928

14925

14827

95.2

99.3

A30 Hartley Wintney

14956

14733

14581

14473

14226

14761

98.7

102.0

A30 Black Dam

17065

16479

16048

15715

15951

15628

91.6

99.4

A323 Hartley Wintney

10018

9827

9732

9729

10244

10449

104.3

107.4

A340 Tadley

14638

14895

14726

14410

14594

14783

101.0

102.6

A3011 Lynchford

18564

19382

19338

19155

19518

19486

105.0

101.7

A3013 Fleet

23731

24063

24342

23420

24869

22018

92.8

94.0

B3272 Eversley

8807

8793

8779

8594

8564

8828

100.2

102.7

County Roads total

280228

287356

290614

288472

294729

294158

105.0

102.0

Overall Total

553192

570823

577793

574637

590867

594498

107.5

103.5

Boundary Roads

A34 south of Bullington

36348

37563

40558

43224

43673

45730

125.8

105.8

A34 Whitchurch

28963

29171

36654

39375

40672

40725

140.6

103.4