Archived decisions

Alternative Procurement 2003/2004 Appendix 2

WORKS

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

Two Stage Partnership Arrangement with Preferred Contractor

New Sports Halls

Totton Hounsdown incorporating:

    · Science Laboratories funded from the Specialist Schools initiative

Fernhill

Alderman Quilley incorporating:

    · Main entrance improvements

Wyvern incorporating:

    · Refurbishment of existing Sports facilities

Test Valley School incorporating:

    · Basic Need Accommodation

    · Food Technology and fire precautions (NDS 2004/5)

Brazier

1,529,000

(est)

1,298,405

1,430,000

(est)

· Best value submission based upon a package of work

· Further collaboration with a preferred contractor over design and construction of a standard sports hall solution

· Creating capacity to deliver a programme of work

· Establish supply chains for key components and specialist designed elements

· Consideration of package procurement to achieve economies of scale

· Involvement of a preferred contractor with key enabling works in advance of the main contracts

2,187,000

2,267,000

(est)

· Repeat opportunities for similar work

Brookfield School

Performing Arts Building

1,365,544

· Invitation to undertake scheme on the basis of a best value submission

· Major contractor with design development expertise required to complete the design and to procure this scheme in line with the agreed programme

· Early involvement of a preferred contractor desirable in order to carry out key enabling works in advance of the main contract

· Early involvement of key specialist subcontractors desirable in order to procure key packages in line with the main building programme.

Wildern School

New multi-use Sports Hall and Learner Pool

HBG

1,986,194

· Invitation to negotiate based upon an agreed cost limit to develop the design and build

· Existing develop and construct contractor's team have recently successfully completed a major project at the same site

· Need to procure this package of work in a short timescale to meet the agreed programme; this will involve some overlapping of the design and procurement which is best managed through collaborative arrangements

· Contractor with good track record of delivering complex projects through a partnership approach

· Will be able to establish cost certainty in the shortest possible time

Best Value Single Stage Tendering

Best Value Single Stage Tendering

Alton Library

Richardsons

1,274,000

· Short list of three preferred firms invited to tender on the basis of best value proposals

· Complex town centre project which would benefit from earlyinvolvement of preferred contractor

· Essential to incorporate evaluation of contractor's site management proposals as part of the tender evaluation process

· Maximise programme and cost certainty

Elvetham Heath School

Enlargement to 2FE

Mansell

1,123,492

· Short list of three major contractors invited to tender on the basis of best value proposals

· Essential to evaluate contractor's scheme implementation proposals for this significant project to extend the recently completed school

· Ensure a good understanding of the project, programme and the site Health and Safety management before commencing the works

· Evaluation of supply chains and programme to assure effective delivery of this project

Negotiated Work

Alton Day Care Centre

Benson

969,000

· Negotiation with tenderer who submitted lowest price for original scheme

· Need to retender specific elements of original scheme due to higher than expected initial price

· Utilise key retained elements of original tender in establishing cost of revised scheme

· Achieve earliest possible programme and cost certainty

· Involvement of preferred contractor with final design development

Warblington School

Internal alterations to Technology Block

Mansells

1,098,260

· Negotiation based upon a two stage tendering process

· Early contractor involvement in programming and phasing of work to achieve a short construction period in order that the facilities are operational at the commencement of the new academic year.

· Contractor with established supply chains for this type of scheme who are able to mobilise at short notice

· Previous good performance on similar projects

Westgate School

Science, administration and entrance improvements

Benson

1,000,000

(est)

· Negotiate with preferred contractor

· Contractor with understanding of site and buildings to be involved with this scheme on a design develop and construct basis

· An earlier competitive tender by the same contractor will form a basis to negotiate

Henry Beaufort School

Improvements to Dining Area, Kitchen, ICT and CDT

Calthorpe Park School

Additional Teaching Accommodation

Richardsons

349,980

1,201,500

· Schemes transferred to an alternative preferred contractor following financial difficulties encountered by original firm

· Contractor with capacity and resources to take on these projects and respond at short notice

· Ensure continuity with original programme intact

· Retain the benefit of tendered work to date including proposed supply chains, pricing and programme structure

· Contractor has a successful track record of delivering similar schemes

Rookwood School

Fire damage reinstatement, recladding and alterations

Tew Brothers

787,000

· Negotiation with preferred contractor

· Previous experience of fire damage reinstatement and associated work

· Need to appoint a contractor quickly to make building safe and commence emergency work

· With the works later extended it was sensible to continue with the same contractor due to overlapping sequence of work and to maintain continuity

· Works requires early completion as connected with the new Winchester EYC due to start spring 2004 (requires relocation of Hampshire Music form Bereweeke Road to this site)

·

Aldershot Park Primary School

Early Years Centre

Gregory Havant

609,000

· Need to appoint reliable contractor able to undertake design develop and construct approach - working closely with in-house designers

· With a programme giving a September 2004 completion, an early contractor appointment is advisable

Marchwood Junior School

Additional classrooms

Bensons

740,370

· Invitation to negotiate based upon previous partnering experience

· Early involvement of preferred contractor required over enabling works phasing and implementation programme

· Established pricing frameworks from previous projects

· Opportunity to engage with same contractor team who have just successfully delivered major partnership scheme for the County Council

Hamble Community College

Replacement Youth Building and refurbishment of the Newbold Block

Bensons

670,000

· Negotiation with existing contractor on site

· Shared resources and achieve an economy of scale

· Inappropriate from a health and safety point of view to have two contractors working in similar locations

· Competitive tender prices will serve as a pricing benchmark and existing supply chains would also be utilised

Costello Technology College

Fire Re-instatement

Tew Brothers

489,000

· Negotiation with preferred contractor

· Proven track record required (recently completed Thornden School fire damage re-instatement and currently undertaking the former Rookwood School fire damage re-instatement

Sharpes Copse Primary School

Early Years Centre

Brazier

480,453

· To involve a preferred contractor with the development of the scheme who has a good understanding of site security issues which may be faced

· Established good working relations with school and work of a high standard

· To resolve access and phasing issues at an early stage

· Established pricing framework from earlier phase of work undertaken at the site

Serles House Winchester

Phase 1b , 2 and 3

Richardsons

420,965

· Competitively tendered Phase 1b to a short list of specialist contractors and negotiation of Phase 2 with successful contractor

· Limited number of firms suited to this type of work

· Would enable Phase 2 to be design developed for greater cost certainty with specialist firm working alongside the design team.

· Reduction in contractor set-up costs by combining both schemes with a single contractor

Horndean and Noadswood Schools

Fire Alarm Installation

Prestige Fire Protection

215,000

· Negotiation with preferred contractor

· In order to meet the intended Autumn 2003 start it was sensible to engage with a preferred contractor over procurement and access

· Consistency with work being done through Term Engineering Contracts with same specialist

· Sound basis to negotiate using previous pricing models

· This contractor has a track record of producing work to a high quality

Hounsdown School

Dining Room Extension

TAB

176,000

· This project is best undertaken on a develop and construct basis to achieve a prompt start on site to meet the programme

· TAB have successfully undertaken work at the school under similar arrangements

· Contractor with resources available in the required timescale

· Previous good working relationship with School and Department

· Early cost and programme certainty required to launch scheme

Audleys Resource Centre

Bartrams

163,345

· Negotiation with contractor who carried out pilot phase

· Joint development of solution

· Cost developed from pilot phase of work

· Continuity together with knowledge and understanding of project issues

Fitting out Unit B, Winnall

H N Edwards

160,000

· Negotiation with preferred contractor

· Further phase of work required which it would be sensible to undertake through original contractor

· Established rates and prices would enable quick agreement of cost

· Pre-planning and programme management

Wildern School

Science Laboratory Refurbishment

HBG Construction

156,201

· Negotiation with existing contractor on site

· Continuity with works already underway of a similar character

· Single point of responsibility for all works being undertaken at the site

· Existing rates and prices will form a sound basis for negotiation

· Economy of scale through a larger package of work

Wyvern Technology College

Sports Facilities

McArdle

141,030

· Negotiation with specialist contractor involved with earlier phase of work

· Competitive price already obtained which is unlikely to be bettered by further tendering

· Advantageous to involve specialist with prior knowledge of the site

· Specialist who performed well on the previous phase of work

· Advance works required by specialist ahead of main new build sports hall

Woodcott Primary School

Re-cladding and re-roofing

D M Habens

134,000

(est)

· Negotiation with existing preferred Contractor

· Further phase of work as a continuation of work already underway

· More efficient programme delivery and cost certainty at an early stage through existing pricing structure

· `Open book' tendering for new works and reduced/lower site set up costs due to continuity of work

Brune Park Community School

Window/Cill replacements

John Hobden

103,500

(est)

· Negotiation with existing contractor on site

· Continuity with works already underway of a similar character

· Single point of responsibility for all works being undertaken at the site

· Existing rates and prices will form a sound basis for negotiation

· Economy of scale through a larger package of work

New Milton Junior School

Extension to ladies toilets, alterations and rewiring following asbestos removal

Woods Commercial Facilities

96,000

· Negotiation with existing contractor

· Continuity, shared management costs and the practicality of interfacing with a single contractor

· Early engagement desirable based upon contract arrangements

The Hurst Community School

Fire Alarm Installation

W Churches

90,000

· Negotiation with preferred contractor

· Continuity with other work undertaken with the same specialist throughout the County

· Sound basis to negotiate using previous pricing models

· Established preferred contractor for this type of work

Elizabeth II Court - Winchester

Roof Repairs

West End Roofing

87,000

· Need to address Health and Safety risk as soon as possible due to slipping tiles

· Have sound basis to negotiate through existing projects and market tested rates

Elson Infant School

Library Extension

Gregory Havant

85,000

· Negotiation with preferred contractor on the basis of a develop and construct package

· This contractor has combined successfully on a number of schemes with the same architectural team to deliver projects for the County Council

· Enables a fairly short pre-contract period in order to take advantage of project commencement over the 2003 Summer period

· This contractor has achieved a good to excellent performance in the delivery of previous projects of a similar nature

Negotiated packaged work

Science and Food Technology under NDS 2004/5

Cove and Fernhill Secondary Schools

Noadswood and Richard Aldworth Secondary

Nolan Davis

540,000

· Negotiation with preferred contractor

· Previous experience and involvement with an earlier phase of work under the 2003/4 programme which had been competitively tendered

· Potential to link to established supply chain for specialist furniture

LST Building Services

250,000

·

Electrical Installation

T&I Programme

Caradas Technical Services

350,000

(est)

· Negotiation with preferred contractor based upon pricing for previously completed work

· To resolve procurement and access issues at an early stage

· Sensible to engage early with a preferred contractor who has successfully delivered similar work over recent years

Primary School Sites

Playing Field Drainage Schemes comprising a Package of 13 Sites

Swanwick Construction

Kieron Beattie Landscaping

167,000

(est)

· Invitation to negotiate

· Packages of work added to a competitively tendered larger package to ensure these further sites are completed over the summer holiday period

· Both contractors have capacity in required timescale and the competitively tendered rates will form a sound basis for the negotiation

External Redecorations and prior repairs (including NDS funded schemes)

Package 1

Audleys Resource Centre

Buryfields Infant School

Cliddesden Primary School

Crookham Junior School

Mottisfont Court

The Butts Primary School

The Clere School

The Vyne Community School

Pool & Son (Hartley Wintney) Ltd

345,897

· Negotiation with preferred contractors

· Demonstratable track record of delivering similar work to a high standard

· Available resources in required timescale

· Sensible to strategically package a group of projects with a reliable contractor

· Established pricing frameworks will ensure value for money is achieved

Package 2

Birch House

Fleet Library

Grayshott Primary School

Petersfield Secondary (F) School

South Farnborough Infant School

Belgravia Renovations

241,993

·

·

Package 3

Locks Heath Infant School

Locks Heath Junior School

Northern Infant School

Purbrook Park Community School

Ranvilles Infant School

219 West Street - Fareham

110A West Street - Havant

Mitie Property Services (Southern) Ltd

427,515

·

·

Package 4

Emsworth Primary School

Havant Registrars

Meadowlands Infant School

Padnell Junior School

Sisken Infant School

Siskin Junior School

Warblington Secondary School

Richardsons Decorating Contractors Ltd

233,202

·

·

External Redecorations and prior repairs(including NDS funded schemes) Continued

Package 5

Alton Registry Office

Bungalow at Fort Nelson

Porchester Community School

St John the Baptist (Solomon's Lane)

Three Minsters House

The Mead Children's Home

Robert G Warwick & Son

264,494

· Negotiation with preferred contractors

· Demonstratable track record of delivering similar work to a high standard

· Available resources in required timescale

· Sensible to strategically package a group of projects with a reliable contractor

· Established pricing frameworks will ensure value for money is achieved

Package 6

Ashley Infant School

Cranleigh Paddock Day Centre

Fordingbridge Infant School

Fordingbridge Junior School

Langdown Infant School

Langdown Junior School

Masters House

New Forest Family Resource Centre

Romsey Infant School

Ferris Painting

198,427

·

·

Package 7

Acorns Early Years

Harrow Way Community School

Knights Enham Infant School

Norman Gate School

St Thomas Infant School

Atkins Painting and Decorating (Contractors)

131,448

·

·

Package 8

Chilcomb Sports Pavilion

Freegrounds Infant School

Freegrounds Junior School

Gosport Day Services

Gosport Family Centre

Hook-with-Warsash Primary School

Stoke Park Infant School

Stoke Park Junior School

Tower Arts Centre

Wickham CE Primary School

Tew Brothers Ltd

318,847

·

·

External Decorations and Prior repairs (Incorporating NDS 2004/05) Continued

Package A

Anton Junior

Burley Primary

Burley School House

Foxhills Infant

Merdon Junior

Ealing Infants

Hale Primary

Netley March Infant

Orchard Close

Atkins Painters and Decorators

165,575

· Negotiation with preferred contractors

· To create capacity to deliver a large programme of work with contractors who have previously given good service which represents value money

· Available resources in required timescale

· Sensible to strategically package a group of projects with a reliable contractor

· Established pricing frameworks will ensure value for money is achieved

Package B

The Hurst Community College

Aldershot Military Museum

Anstey Junior

Chawton Primary

Belgravia Renovations Ltd

239,500

Package C

Noadswood School

Hambledon Infant

Ringwood Junior

Oak Lodge Special

Monument House

St Lukes Swan

Ferris Painting Contractors

345,375

Package D

Eggars School

The Mark Way School

Hampshire Records Office

Harestock Hostel

Riverside Special

Tower Hill Primary

Heathfield Special School

Newtown Primary

Red Barn Primary

Wallisdean Junior

Horndean Junior

Purbrook Junior

Bidbury Infant

Catherington Primary

Mitie Property Services

521,975

WORKS

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

External Decorations and Prior repairs (Incorporating NDS 2004/05) Continued

Package E

Bridgemary Library

South Wonston Primary

Stubbington Study Centre

Droxford Primary

Rachel Maddox Special

Botley Primary

Winnall Primary

Woodcote Primary

Malmsbury Lawn OPH

Richardson Decorating Contractors Ltd

282,875

Package F

The Romsey School

St Patricks Infant School

North Baddesley Infant

St Michaels Infant

Western Downland Primary

Wellow Primary

Cherburg Primary

Hiltingbury Primary

Cupernham Infants

Tew Brothers Ltd

376,625

Package G

Kings School

Curdridge Primary

Ashcroft Arts Centre

Itchen Abbas Primary

Robert G Warwick & Son

246,925

Package H

Winton School

Guillmont Junior

Kings Somborne Primary

Liss Infant

Liss Junior

Portway Infant

South Farnborough Junior

Balksbury Junior

Weeke Primary

Pool & Son (Hartley Wintney)

412,625

WORKS

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

SCOLA Re-cladding Strategy

Hamble Secondary School (completion)

Benson Ltd and

Wessex Windows

288,000

(subcontract)

· Competitive tendering with specialist windows package

· Recladding works included in major Education Capital Programme project using an established preferred specialist to ensure continuity with previous phases

Alton Eggars (Phase 2)

Drew Smith and

Wessex Windows

536,391

· Negotiation with preferred contractors

· Both contractors have combined to give negotiated prices on Phase 1, working effectively together to minimise disruption to school

· Continuity of utilising an established good working relationship to delivery this project

Hounsdown School (NDS 2004/5)

DM Habens and

Wessex Windows

200,000

(est)

· Negotiation with preferred contractors

· Continuity with previous phase of work with the same specialist and main contractor (appointed following a competitive tender process)

Winklebury Infant

D M Habens

Architectural Aluminium

Systems Ltd

358,900

· Negotiation with preferred contractors

· Recladding works included in major Education Capital Programme project using an established preferred specialist to ensure continuity with previous phases

Roofing Repairs

Winton School

Replace vapour barrier to Sports Hall

West End Roofing

117,000

(est)

· Negotiation with preferred contractor

· Continuation following pilot phase of work

Elizabeth II Court

Roof repairs

87,000

(est)

·

· Need to appoint a preferred contractor quickly to respond to Health and Safety risk of slipping roof tiles

Flat Roof Maintenance Framework

Existing Programme

Clere Secondary

Front Lawn Infant

Front Lawn Junior

Frogmore Community

Icknield Special

Kempshott Junior

Mill Rythe Junior

Petergate Infant

Poulner Junior

Preston Candover Primary

Romsey Junior

Saxon Wood Special School

South View Junior

Wolverdene Special School

Survey & Construction (Roofing) Ltd

910,721

(est)

· Framework Agreement

· Specialist contractor who can undertake a serial Contract for roofing work over an agreed term

· Continuity of work and establishing common standards

· Ability to `call off' schemes to an agreed programme

· Value for money due to a larger package of work

WORKS

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

Flat Roof Maintenance Framework Continued

Further projects included in the 2004/05 NDS programme

Chalk Ridge Primary

Crofton Ann Dale Junior

Frogmore Secondary

Front Lawn Junior

Hart Plain Junior

Holbury

Kings Secondary

Meadowlands Junior

St James Primary

St James Emsworth

Samuel Cody

The Bridge Centre

The Clere Secondary

Vigo Infants

Westfields Junior

Winklebury Junior

1,135,000

(est)

Single Stage Selective Tendering (Short List)

Laboratory Refurbishment Package 1

Crookhorn Community

Purbrook Park Secondary

Swanmore College of Technology

Testbourne Community

Benson

1,155,492

· Short list of four preferred contractors

· Proven track record required

· To meet the needs of the school and achieve completion of the works during the school holidays.

Single Stage Selective Tendering (Short List)

Laboratory Refurbishment Package 2

Crestwood Community

Noadswood Secondary

Toynbee Secondary

Nolan Davis Contracting

310,299

· Short list of three preferred contractors

· Proven track record required

· To meet the needs of the school and achieve completion of the works during the school holidays.

Wavell Secondary

Alterations to Library and ICT Areas

Beavis & Partners

130,169

· Short list of four preferred contractors

· Experienced Contractors with proven track record preferred

· To meet the needs of the school and achieve completion of the works during the 2003 school holidays a simplified order process is required.