Archived decisions
WORKS |
CONTRACTOR(S) |
VALUE |
SELECTION METHOD |
REASON FOR PROCUREMENT STRATEGY | ||||
Nursing Care Initiative Strategy (Phases 1&2) | ||||||||
Ticehurst Oakridge House |
Brazier |
4,680,000 4,900,000 (est) |
· Framework arrangements · Sensible to continue with both contractors following pre contract involvement with scheme development |
· Essential to collaborate with selected firms to resolve programme and technical matters at an early stage · Jointly develop key supply chains in order to maximise the benefit of scale and the repetitive nature of the programme of works · Joint financial and risk management in order to ensure greater certainty related to issues of time, quality and cost. · Opportunity to investigate continuous improvement through the the programme of work | ||||
Coldeast Hospital Andover Hospital |
HBG |
5,900,000 5,200,000 | ||||||
Fleming House Marlfield House |
Balfour Beatty |
4,280,000 (est) 4,750,000 (est) |
· Framework arrangements · Suitability - development of refurbishment schemes (based on Malmsbury Lawn) | |||||
Education Capital | ||||||||
South Basingstoke Schools Reorganisation Manor Field Infant and Junior Schools Hatch Warren Infant and Junior Schools (including roof repairs) |
Wates |
1,947,997 2,785,000 (est) 1,560,000 (est) |
· Framework arrangements · First stage tender included with original Framework bids |
· Collaborate with the selected framework contractor over design and programming of the works · Involvement of a contractor in resolving technical issues associated with a major reorganisation package and complex repairs · Achieve an economy of scale by combining both schemes as a single package of work | ||||
· Framework arrangements |
· Collaborate with the selected framework contractor over design and programming of the works · Early involvement of a contractor in resolving complex phasing issues and dealing with site health and safety issues | |||||||
Special Schools Lakeside School extension and improvements | ||||||||
Education Capital (cont'd) | ||||||||
John Hunt of Everest |
Short list of four firms (decision early 2004/5) |
22,000,000 |
· Best value proposals |
· Collaborate with the selected framework contractor over design and programming of the works` | ||||
Winchester Early Years Centre |
Mowlem |
2,400,000 |
· Framework arrangements |
· Resolution of major earthworks scheme requires early contractor involvement · Collaborate over design development and programming | ||||
Eggars School new IT Classroom block and Sports Hal |
1,850,000 |
· Framework arrangements · Packaged with competitively tendered work |
· Achieve economy of scale by combining with major scheme won in competition by same contractor (Amery Hill) · Pre contract contractor involvement required in terms of design development work , programming planning | |||||
Minstead Rural Study Centre |
900,000 |
· Framework arrangements |
· Pre contract contractor involvement required in terms of design development work , programming planning · Good local knowledge required for resolution of local supplier sources to meet sustainable construction brief | |||||
Perins School Sports Hall |
Mansell |
1,500,000 (est) |
· Framework arrangements |
· Pre contract contractor involvement required in terms of design development work , programming planning | ||||
Priestlands School - New Music/Drama facility and extension to dining area |
1,280,000 (est) |
· Framework arrangements · Package with competitively tendered work |
· Achieve economy of scale by combining with major Lottery scheme · Pre contract contractor involvement required in terms of design development work , programming planning · Inappropriate to have two contractors on same site at same time form a health and safety management perspective | |||||
Discovery Centre | ||||||||
Gosport Discovery Centre |
Mansell |
1,700,000 (est) |
· Framework arrangements |
· Pre contract contractor involvement required in terms of design development work , programming planning · Contractor with good track record of similar work for the County Council | ||||
Social Services Re-investment Strategy | ||||||||
Malmsbury Lawn Home for the Elderly Refurbishment |
Balfour Beatty |
1,559,000 |
· Framework arrangements · First stage tender included with original Framework bids |
· Pre contract early contractor involvement desirable in order to resolve design and technical issues associated with this major refurbishment · Early involvement of a contractor regarding programme and phasing arrangements · Potential synergy with the DoH project (also through the framework) and the need to drive continuous improvement into that project | ||||