Archived decisions

Safer Routes to School Programme 2003/04 APPENDIX 3

Schemes in the Test Valley District

School Name

District/

Transport Strategy

School Travel Plan Level

Details/Progress

Clatford CE Primary School

TVBC

WHTS

3

Atkins currently undertaking design and implementation

Halterworth and Mountbatten Schools

TVBC

SWHTS

2

Design underway, work due to start spring 2004

Hatherden CE Primary

TVBC

WHTS

3

Atkins currently undertaking design and implementation

Hurstbourne Tarrant CE Primary

TVBC

WHTS

3

Design underway

Shipton Bellinger Primary

TVBC

WHTS

3

Atkins currently undertaking design and implementation

Test Valley School, Stockbridge

TVBC

WHTS

3

Complete

Wellow School

TVBC

WHTS

3

New footway to rear entrance of school complete. Cycle parking facilities and improvements to school signage underway.

Wherwell Primary School

TVBC

WHTS

3

Complete

Key:

0 Interest shown

1 Initial work on travel plan started

2 Draft travel plan completed

3 Final travel plan submitted