Archived decisions
Safer Routes to School Programme 2003/04 APPENDIX 3
Schemes in the Test Valley District
School Name |
District/ Transport Strategy |
School Travel Plan Level |
Details/Progress |
Clatford CE Primary School |
TVBC WHTS |
3 |
Atkins currently undertaking design and implementation |
Halterworth and Mountbatten Schools |
TVBC SWHTS |
2 |
Design underway, work due to start spring 2004 |
Hatherden CE Primary |
TVBC WHTS |
3 |
Atkins currently undertaking design and implementation |
Hurstbourne Tarrant CE Primary |
TVBC WHTS |
3 |
Design underway |
Shipton Bellinger Primary |
TVBC WHTS |
3 |
Atkins currently undertaking design and implementation |
Test Valley School, Stockbridge |
TVBC WHTS |
3 |
Complete |
Wellow School |
TVBC WHTS |
3 |
New footway to rear entrance of school complete. Cycle parking facilities and improvements to school signage underway. |
Wherwell Primary School |
TVBC WHTS |
3 |
Complete |
Key:
0 Interest shown
1 Initial work on travel plan started
2 Draft travel plan completed
3 Final travel plan submitted