Archived decisions

     

    Hampshire County Council

     

    Executive Member - Environment

    Item 7

     

    7 April 2004

     
     

    Environment Policy Review Committee

     

    5 May 2004

     

    Revenue Budget Monitoring 2003/04

     

    Report of the County Treasurer and Director of Environment

      Contact: Ejner Knudsen, ext 7403 e-mail: [email protected]

      1 Introduction

      1.1 This report provides a further update on the budget monitoring position for the Environment services for the 2003/04 financial year, covering the revenue budgets for highways and transportation, planning and waste management.

      1.2 It reflects the outcome of the most recent budget monitoring exercise, carried out by budget holders within the Environment department, during January and February 2004. During the review, expenditure and income trends have again been considered and planned commitments for the remainder of the year evaluated, in order to arrive at an outturn forecast for each budget heading.

      1.3 Members need to be aware that the figures in this final budget monitoring report for 2003/04 reflect estimated expenditure and the projected outturn for the year based on the monitoring information available at the end of February. Therefore it does not, at this stage, represent the final year end position for the 2003/04 financial year.

      1.4 Almost certainly, some additional variations from the budget plan will have arisen during March, which will need to be identified and reported when the final accounts for the year are prepared. This work is currently underway and is planned to have been completed by the end of May, which would enable the final outturn for the year, together with any significant variations from the budget, to be reported in June.

      2 Corporate Strategy

      2.1 Monitoring of the Environment revenue budget supports all of the aims of the corporate strategy by focusing financial resources in these areas:

            1 Maximising life opportunities

            2 Stewardship of the environment

            3 Achieving economic prosperity

            4 Building strong and safe communities

            5 Improving services

            6 Developing councillors and staff

      3 Changes to the 2003/04 revenue budget cash limit

      3.1 The most recent budget monitoring position, setting out the revised budget for the 2003/04 financial year, was presented as part of the 2004/05 revenue budget report to the Environment Policy Review Committee on 21 January 2004 and to the Executive Member - Environment at his decision day meeting on 23 January 2004. A revised budget of £83.166 million was approved for submission to the Cabinet and included proposals for the carry forward to the 2004/05 budget of savings of £100,000 on management and support services, in support of planned additional expenditure in 2004/05 on IT and e-Government developments, and a projected underspending of £311,000 on the waste management budget for the disposal of abandoned vehicles.

      3.2 The Cabinet subsequently approved the 2003/04 revised budget at their meeting on 12 February 2004. However it was suggested that the carry forward of the anticipated underspending of £311,000 on the budget for the disposal of abandoned vehicles be ring-fenced for the cost of disposal of abandoned vehicles, refrigerators and other electrical or battery components in 2004/05.

      3.3 The only change to the 2003/04 revenue budget limit since January has been in relation to the waste management contract related budgets, where a further allocation of £515,000 has been made from the central waste management contingency to cover estimated cost increases during the third quarter of the financial year. The Environment service's cash limit has been increased to take account of the above change, giving an adjusted revised budget figure of £83.681 million. Further adjustments will be made at the end of the year to reflect the final expenditure on the waste management contract related services together with any other changes that may be required.

      3.4 Appendix 1 sets out the latest budget monitoring position for each of the standard divisions of service, including an assessment of actual expenditure to the end of February, and the projected outturn. The most significant issues that have emerged from the review are discussed in the following paragraphs.

      4 Highways maintenance

      4.1 The 2003/04 cash limit for routine highways maintenance being funded from the revenue budget is £19.865 million. At the time of the final budget monitoring review in February, the value of committed highways maintenance works orders totalled £19.610 million, being an under-commitment of £255,000 against the cash limit. This variation reflected a number of savings against programmes, identified during the budget monitoring review, together with a previous balance of unallocated reserves. Further allocations were subsequently made to the highways units and other departmental budget holders during March to utilise the remaining balances, including provision for additional expenditure on emergencies, signs and road markings, additional traffic management schemes and street lighting energy reduction measures.

      4.2 The 2003/04 revised budget for highways winter maintenance salting and snow clearance is £1.817 million, based on the average level of expenditure during the past four years. A provisional assessment has been made of the additional costs that were incurred during the periods of cold weather and associated snowfall in the last week of January and the second half of February. This suggests that the winter maintenance budget is likely to be over-committed in 2003/04 by approximately £800,000 which, in line with the special budgeting arrangements that apply to this activity, would need to be accommodated from central balances. However, this excess expenditure would result in an increase to the level of provision that would need to be made for winter maintenance in future years' base budgets, based on the four-year average, with a resultant decrease in funding available for structural maintenance.

      4.3 Appendix 2 sets out details of the adjusted 2003/04 highways maintenance programme following the release of available reserves and other adjustments. Details are also provided of works being funded from the capital programme provision for structural highways maintenance.

      5 Public transport

      5.1 The 2003/04 revised budget for County Council funding of public transport is £5.406 million, together with a further sum of £1.335 million being provided from Government Rural Bus Subsidy grant. The 2003/04 revised budget which was approved in January, included an uncommitted sum of £30,000 within the bus subsidies budget, which was expected to be sufficient to meet the cost of any further contract increases during the remaining months of the year.

      5.2 The latest budget monitoring position on public transport shows a forecast outturn for 2003/04 in line with the revised budget. On the bus subsidies budget, there have been a number of largely offsetting minor contract variations which has enabled the remaining uncommitted sum to be allocated for service improvements in the Petersfield area. The £1.335 million allocation of Rural Bus subsidy grant is also expected to be fully consumed in the provision of rural bus services.

      6 Management and support services

      6.1 The 2003/04 budget of £20.246 million for management and support services assumed that savings from staff turnover and other housekeeping efficiencies would be achieved during the year in order that overall departmental expenditure could be contained within the budget. The original savings requirement was set at £603,000, which was equivalent to a saving of 3% of the overall net departmental budget for management and support services.

      6.2 The previous budget monitoring position, covering the period to the end of November 2003, identified savings to date of £283,000, meaning that further savings of £320,000 would need to be identified during the remainder of the year. However, in view of the likely funding pressures facing the department in 2004/05 for IT developments, due to mainframe system replacements, SAP implementation and continued e-Government developments, it was decided to seek further savings of £100,000 on management and support services during 2003/04. This sum could then be carried forward to 2004/05 to contribute towards the future funding of the IT developments.

      6.3 The 2003/04 revised budget therefore required savings totalling £420,000 to be identified during the remainder of the year. Although it was thought likely that some further incidental savings would emerge from staff vacancies, it was decided that it would also be necessary to restrict departmental expenditure by taking management action to strengthen control over the appointment of replacement staff and to implement a small delay in commissioning some work from external consultants until the new financial year.

      6.4 As mentioned above, a comprehensive review of all management and support services budgets has been carried out during January and February by departmental budget holders in order to produce revised outturn forecasts for all budget headings. As a result of the review, overall expenditure during 2003/04 on management and support services is forecast to be £20.108 million. This outcome means that further projected savings of £558,000 have been identified during this budget monitoring review, in comparison to the 2003/04 revised budget position reported in January, representing a forecast underspending of £138,000 against the cash limit.

      6.5 In summary, the main reasons for the increase in projected savings on the management and support services, compared to the 2003/04 revised budget, are as follows:

        · Salaries - additional savings of £252,000 are forecast from staff turnover and holding vacant posts

        · Consultants - projected underspending of £230,000, reflecting management decision to delay further commisions until 2004/05, together with projected savings against allocated sums

        · Feasibility studies - savings of £21,000 following revised assessment of costs to be capitalised

        · Income - additional projected income of £34,000 from planning application fees

        · Other minor variations - resulting in savings of £21,000

      6.6 With regard to the projected excess savings of £138,000 on management and support services, a decision has been taken, in consultation with the Executive Member - Environment, to allocate this sum to support additional expenditure on highways maintenance. This included additional expenditure on minor patching works in advance of carrying out the 2004/05 programme of surface dressing patching programme, which would otherwise need to be met from the new financial year's highways maintenance budget.

      7 Waste Management

      7.1 The waste management revenue budget is sub-divided into two separate categories for budget monitoring purposes:

        · The waste contract related budgets, covering the main waste disposal contract, trade waste income and recycling credits

        · The other non-contract related waste management services, covering facility maintenance, administration, promotions and developments, disposal of abandoned vehicles and provision for household waste recycling centre management.

      7.2 The current cash limit for the waste contract related budgets is £32.820 million, including the assessed third quarter call of £515,000 on the central waste management contingency. Overall, the budget now includes total allocations of £1.723 million from the central waste management contingency sum of £3.700 million, covering known variations on the waste contract related budgets during the first three quarters of the financial year. This left a sum of £1.977 million available within the contingency to meet any increases during the remainder of the year. Current indications are that there may be an outturn saving against the waste contingency of approximately £1.3 million, although this will be subject to confirmation when the 2003/04 final accounts are prepared.

      7.3 The reason for this large saving is directly related to a reduction in the levels of waste requiring disposal during 2003/04, whereas the assumption within the 2003/04 budget was that there would be an increase in waste volumes. As an illustration, waste volumes during the first nine months of the year were 2.5% lower than in the corresponding period in 2002/03, compared to an assumption in the budget that volumes would increase by 3.9%. Similarly, tonnage levels from household waste recycling centres has also decreased since last year by 4.7%, against budgeted growth of 4.4%, although this is partially due to increased levels of recycling being experienced. These reductions in disposal tonnages has contributed to a combined saving of over £1.1 million during the first nine months of the year, compared to the assumption included in the calculation of the waste management contingency.

      7.4 The 2003/04 budget for the non-contract related waste management services is £2.562 million, which is subject to normal budget management arrangements which require services' expenditure to be controlled within cash limits. The latest forecast for this service heading makes allowance for an additional provision of £26,000 which has been made available for facility maintenance, offset by equivalent savings on administration and promotions and development. The overall position on this division of service is expected to be in line with the cash limit at year end.

      8 Conclusion

      8.1 The report provides a summary of expenditure to date and the forecast outturn on the Environment Services revenue budget for 2003/04, based on the budget monitoring position at the end of February 2004. It shows that expenditure is being progressed in accordance with the revised budget for 2003/04 which was approved by the Executive Member - Environment during January.

      8.2 Projected savings of £558,000 have been identified on management and support services which more than covers the savings requirement of £420,000 included in the 2003/04 revised budget. The excess savings of £138,000 have been allocated to highways maintenance to enable a programme of patching work to be carried out in preparation for the 2004/05 surface dressing programme.

      8.3 Significant savings are expected to be made on the waste contract related budgets against the central contingency provision of £3.7 million as a result of lower than anticipated waste volumes.

      8.4 The overall budget monitoring position suggests that that final expenditure for the year on cash limited budgets, which will be reported after the 2003/04 final accounts have been closed, will be close to the revised budget cash limit.

      Recommendation

      1 That the latest 2003/04 revenue budget monitoring position be noted

      Section 100 D - Local Government Act 1972 - background papers

      The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

      NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the Act.

      TITLE FILE

        Environment Departmental Management Board : 17 February 2004 - Revenue Budget monitoring 2003/04 update

                      Appendix 1

    Environment

           
               

    Revenue budget 2003/04 - monitoring statement

       
               

    Analysis of variations

           
     

    2003/04

    cash

    limit

    Assessed expenditure to

    29 Feb 2004

     

    2003/04

    forecast outturn

    2003/04

    forecast variation

     

    £'000

    £'000

    %

    £'000

    £'000

    Highways and transportation

             
               

    Highways maintenance

    19,865

    18,029

    90.8

    20,003

    138

               

    Road safety education

    222

    169

    76.1

    222

    -

    School crossing patrols

    934

    811

    86.8

    934

    -

    Traffic surveys

    243

    240

    98.8

    243

    -

    Parking services

    -95

    -95

    100.0

    -95

    -

               

    Public transport support & co-ordination

    5,406

    4,930

    91.2

    5,406

    -

    Rural bus subsidy grant

    1,335

    1,228

    92.0

    1,335

    -

               

    Management and support services

    16,706

    16,030

    95.9

    16,712

    6

               
     

    44,616

    41,342

    92.7

    44,760

    144

               

    Planning services

             
               

    Development control

    685

    452

    66.0

    609

    -76

    Planning policy

    1,862

    1,638

    88.0

    1,807

    -55

    Environmental initiatives

    815

    852

    104.5

    802

    -13

    Economic development

    136

    124

    91.2

    138

    2

    Community development and other projects

    42

    36

    85.7

    40

    -2

               
     

    3,540

    3,102

    87.6

    3,396

    -144

               
               
               
               
     

    2003/04

    cash

    limit

    Assessed expenditure to

    29 Feb 2004

     

    2003/04

    forecast outturn

    2003/04

    forecast variation

     

    £'000

    £'000

    %

    £'000

    £'000

    Waste management

             
               

    Contract and related services

    32,820

    26,859

    81.8

    32,820

    -

    Direct managed services

    2,562

    1,971

    76.9

    2,562

    -

               
     

    35,382

    28,830

    81.5

    35,382

    -

               

    Other Services

             
               

    Reservoirs Act 1975

    24

    12

    50.0

    24

    -

    Chichester harbour conservancy

    119

    119

    100.0

    119

    -

               
     

    143

    131

    91.6

    143

    -

               
               

    Total

    83,681

    73,405

    87.7

    83,681

    -

               

Environment Appendix 2

Summary showing detailed allocation of highways maintenance budget

Revenue budget 2003/04

      Operational heading

      Approved programme

      as at

      31 December 2003

      Revised

      Programme

      as at

      29 February 2004

         
     

      £'000

      £'000

    Ordinary maintenance

       
         

      Routine carriageway and footways running repairs

      3,322

      3,561

      Gully cleaning

      978

      953

      A321 routine maintenance - payment to Surrey County Council

    6

      6

         

      Aids to movement

      1,282

      1,242

      Hazard clearance (road traffic accidents)

      318

      366

      Traffic management

      402

      436

      Sign renewals

      78

      78

      Traffic signal maintenance and modification

      617

      589

      Intelligent transport systems

      175

      200

      Urban traffic control

      70

      57

      Remote monitoring of traffic signals

      66

      82

      Rechargeable accident damage

      166

      166

         

      Grass cutting, trees and shrub maintenance

      1,517

      1,584

      Weed control

      551

      551

      Arboricultural

      446

      441

         

      District managed urban grass cutting

      468

      468

         

      Sub total - ordinary maintenance

      10,462

      10,780

         
         
         
         

      Operational heading

      Approved programme

      as at

      31 December 2003

      Revised

      Programme

      as at

      29 February 2004

         
     

      £'000

      £'000

    Street lighting and illuminated signs

       
         

      Energy - street lights

      1,449

      1,449

      Energy - signs and bollards

      93

      93

      Energy - traffic signals and crossings

    208

      208

         

      Maintenance contract - street lights

      2,520

      2,535

      Maintenance contract - signs and bollards

      952

      972

         

      Special replacement programme - works

      1,292

      1,292

      Special replacement programme - scheme design fees

      51

      51

         

      Sub total - street lighting and illuminated signs

      6,565

      6,600

         

    Bridges

       
         

      Routine maintenance

      98

      98

      Subway pumps - maintenance and energy

      43

      43

      Subway grafitti cleaning

      129

      129

      Railtrack charges

      68

      68

      Disused railway bridges

      9

      9

      Weight restriction signing

      6

      6

      Footbridges

      91

      91

      Monitoring of sub-standard bridges

      11

      11

         

      Sub total - bridges

      455

      455

         

    Other items

       
         

      Technical surveys

      277

      277

      Depots maintenance

      138

      138

      Highways maintenance IT system development

      306

      306

         

      General reserves - to meet unforeseen demands

      135

      -

      General reserves - inflation contingency

      -

      -

      General reserves - contractual claims

      -

      72

      Other reserves - A339 grant not yet allocated

      44

      -

         

      Previous year's accounting adjustment

      -16

      -113

         

      Sub total - other items

      884

      680

         
         

      Winter maintenance

      1,852

      1,852

         

      Operational heading

      Approved programme

      as at

      31 December 2003

      Revised

      Programme

      as at

      29 February 2004

         
     

      £'000

      £'000

    Income

       
         

      Depots net rental

      -138

      -149

      Rechargeable works

      -109

      -109

      Private street works interest from frontagers

      -6

      -6

      Allocation from commuted sums for soakaways maintenance

    -100

      -100

         

      Sub total - Income

      -353

      -364

         

      Total highway maintenance programme

      19,865

      20,003

         

    Reconciliation to revenue budget

       
         

      Approved 2003/04 revenue budget - February 2003

      19,141

      19,141

         

      A339 de-trunking - special Government grant

      374

      374

      Savings reallocated from capital maintenance

      350

      350

      Savings reallocated from management and support services

      -

      138

         

      Total 2003/04 highways maintenance revenue

      budget

      19,865

      20,003

       
         

Capital maintenance programme 2003/04

      Operational heading

      Approved programme

      as at

      31 December 2003

      Revised

      Programme

      as at

      29 February 2004

         
     

      £'000

      £'000

    Principal roads structural maintenance

       
         

      Carriageway, footway and drainage routine repairs

      766

      766

         

      Strengthening major maintenance schemes

      2,100

      2,100

      Special maintenance

      786

      693

      Resurfacing

      187

      175

         

      Surface dressing - high performance roads contract

      750

      750

         

      Design and supervision fees:

       

      - major maintenance schemes

      150

      150

      -special maintenance, resurfacing and surface dressing

      113

      103

      - routine maintenance

      8

      9

         

      Reserves

      152

      163

         

      Sub total - principal roads structural maintenance

      5,012

      4,909

       
         

    Non-principal roads structural maintenance

       
         

      Carriageway, footways and drainage routine repairs

      4,674

      5,064

         

      Surface dressing - High performance roads contract

      765

      765

      Surface dressing - minor roads contract

      1,032

      1,032

      Surface dressing - footways contract

      500

      500

         

      Special maintenance and recycling

      4,314

      4,271

         

      Tactile surfacing and pram crossings

      136

      136

      Resurfacing

      3,231

      2,989

      Blacktop testing

      30

      30

         

      Aggregates tax

      17

      17

         

      Design and supervision fees:

       

      - special maintenance, resurfacing and surface dressing

      707

      694

      - routine maintenance

      97

      108

         

      Reserves

      -

      -

         

      Sub total - non principal roads structural maintenance

      15,503

      15,606

       

      Operational heading

      Approved programme

      as at

      31 December 2003

      Revised

      Programme

      as at

      29 February 2004

         
     

      £'000

      £'000

    Non-principal roads structural maintenance - additional programme of £3.5m

       
         

      Footways special maintenance schemes

      1,785

      1,785

      Carriageway haunch repairs, resurfacing and recycling

      892

      892

      Footways surface dressing

      474

      474

      Patching

      124

      124

      Fees

      225

      225

         

      Sub total - non-principal roads structural maintenance

      3,500

      3,500

       
         

    Bridges

       
         

      Strengthening schemes

      1,438

      1,438

      Assessments, studies and feasibility

      450

      450

      Structural maintenance

      1,150

      1,150

         

      Sub total - bridges structural maintenance

      3,038

      3,038

       
         

      Total capital maintenance allocations

      27,053

      27,053

         

      Reconciliation to capital programme

       
         

      Schemes supported from local resources:

       

      Structural maintenance of non-principal roads

      11,068

      11,068

      Additional provision for repairs to local roads

      and footways

      3,500

      3,500

      Net underspendings brought forward from 2002/03

      129

      129

      Savings transferred to revenue maintenance budget

      -350

      -350

         

      Schemes supported by Government borrowing

      approvals

      12,706

      12,706

         

      Total 2003/04 capital maintenance programme limit

      27,053

      27,053