Hampshire County Council Item 14 Executive Member - Education 13 May 2004 Major Projects Status report Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 email: [email protected]
|
|
|
|
|
|
1 |
Summary |
|
|
|
The following decisions are sought: |
|
|
1.1 |
That approval be given to the schemes being undertaken at various secondary schools under the NDS Modernisation 2004/05 Schools Specialist Accommodation, in particular the scheme at Bridgemary Community School at a value of £341,723, excluding fees. |
1.2 |
That approval be given to the scheme at Sharps Copse Primary School to provide a Children's Centre, subject to the agreement of funding arrangements detailed in the County Education Officer's Capital Programme Update report elsewhere on the agenda. |
2 |
Reason(s) |
|
|
2.1 |
To provide enhanced science laboratory, food technology and textile laboratory accommodation at various secondary schools |
|
|
2.2 |
This decision supports Aims 1 and 5 of the Corporate Strategy by providing improved school facilities which will benefit the school and its users. |
|
|
3 |
Other options considered and rejected |
|
|
3.1 |
The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost-effective way of meeting that need. |
|
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
|
|
4.1 |
Not applicable |
|
|
5 |
Dispensation granted by the Standards Committee |
|
|
5.1 |
Not applicable |
|
|
6 |
Reason(s) for the matter being dealt with if urgent |
|
|
6.1 |
Not applicable |
|
|
|
|
|